|
Canada's Rock to Road Magazine
November-December
2003 Issue
For a copy
of the issue that contains these articles with colour photos, click
here.
New
equipment promises high productivity, low cost for West Coast aggregate
producer
By Andy Bateman, Engineering
Editor
Mobile equipment changes
at a major B.C. aggregate producer's operations promise to diliver high
productivity at low cost.
Vancouver-based
Construction Aggregates Ltd. (CAL) recently took delivery of seven new
pieces of equipment including four wheel loaders, two ADT trucks, and
an excavator for their Lower Mainland and Sechelt B.C. operations. Sechelt
will be a familiar name to Aggregates & Roadbuilding's readers, having
occupied the top spot in our annual survey of the country's Top 20 Sand
& Gravel operations for a number of years, reporting over 3 million
tonnes of production for 2002.
At Sechelt, mine manager Gordon Doerksen reports
that two Komatsu WA700-3 wheel loaders and a Komatsu PC1250LC-7 excavator
went into service this year. The first WA700 arrived this spring and
was joined in September by the second WA700 and the PC1250. Working
exclusively at Sechelt, all three units have manufacturer's extended
warranties as well as "not to exceed" full maintenance packages. The
PC1250's main duty is the excavation of overburden and sand and gravel,
where it is teamed with Caterpillar 773 and Terex TR-70 haul trucks.
The WA700s are engaged in stockpile pushing and pulling as well as material
extraction.
Key factors cited by Doerksen in the purchase
of these new machines include lowest long-term cost per tonne, the manufacturer's
commitment for a full-time site service person, a machine availability
guarantee and favourable reports from existing owners. Doerksen also
underscores the importance of operator input, noting that two operators
completed trials with these machines before purchase, including a comparative
performance test against a shortlist of competitor's machines. With
its expected life of 6 years, Doerksen reports that the PC1250 excavator
is delivering a 50 per cent increase in capacity from 4 to a potential
6 million tonnes/year. In terms of average production rate, the new
excavator has reduced truck loading time by up to 33 per cent, from
1.5 minutes to as low as 1 minute.
At the company's Port Coquitlam quarry operation
near Vancouver, two Komatsu HM300-1 articulated dump trucks (ADT's)
went into service in mid-August of this year while two Komatsu WA500-3
wheel loaders went to work at CAL's North Vancouver and Langley depots.
Dennis Baker, CAL's operations manager for the Lower Mainland & Gilley's
Quarry, explains that both trucks and one of the loaders are on rental
purchase whereas the second loader has been purchased. These are all
stock units, with the trucks typically carrying feed to the quarry's
rip-rap plant, and also loading 4500-tonne capacity barges when required.
Duties for the loaders include truck loadout and barge unloading. Baker
reports that the units are delivering excellent performance, are operator
friendly and have increased overall capacity by about 20 per cent, adding
that it is too early to comment on their operating costs.
Manufacturer's specification data on these
new machines indicates that the PC1250LC-7 excavator has an operating
weight of 113.2 tonnes and a rated bucket capacity range of 3.4 m3 to
5.2 m3. This excavator is one of the Komatsu's Dash-7 Series machines
which are claimed to offer high production and low fuel consumption.
These models are equipped with three working modes - A, E and B mode
for active, economy and breaker operation, respectively. CAL's particular
machine is fitted with a number of options, including extra lights,
autolube systems, a modified windshield and a fire suppression system.
Data on the WA700-3 wheel loaders indicates
a rated bucket capacity, when equipped with a general purpose bucket
(straight edge) without tip teeth, of 9.4 m3 heaped and 8.2 m3 struck,
delivering a breakout force of 62 400 kg. For the WA500-3, rated bucket
capacity, fitted with a general purpose bucket with bolt on cutting
edge, without tip teeth, is 5.0 m3 heaped and 4.3 m3 struck, delivering
a breakout force of 23 700 kg.
Turning to the HM300-1 ADTs, these machines
have a maximum rated payload of 27.3 tonnes and a heaped body capacity
of 16.6 m3. High productivity is claimed from performance numbers such
as a maximum travel speed of 59.0 kph (36.7 mph) and a minimum turning
radius of 7.96 m.
