|

Canada's "Rock to Road" Magazine

All crushing and
screening equipment at the secondary plant is
enclosed to reduce sound levels. The enclosure panels,
manufactured by Norseman Inc. consist of two layers of
industrial grade vinyl with integral sound absorbing material.
By
Andy Bateman, Engineering Editor
Extensive
sound reduction measures and active community involvement are just two
of the ways in which Calgary-based aggregate producer Burnco Rock Products
Ltd. is setting the standard for fostering good community relations.
At its main Indus pit south-east of Calgary,
Burnco has taken the unusual step of enclosing both the primary and
secondary portable processing plants to reduce noise emissions. Completed
in 1997, this initiative is part of an impressive list of environmental
protection measures that includes separate dewatering and wash water
circuits, sequential overburden stripping and permanent sound level
monitoring stations. On top of these, community relations initiatives
include a number of voluntary financial contributions to the local community,
access road paving and charter membership in a central truck registry
system.
The
primary crusher is fully enclosed by a purpose built precast concrete
building to reduce noise. Sound insulation attached to the hopper canopy
absorbs sound from discharging trucks.
Kim Titus, manager of Burnco's Aggregate Division,
explains that the original purpose of the distinctive plant enclosures
was to reduce sound levels at the operation's closest neighbours, located
some 800 m from the processing plant. The pit's primary crusher is fully
enclosed in a purpose-built precast concrete building, while the secondary
plant is enclosed by panels consisting of two layers of industrial grade
vinyl with integral sound absorbing material. In practice, it was found
that these measures not only delivered the required noise reduction,
but also significantly reduced fugitive dust emissions. Building on
this successful experiment, Burnco's three other portable spreads are
now equipped with enclosure systems similar to the secondary plant.
Located about 40 km south-east of downtown
Calgary and six km from the city limits, aggregate production was carried
out at Indus on a small scale prior to Burnco's acquisition of the property
in the mid 1980's. Since then, demand for the pit's aggregates has been
fuelled by Calgary's rapid commercial and residential development, particularly
in the city's southeast and southwest quadrants.
Covering some 445 ha (1100 acres) on a flood
plain of the Bow River, the pit is worked dry by lowering the local
water table some 3.5 m. To protect the water quality of the river, the
dewatering system has its own self-contained circuit that is isolated
from the circuit supplying water to the pit's wash plant. As a further
precaution, all pumped groundwater is first discharged into intermediate
holding ponds and tested before being pumped back into the river. The
ponds are located in the floodway, a previously mined buffer zone between
the extraction area and the river which forms part of the pit's ultimate
rehabilitation back to pasture.
The Indus pit wash plant produces a full range of coarse and fine
sizes for BurncoÍs area ready mix concrete and asphalt plants. All material
arriving at the wash plant first passes through an Eagle Iron Works
914 mm diameter by 5.5 m long twin screw log washer.
The stripping process here is completed in
three stages in accordance with permit conditions. It begins with the
removal and stockpiling of a surface layer of black topsoil about 150
mm thick, followed by the separate treatment of a 150 mm layer of subsoil.
Finally, a layer of silty clay, varying in thickness from 2.5 m to 3
m, is removed to expose the underlying gravel. Titus reports that about
200 000 m3 of overburden is stripped and stockpiled annually under the
company's dirt moving contracts.
The coarse aggregate deposit here contains
between 60 and 70 per cent material coarser than 4.75 mm, with occasional
rocks as large as 750 mm.
Primary loading is completed by two John Deere
330LC excavators, fitted with 2.3 m3 buckets and loading up to seven
contracted tandem trucks. With a payload of about 18 tonnes each, the
tandems have a typical haul of some 500 m. At the primary, a 30x40 Nordberg
C100 jaw crusher reduces the pit run to 115 mm minus. Plant foreman
Garry Derhak reports typical primary throughput of between 600 and 800
tonnes/h, or between 7000 and 8000 tonnes over a 12-hour shift. Noise
reduction measures at the primary extend even beyond the full concrete
enclosure. In addition, sound absorbing insulation has been attached
to the canopy over the truck dump hopper and has proved to effective
in absorbing sound emitted by haul trucks during the reverse and dump
cycle.