Overall, the new machines are meeting both
managers' expectations to date. Aggregates and Roadbuilding will report
their views on the machines longer term performance in a future edition.
Construction Aggregates Ltd. is part of the North American Lehigh Group
and worldwide Heidelberg Cement group.
Back to
top
Superpave
aggregates go the distance
By Andy Bateman,
Engineering Editor
With the increasing
use of Superpave asphalt mixes and tight supply, quality aggregates
are travelling further than ever before in southern Ontario. This article
describes how one custom crushing contractor met specifications for
a Superpave surface mix aggregate used in several distant roadbuilding
projects.
Both
granite and sand and gravel are extracted from the Aspdin Rd. operation
of W. Robert Hutcheson Sand & Gravel Ltd. near Huntsville, Ont. Crushing
contractor J.G. Stewart Construction Ltd. has been there three years
a row and focussed this year on maximizing production of HL1 sized (13.2
mm x 4.75 mm) Superpave granite aggregate for Dufferin Aggregates. Dufferin
has been successfully marketing HL1 stone and Dense Friction Course
(DFC) aggregates south of Barrie through a distribution arrangement
with Hutcheson, with the result that these products are being trucked
as far the Niagara Region, nearly 400 km from the quarry.
Aggregate processing began at the quarry's
rock face, where two of Stewart's wheel loaders, Caterpillar 988B and
988F models, hauled shot rock from the 18.3 m high granite face at a
rate of 360 tonnes/h to the primary, a 37x49 Nordberg C125 jaw crusher.
The jaw reduced the 600 mm minus feed to 150 mm minus and was fitted
with a BTI TB-725X breaker to deal with any oversize. From there, two
914 mm x 30.5 m long Riverwood transfer conveyors and a 914 mm x 76.25
m Riverwood field conveyor carried material to the secondary plant,
discharging into a 30-tonne capacity metering bin. The bin regulated
flow onto a 6x16 Cedarapids ElJay double-deck screen fitted with 32
mm and 22 mm screen cloths. Here, 150 mm x 32 mm oversize material continued
forward for further processing, while 32 mm x 22 mm clear drainage stone
and Granular A base sizes were drawn off and stockpiled. The oversize
first passed through a Cedarapids 1372 mm (54-in) Rollercone, set at
a closed side setting (CSS) of 38 mm before being conveyed to a 8x20
Cedarapids triple-deck inclined screen fitted with 32 mm (top), 15.9
mm and14.3 mm (middle) and 6.3 mm (bottom) screen cloths. All 14.3 mm
plus material retained on the screen's top and middle decks was conveyed
to a Nordberg HP 400 cone for further reduction, while HL1 product continued
forward and 6.3 mm minus screenings were stockpiled separately. Plant
foreman Alvin Lamb puts the plant total throughput rate with this set
up at 360 tonnes/h, an impressive number bearing in mind that all of
the granite feed was reduced to 19 mm or smaller sizes. Out of this
total, Lamb estimated the product split at 35 per cent HL1 together
with 35 per cent screenings, 25 per cent granular A and 5 per cent drainage
stone.
In many set ups, the secondary screen would
mark the end of the material processing. Here however, Stewart refined
the process by a number of additional steps, including a finishing screen
to remove residual fines from the HL1.
The 5x16 Dillon double-deck finishing screen
was fitted with 14.3 mm and 6.3 mm screen cloths, with the 14.3 mm cloths
dispersing the material flow and the 6.3 mm cloths completing the fines
separation. As an added refinement, HL1 product from the Dillon screen
was stockpiled by a Thor 914 mm x 41.9 m programmable stacker to minimise
segregation. Finally, 6.3 mm minus screenings from this screen (and
also occasionally from the Cedarapids screen) were subdivided into 6.3
mm by 3.2 mm chip and 3.2 mm minus fractions so that some of the chip
fraction could be separately shipped and metered into Superpave asphalt
mixes.
According
to Stewart president John Stewart, this set up is just one example of
company's track record on Superpave aggregate production. "This year
alone, we have successfully met Superpave specifications in a number
of locations, utilising both hard rock and gravel sources. We have found
that some initial experimentation with our portable spread set ups,
followed by good production practice has normally delivered the required
result."
|
Specialty
sports sands hot commodity for Ontario producer
Bob
Hutcheson founded Hutcheson Sand and Gravel some 30 years ago.
The Aspdin Road property, near Huntsville Ont., was originally
a Christmas tree farm, and although the business was successful,
Hutcheson had to give up the business because of an allergic reaction
to the trees.
While looking for alternative business
opportunities, it was discovered that a high-quality aggregate
deposit existed underneath the Christmas tree farm. The deposit
contains both granite and weathered granitic sand.
Hutcheson Sand and Gravel Ltd. operated
the Aspdin property as a typical aggregate operation until the
mid 1980s. It was at that time that research began into developing
products for the turfgrass industry, focusing on golf course applications.
Speciality mixes containing varying proportions of sand, peat,
topsoil, and compost were developed and computerized mix quantities
are tailored to specific applications. The sand particles in the
Aspdin deposit have naturally fractured surfaces with minimal
surface rounding. No crushing takes place although nearly all
of the sand products are washed, classified and sized to exceed
tight USGA specifications.
From these beginnings the company has
developed over 60 products for golf greens and playing fields.
Hutcheson Sand & Mixes is the marketing division of Muskoka Minerals
and Mining Inc. Most Hutcheson products are produced in Ontario
from the Huntsville and Ottawa bases. Elsewhere, local sources
are used where possible.
A mobile blending service was added in
the early 1990s. The blender units, consisting of several product
feed bins, a screening plant, and a control unit. The product
bins deliver sand and organic source material through electronically
controlled metering augers at a capacity of over 180 tonnes/h
to an accuracy of within 1 per cent. Early experiments with belt
feeders under the bins revealed that the auger feed system was
essential to obtain the required blending accuracy.
The business grew, first across Ontario
and Quebec, later expanding to include all of Canada as well as
the northeast U.S. Hutcheson's joint venture partner in British
Columbia is OCL Industrial Materials Ltd.
The company's expertise gained through
golf course applications became the springboard for the development
of other speciality sport sands, most notable in the fast growing
sport of volleyball. Characteristics of a suitable volleyball
sand are very different to most of the golf course applications
with rounded particles, quick backfilling properties to maintain
a level surface, and fast draining in case of wet weather. Hutcheson
is the acknowledged international consultant company for the f³d³ration
internationale de volleyball (FIVB) for volleyball sand designs
around the world. An impressive list of credits includes sand
design for the volleyball events at the 2000 Sydney Olympic Games
held on the world famous Bondi Beach, while this year's events
include Marseille, France, first Grand Slam stop on the 2002 FIVB
Beach Volleyball World Tour, and Cadiz in Spain.
Ted Hutcheson, president and CEO of Muskoka
Minerals and Mining Inc. emphasised that the two key aspects for
the successful developments of these speciality sport mixes are
the availability of suitable raw material combined with the company's
expertise acquired in over 15 years of product development.
In terms of raw materials, few Canadian
deposits reportedly have the necessary characteristics. Equally
important, Hutcheson's team, many of whom have been here since
the tree farming days, have acquired a wealth of knowledge in
the development and marketing of products for the speciality sports
sand market, enabling the company to achieve international recognition
it enjoys today.
|
Back to
top
Concrete
road paver heads east for big job
By Andy Bateman, Engineering
Editor
Making
its first appearance in the Maritimes, a concrete road paver has played
a key role in the upgrading of Nova Scotia's Highway 101. Andy Bateman
reports...
Concrete
won out over asphalt for a major highway paving project in Nova Scotia
based on life cycle costing by the winning bidder. Project number 2003-030
was awarded by the Nova Scotia Department of Transport and Public Works
(TPW) for one section of Highway 101 in Hants County between Halifax
and the Annapolis Valley. Extending 10.9 km, work involved the construction
of two new lanes and shoulders for eastbound traffic, together with
the removal of existing climbing lanes on the westbound lanes. Bidders
had the option of submitting bids based on Alternate 1, Gravelling and
Portland Cement Concrete Paving or Alternate 2, Gravelling and Asphalt
Concrete. The aggregate amounts submitted for the asphalt alternate
were then increased by $1,500,000 in accordance with the project tender
documents.