The 36.6m long
circular reclaim tunnel under the wash plant surge pile is a modified
steel butane tank fitted with two in-house feeders.
Downstream of the jaw, a 39.7 m long Assinck
stacker, programmable for radial, luffing and extendable operation,
stockpiles run-of-primary onto a surge pile providing about four shifts
of live capacity. From there, material is conveyed to the enclosed secondary
processing system consisting of three JCI 6x20 triple-deck screens,
two Nordberg Omnicone 1560 crushers and associated conveyors. The first
JCI screen directs material larger than 115 mm to a Torspec feeder which
in turn supplies a coarse head Omnicone 1560 reducing the feed material
to 38 mm minus. Meanwhile, material between 38 mm and 63 mm is reduced
to 16 mm minus by a second Omnicone 1560, similar to the first except
that this unit is fitted with a fine head. Product from the fine head
is conveyed to the third JCI screen which separates 16 mm and 10 mm
dry screened finished product. The 10 mm product is stockpiled by the
operation's second Assinck programmable stacker, this unit being extendable
to 42.7 m. Other sizes produced at the secondary plant include 40 mm
by 28 mm drainage rock and 28 mm minus wash plant feed, also stockpiled
by a 42.7 m Assinck programmable stacker. Largely hidden from view,
the reclaim tunnel under the wash plant surge pile is an innovative
example of equipment reuse; the 36.6 m long circular tunnel consists
of a former steel butane tank which has been successfully adapted to
this duty by the addition of two in-house feeders.
One
of Burnco's two John Deere 330LC excavators loading a tandem truck.
Up to seven contracted tandems are used to feed the primary plant.
Located some 200 m from the secondary plant,
the multi-stage wash plant incorporates a log washer, three screw washers
and two triple deck wash screens, as well as a sand-classifying tank.
All material arriving at the wash plant first passes through an Eagle
Iron Works (EIW) 914 mm diameter by 5.5 m long twin-screw log washer.
The initial 2 m section of the washer is fitted with paddles rather
than helical screw section to break up any residual clay materials in
the feed. Material leaving the log washer then passes over a Simplicity
6x16 triple-deck screen that divides the material stream into coarse
and fine sizes. The coarse stream receives an additional scrubbing phase
in an EIW 1.12 m diameter single-screw washer, before passing over a
second Simplicity 6x16 screen that separates 28 mm, 14 mm and 7 mm finished
product sizes.
Secondary cone
plant is enclosed by vinyl panels to control noise and dust.
Meanwhile, material finer than 5 mm is conveyed
to a 10-cell EIW classifier separating 5 mm and 3 mm sand sizes. From
there, 5 mm concrete sand is dewatered by a 1.12 m diameter EIW single-screw
washer while the finer 3 mm mortar sand is dewatered by a 914 mm diameter
EIW single-screw unit. Once inventories of mortar sand are sufficient,
both sand fractions are recombined into a single size to maximize the
plant's yield of concrete sand. For finished product loading, the wash
plant features two bins whose clamshell discharge gates have timed opening
to provide accurate product weights.
In addition to the bins, wash plant product
storage is provided by four shop-built luffing stackers Æ two 45.8 m
long stackers stockpile 5 mm sand and 28 mm washed material, while two
36.6 m long units stockpile 14 mm and 7 mm washed sizes. Derhak adds
that imported blend sand is added to the wash plant feed to balance
the plant's output of coarse and fine sizes with demand from the company's
area ready mix concrete and asphalt plants. The blend sand is introduced
into the system by two 40-tonne capacity driveÆover bins, fitted with
feeders to regulate its addition rate.
Overall plant control at Indus is provided
by two operators. The secondary plant operator monitors production in
a Clemro control trailer, assisted by 13 cameras. Over at the wash plant,
the operator has a high level view of the plant from the top mounted
control room. Site materials handling and sales load out duties are
performed by a fleet of three John Deere 744H front-end loaders, while
a water truck works full time to minimise dust generation from loader
and truck tires.