St. Lawrence Cement Inc. submitted the winning
bid of $5, 911,460 utilising the concrete alternate. Project manager
Jean-François Côté explains that the ability of
the company's concrete paver to complete the paving operation in a single
pass was critical to the bid's aggressive 3-week paving schedule. Côté
adds that the bid package also drew extensively on the area's workforce
with local contractor Alva Construction Ltd., for instance, responsible
for all earthmoving, base material crushing, placement and fine grading
as well as the installation of nearly 6 km of guardrail.
In cross section, the pavement foundation utilizes
two coarse graded base materials to both support the concrete and facilitate
drainage; gravel Type 2 (102 mm minus) sub-base material and a 100 mm
lift of Type 1 (20 mm minus) granular base material for Portland Cement
concrete. The concrete pavement itself is 10.6 m wide, consisting of
two lanes each 3.7 m wide, together with a 2.0 m wide tied concrete
shoulder to the right lane and a 1.2 m wide integral shoulder for the
left lane. At 240 mm, the concrete thickness under the right lane is
20 mm more than the left lane in recognition of the right lane's heavier
truck loading.
Base aggregate tender quantities included 25
000 tonnes of Type 2 granular sub-base and 40 000 tonnes of Type 1 granular
base, as well as 25 000 tonnes of gravel type 1S shoulder material adjacent
to the concrete. The pavement contains some 27 000 m3 of concrete, based
on its surface area of 116 000 m2 and 230 mm average thickness.
Preparatory work included the fine grading
of the base material to ensure a level surface for concrete paving operations.
Initially completed some 3 km ahead of the paver, the fine grading was
later reduced to about 500 m ahead in steady running conditions to provide
a smooth surface for paving. As a further precaution, one of the compactors
was stationed ahead of the paving train to iron out any small grooves
left by concrete delivery truck.
At the heart of the concrete paving operation
was Dufferin Construction's Guntert & Zimmerman S-1500 paver. This multi-function
unit formed and consolidated the concrete to the required slope, inserted
dowel bars for the pavement's transverse joints and provided initial
surface finishing. During paving operations, concrete was dumped in
front of the S-1500 by a fleet of up to 15 open tandem trucks and distributed
evenly across the base material by the paver's frontal spreader. The
concrete was then formed into a continuous slab by the paver's vibrating
screed. Behind the screed, the on-board dowel bar system then inserted
24 greased dowel bars horizontally into the surface of the fresh concrete
from above, repeating the process every 5 m at each transverse joint.
Following insertion, the position of each joint was marked for later
joint cutting. The surface concrete then received a multi-stage finishing
process that included both mechanical and hand finishing. Behind the
dowel bar inserter, a sheet of wet burlap and the 1500's rotating bull
float provide initial smoothing, followed by Dufferin's crew who hand
finished both the surface and the edges of the slab. Towed some distance
behind the paver, a travelling Bidwell workbench straddled the concrete,
allowing the crew to access the central area of the slab to complete
any necessary hand finishing. A second sheet of burlap, dragged behind
the workbench, then added longitudinal texture to the concrete surface.
|
Highway
101 - Concrete mix design
|
| Material |
|
| Type
10 cement |
360
kg/m3
|
| Gateway
Material 5 by 20 mm granite |
736
kg/m3
|
| Gateway
Material 20 by 40 mm granite |
458
kg/m3
|
| V.J.
Rice fine aggregate (Sand) |
635
kg/m3
|
| Admixtures |
|
| Master
Builders Pozzolith 200N Water Reducer |
385
l
|
| Master
Builders Micro Air Entrainment |
End
result 4 @ 7% on fresh concrete
|
| The concrete is batched to a low
slump of 40 mm |
The last major piece of equipment in the paving train was the dual purpose
Guntert & Zimmerman TC 600 texture and curing machine. During its first
pass over the concrete, its tines cut fine transverse grooves in the
fresh concrete surface in order to provide optimum skid resistance.
The TC 600 then made a second pass to and applied of Meadows curing
compound to seal the surface.
Concrete was produced by a dedicated Rexcon
drum mix concrete plant, set up near the mid-point of the job. This
is the company's biggest portable plant, with an individual batch capacity
of 8 m3 and hourly production capacity of up to 300 m3. From there concrete
was delivered to the paver by a fleet of up to 15 open tandem trucks.
Overall, Côté reports an average system production rate
of 1800 to 2200 m3/day for the project. Equally important, the system
delivered pavement smoothness of 12 mm/100 m (120 mm/km) compared to
a specified limit of 240 mm/km.
Côté emphasises that close attention
has been paid to joint design on this contract to deliver joint durability
of up to 15 years. For transverse joints, a 3 mm relief cut is made
between 8 and 12 hours after concrete placement. Fourteen days later,
a larger cut is made using a ride-on saw to ensure that the tight dimension
tolerances of the joint slot are met. The saw cut then receives a high
volume pressure wash, followed by sandblasting to roughen the vertical
sides and remove any residual dust. Preformed neoprene is then inserted
into the joint after lubrication with a small quantity of adhesive.
Joint integrity is maintained by using a single continuous piece of
neoprene across the full pavement width to avoid any neoprene joints.
Côté adds that, unlike conventional transverse joints where
the poured sealer is stretched between the concrete sidewalls of the
joint, the neoprene joint material remains in compression to provide
long-term joint flexibility. The longitudinal relief cut is completed
in a similar manner to the transverse cut and also enlarged 14 days
later. In this case the cut is enlarged by a conventional walk-behind
saw and hot bituminous sealer is poured into the longitudinal joints
once nearby transverse joints have been completed.
Support mobile equipment included Alva Construction's
fine grading fleet of two graders, two water trucks and three compactors.
Alva utilised Caterpillar 14G and 140G machines, while the compactor
fleet consisted of SuperPac 840, Ingersoll-Rand Pro-Pac 100 and Caterpillar
CS-563D machines. Also ahead of the paver, a bucket equipped Caterpillar
IT28G was kept on standby to move dumped concrete if required. Material
sources for the contract included two wayside granite quarries for all
base materials, while non-reactive concrete aggregates were supplied
by Gateway Materials Ltd. (two sizes of coarse aggregate) and V. J.
Rice Concrete Ltd. (fine aggregate).
Demix Construction and Dufferin Construction
are business units of St. Lawrence Cement Inc. Demix Construction managed
the project, while Dufferin Construction completed concrete paving.
|
Life
cycle costing gives edge to concrete
Tom
Gouthro, Manager of Technical Services in Nova Scotia's Department
of Transportation and Public Works (TPW), explains that the $1.5
million premium on asphalt bids for this contract was added to
allow for a fair comparison of asphalt and concrete bids, reflecting
the expected durability and increased service life of a concrete
pavement. "There are two pre-existing sections of concrete road
in the province and a study on the TCH 104 section in Oxford,
carried out over a five year period following construction, yielded
favourable performance results. For the just completed Highway
101 contract, we adopted the generally accepted industry view
that the increased durability of a concrete pavement would warrant
an increased cost of between 20 per cent and 30 per cent on initial
construction. Specifically, we included a clause in the contract
documents, stating that we would add $1.5 million or 20 per cent
of the bid price to the low asphalt bid, whichever was the greater
figure."
|
Back to
top
Expanded
asphalt with HMA overlay protects road assets for Ontario city
By Andy Bateman, Engineering
Editor
Grader-laid
expanded asphalt is proving to be a cost effective pavement rehabilitation
method for the City of Burlington as well as an integral part of the
city's asset management program.
Dave Youkhana, Quality Control Coordinator
in the Design and Construction Section of Burlington's Engineering Department,
explains, "Our challenge is to maintain the city's extensive and rapidly
growing road network on a limited maintenance budget. We have found
that an expanded asphalt base combined with a hot mix asphalt surface
overlay provides a cost effective pavement rehabilitation method.
"At the same time, we recognise the environmental
benefits of a process that reuses existing road material and thereby
minimizes the use of virgin material." On a recently completed project,
for instance, over 30,000 m2 of pavement was rehabilitated by this method
in a mature residential suburb known as Birdland. Here, the condition
of several streets had deteriorated in recent years, despite relatively
low traffic volumes and a number of surface repair treatments, including
straight hot mix overlay, tar and chip, patch repair and crack sealing.