Inside the enclosure,
a Nordberg Omnicone 1560 fitted with a coarse head reduces the plus
115 mm material to 38 mm minus.
When it comes to repair and maintenance, the
enclosures at the primary and secondary plants have been designed with
easy access in mind. At the primary, a number of the precast wall and
roof panels are fitted with lifting eyes to facilitate their easy removal
and provide full access to the crusher. Gaining access at the secondary
plant is faster still, as individual enclosure panels can simply be
rolled back as required. For further flexibility, all of the primary
and secondary processing equipment is trailer mounted and semi-portable
Æ the jaw and both cone crushers are mounted on chassis supplied by
WRT of Saskatoon, while the secondary screens are each mounted on a
Clemro chassis.
To ensure that the operation's sound reduction
measures remain effective, two sound level monitoring stations have
been set up near the property boundary and operate continuously throughout
the production season. Titus reports recorded sound levels generally
less than 55 dBA during running hours, numbers that compare favourably
to City of Calgary noise bylaw levels of 55 dBA at night and 65 dBA
during the day. Unlike many jurisdictions across the country, the pit's
operating permit, including conditions on operating hours, is issued
by the local municipality and subject to a public appeal process. As
the permit is renewed for a maximum period of five years, the operation's
track record is subject to public scrutiny on a regular basis. Titus
reports that operating hours at Indus vary throughout the year up to
the permitted maximum of 18 hours/day, with the pit normally shutting
down for the winter months. As a footnote on permitting, Titus adds
that the success of the noise mitigation and monitoring measures at
Indus has enabled the company to increase operating hours from 12 to
17 hours at another company pit operation.
Wash plant product balance is optimized by the addition of imported
blend sand utilising two driveÆover 40 tonne bins. Site materials handling
and sales load out duties are performed by a fleet of three John Deere
744H front-end loaders.
The company's community relations' efforts
extend well beyond the property line at Indus. Each year the company
makes a voluntary business licence fee payment of $30,000 to the Municipal
District of Rocky View, with a further 25 per cent of this figure, $7500,
contributed annually towards community programs. In addition, the company
makes a number of corporate donations to local sports and charity programs.
Other community projects have included two miles of paving on the pit
approach road to further reduce dust generation, the result of a three-way
shared effort between Burnco, the local Municipality and Alberta Transportation.
Product delivery is recognised by Burnco as
an integral part of the aggregate business, with the company implementing
a number of measures to ensure good driving behaviour by truckers hauling
product from the pit. These measures include the strict enforcement
of posted speed limits on public roads near the pit and extra signs
reminding drivers of the requirement for responsible driving.
Further afield, Burnco and several other major
aggregate producers in the area are able to quickly respond to public
concerns on driving standards through a central truck registry system.
Under the system, trucks are required to prominently display a registry
reference number at the rear of each vehicle and, in the event of an
incident, motorists can call a toll-free phone number, quoting the registry
number. This can be quickly cross-referenced to the dispatch systems
of member companies to provide full details of the truck, driver and
specific trip being completed. Once these details are confirmed, the
reported incident can be verified and any necessary follow up completed.
|
A
corporate overview
Burnco Rock
Products Ltd. is a fourth generation family business established
in Alberta, and celebrating 90 years in business this year. Burnco
is a major supplier of high quality concrete, concrete products,
asphalt, aggregate and packaged products in Western Canada. Burnco's
Asphalt Division operates three stationary batch plants and two
portable drum plants. Its Ready-Mix Concrete Division provides
pumping, placing and finishing services, supplied by 12 stationary
concrete plants. The company operates a fleet of approximately
150 mixer trucks as well as 5 truck-mounted boom pumps. The Calgary
central dispatch and truck tracking system connects six plants,
while three plants in the Edmonton have similar central-dispatching
capabilities. Burnco's Concrete Products Division produces a wide
variety of architectural/structural, landscaping and utility products.
It also operates four retail centres, while additional company
assets include a number of aggregate sources as well as a cement
terminal and aggregate truck fleet. The company's website is www.burnco.com.
|
November 2002
issue
Aggregates
and Roadbuilding Magazine
4999 St Catherine
Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca
Back to Library
|