(See sidebar on City of Burlington Asset Management.)
Expanded asphalt stabilization work on the
Birdland contract was completed by Hard Rock Pavement Recycling Inc.
of Port Colborne, Ont. Ron Carleton, Hard Rock's expanded asphalt supervisor,
explains that the stabilization process was completed in two stages.
During stage one, the existing pavement was pulverized, compacted and
graded in preparation for expanded asphalt stabilization. In stage two,
a portion of the prepared surface was then remixed with expanded asphalt
cement, spread by grader and compacted to produce a stable expanded
asphalt base. Specifications here called for an expanded asphalt thickness
of 150 mm, with any material sized above 50 mm to be removed from the
surface of the expanded asphalt mix during stage two of the operation.
Leading off stage one were Hard Rock's two
pulverizers, CMI RS-650 and RS-800 units. Each machine pulverized 50-75
mm of old asphalt together with 75-100 mm of underlying granular base
material to produce a homogenous mixture. In some locations, a specified
quantity of supplemental virgin aggregate was applied to the existing
road in advance to ensure that the pulverized mixture met the required
gradation. Behind each pulverizer, a water truck provided a light water
spray to assist in compaction and minimize the pick-up of loose material.
(Carleton notes that higher volumes of water are often necessary to
reach the specified moisture content, in which case the pulverizer pushes
a water truck). After water spraying, a heavy pneumatic roller was used
to compact the pulverized mixture and provide a temporary running surface
for traffic during construction. The surface was then fine graded to
ensure a good match with adjacent driveways and utilities after final
resurfacing. Behind the grader, rubber and dual steel drum compactors
provided further compaction up to a Bulk Relative Density (BRD) of 2.15
tonnes/m3.
For stage two, the larger of the two pulverizers,
the RS-800, went into action again, this time connected to a 40 tonne
capacity tanker containing Petro-Canada 58-28 PGAC asphalt cement at
190ÁC. Cold water was then injected into the hot asphalt cement in the
RS-800's reaction chamber at a rate of 2 per cent of the mass of asphalt
cement. The resulting asphalt cement froth was then metered into the
drum of the pulverizer at a rate of 3 per cent of the mass of the reclaimed
asphalt pavement (RAP) and granular mixture.
The expanded asphalt froth and recycled material
were mixed and blended in the pulverizer drum and discharged at the
rear of the machine. The expanded asphalt base then received a light
water spray before compaction by the dual steel drum and pneumatic machines.
Stage two was wrapped up by further fine grading and compaction with
the pneumatic compactor and dual steel drum roller to achieve a smooth
matching surface with a specified density of 97 per cent of the BRD
of the mix.
In terms of strength, the expanded asphalt
base has a Granular Base Equivalency (GBE) of between 1.6 and 1.8, compared
to 1.0 for granular base and 2.0 for hot mix asphalt. Hard Rock's Brian
Mountjoy adds, "The pneumatic roller is generally used prior to final
compaction with the steel drum machine. We believe this sequence provides
an opportunity for the rubber tires to knead the material at greater
depths prior to the steel drum roller smoothing the surface and creating
any "bridging" of the mixture. If the total liquid content is in the
range of 8 per cent there is sufficient liquid to provide lubrication
to achieve optimum compaction. The mixture does not require time to
"cure", however this total liquid content of 8 per cent may create a
mixture which is tender. Given 24 hours without precipitation, the mixture
will stabilize sufficiently to allow for a hot mix overlay."
Hard Rock's grading and compaction fleet, all
Caterpillar units, included a 140G grader, CS-433C single drum and CB-634C
dual drum steel compactors as well as a PS-300B pneumatic compactor.
On this contract, Burlington-based general contractor King Paving Ltd.
applied the 50 mm lift of HL3 surface asphalt.
|
City
of Burlington Infrastructure Asset Management System
Italo
Di Pietro, Senior Coordinator, Infrastructure Management for the
City of Burlington's Engineering Department, explains that Burlington
developed a system in 1998 to summarise the condition of all the
city's roads, storm sewers, sanitary sewers and water mains within
a single integrated database.
Known as the Burlington Road Management
System, the system is said to be effective in looking at all the
potential reconstruction or repair needs on a given road, enabling
the City's engineering department to quickly assess and decide
on the co-ordinated rehabilitation for all the elements in the
road right-of-way.
Overall the City's Roads Assets group,
including pavements, storm sewers and bridges, constitutes over
80 per cent of the City of Burlington's "hard assets", with a
total estimated replacement value of some $770 million. This figure
includes $400 million for Burlington's 686 lineal km (1550 lane
km) of roads, $220 million for 500 km of underground storm sewer
pipe and 12,000 catch basins, together with $150 million for 125
major bridges and culverts.
For
the City's Engineering Department, the creation of the Road Management
System was a natural evolution of the asset management systems
that were already in place. Twelve years earlier, in 1986, Burlington
was one of the first municipalities in Canada to implement a Pavement
Management System. This was followed in 1990 by the creation of
two full time positions dedicated to Roads Assets Infrastructure
Management and Capital Budgeting. In 1992 the city was recognised
by the Ontario Good Roads Association (OGRA) for effective use
of the Pavement Management System. Two years later, in 1994, the
city created its "Local Roads Reconstruction Priority Rating"
system that was also recognised by an OGRA award. The system and
data collection has been updated several times since 1986, with
the most recent system upgrade and data collection completed in
2002.
For the city's storm sewers, a digital
condition rating system, originally developed by Region of Halton
staff, was adopted by Burlington in 1996. In a public/private
partnership, the city began a program of video inspection and
digitizing of the entire system, enabling a ranking of sewer condition
to be developed. Closed Circuit Television (CCTV) video inspections
are completed annually for rehabilitation projects and maintenance
needs. The most recent upgrade of the storm sewer system, completed
in 2002, is Web based and allows information and videos to be
accessed via the Internet.
Finally, also in 2002, the city completed
a further upgrade of its Bridges and Culverts system when it adopted
the provincial Ministry of Transportation's new Bridge Management
System (BMS).
|
Back to
top
Roadbuilding
job compares in-place asphalt recycling techniques
By Andy Bateman, Engineering
Editor
A recent
roadbuilding job awarded by the Ontario Ministry of Transportation provides
a rare opportunity to compare the long term performance of cold-in-place
recycling with paver laid expanded asphalt.
Valued at $4.35 million, MTO contract 2002-4040 involved grading, drainage,
granular base and hot mix paving on a 15.1 km section of Highway 7 east
of the Town of Perth, beginning at the municipality's eastern limit.
As originally envisaged, the job included a 50 mm lift of HL1 surface
asphalt laid directly on a 110 mm lift of cold-in-place recycled (CIR)
material. Later, a change proposal resulted in a 5 km experimental section
at the west end of the job being completed instead with 110 mm of expanded
asphalt, while the eastern 8 km section was completed with CIR as originally
planned.
Each in-place recycling method has been applied
to the same depth, in both travel directions and both sections received
a 50 mm lift of HL1 hot mix surface asphalt. In addition, both contractors
involved in the recycling work brought extensive experience to the job:
Miller Paving Ltd. completed the CIR section, while Roto-Mill Services
Ltd. (part owned by Aecon Construction and Materials) completed the
expanded asphalt section. Aecon then completed the HL1 surfacing on
both sections. Shoulders, passing lanes and intersections received more
conventional treatment consisting of granular A base material followed
by two lifts of medium duty binder mix, 50 mm and 40 mm, and the HL1
surface mix.
In Miller Paving's cold-in-place recycling
train, a CMI PR-1000 pavement profiler pushed an emulsion tanker while
simultaneously milling 110 mm of existing asphalt. Milled material was
then conveyed to the towed United Machinery mobile crushing and screening
unit where all the material is reduced to minus 38 mm. From there, the
sized material was transferred to a towed Midland 800 Mix-Paver where
it was mixed with conventional polymer modified asphalt emulsion, pumped
directly from the tanker to the paver's self-contained pugmill. The
recycled mix was also laid down by the Mix-Paver, utilising its standard
paving screed and electronic controls. The material was laid to a depth
of 100 mm as the driving lane was slightly widened from 3.5 m to 3.75
m. Behind the paver, a Dynapac 302 single-drum vibratory compactor and
a Dynapac CP 271 pneumatic roller compacted the recycled mix. The average
production rate of this train was 200 to 300 tonnes/h, depending on
the local profile correction.
For the expanded asphalt section, Roto-Mill
utilised its paver laid expanded asphalt recycling train. This train
included the Roto-Cycler, an integrated portable unit that both processed
recycled aggregate and produced expanded asphalt. (See Aggregates &
Roadbuilding, September/October 2002 edition for additional information).
The expanded asphalt was then laid to the required width and depth by
a paver travelling directly behind the Roto-Cycler. In a change from
last year, Roto-Mill teamed the Roto-Cycler with a new European-built
Vùgele Super 2100 paver having, according to manufacturer's data, a
laydown rate of up to 1000 tonnes/h. Roto-Mill's paver is fitted with
an extending screed that incorporates a tamper and two pressure bars
and has a maximum rated mat width capability of 9 m. According to Dan
Hanley, Roto-Mill's Marketing & Product Development manager, the switch
helped the company Roto-Mill complete the expanded asphalt portion of
the job in three days. "Paving productivity has increased by up to 30
per cent in ideal conditions on this and other partial depth projects,
while productivity has increased by 20 per cent on average for all depths.
The paver delivers very high initial compaction immediately behind the
screed, thereby eliminating the need for the fourth and the sometimes
the third pass with the breakdown roller on some partial depth projects.
Not only that, there is reduced secondary finishing and rubber tire
roller time as well."
Aecon Construction and Materials completed
a 50 mm HL1 surface lift on both the CIR and paver laid expanded asphalt
sections of the Highway 7 contract. Aecon's paving train included a
Roadtec SB-2500 Shuttle Buggy, Caterpillar AP 1000B paver and Caterpillar
PS 300B pneumatic compactor. Aecon superintendent Pat Goody reports
that the weather played a key role when it came to final surface paving
of the respective sections. On the expanded asphalt section, HL1 could
be paved within 2-3 days after the expanded asphalt train has passed
through. By comparison, it was sometimes a challenge to meet all job
requirements on the CIR section during one wet spell. These requirements
included a minimum 14-day exposed period for curing and a moisture content
of 2 per cent or less, as well as completion of HL1 paving within 30
days. Fortunately, several days of continuous hot dry weather provided
the necessary drying for HL1 paving to proceed.
In general, proponents of expanded asphalt
note that the finished mat of expanded asphalt requires typically only
24 hours of curing and can be paved immediately with the final surface
lift of hot mix or other surface treatment applications. However, as
Miller vice president Stephen Damp points out, "There are now at least
two manufacturers who are producing fast curing emulsions for cold in
place recycling. As a result, the traditional 7-14 day curing period
is being reduced to 4-7 days, much closer to the expanded asphalt process
curing."
Either way, CIR and expanded asphalt are both
well proven-pavement rehabilitation methods whose construction phase
represents only a small percentage of the pavement's expected service
life. As to the actual service life for each method on this particular
contract, time will tell.
|
What
is the difference between cold-in-place recycling
and expanded asphalt?
The
principal difference between cold-in-place recycling (CIR) and
expanded asphalt is the method by which asphalt cement is mixed
with cold recycled material. The CIR process normally utilises
a conventional asphalt cement emulsion that is often modified
with the addition of a polymer. Expanded asphalt, on the other
hand, utilises the expanded (foamed) asphalt cement that results
from the reaction between hot asphalt cement and a controlled
amount of cold water. Both processes can be enhanced by the addition
of additives such as Portland cement to facilitate strength gain
and resistance to moisture damage.
Many of the benefits of in-place recycling,
such as the savings in energy and non-renewable crude oil and
granular materials, are well known and shared by both methods.
What is less well known is the difference in expected service
life of each method in a similar application. The Asphalt Recycling
and Reclaiming Association's respected Basic Recycling Manual,
for instance, puts the expected life of CIR with a hot mix asphalt
overlay in the range of 7-15 years. However, no equivalent number
for paver-laid expanded asphalt is offered, as this method arrived
on the recycling scene after the manual's 2001 publication date.
|
Back to
top
November/December
2003 issue
Aggregates
and Roadbuilding Magazine
4999 St Catherine Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca
|