|
|
|
|
Ontario
Paver of the Year
|
By Andy Bateman,
Engineering Editor
 Aecon
Construction & Materials Ltd.'s Brian Morris proudly displays the
Paver of the Year Award and the Southwestern Region Award. Both awards
were presented to the company at the Ontario Road Builders Association's
76th Annual Convention.
Quality
roadbuilding was once again acknowledged at the Ontario Road Builders'
Association (ORBA) 76th Annual Convention, held this year February 3-5,
2003 at the Fairmont Royal York Hotel in Toronto. Award winners, including
2002 Paver of the Year, are selected annually for outstanding performance
in each of the Ministry of Transportation of Ontario's five regions.
The prestigious 2002 Paver of the Year
Award and the MTO's Northern Region Award went to Aecon Construction
and Materials Ltd. for the company's work on MTO contract number 2000-0235.
Located on Highway 69 at Mactier, this contract was valued at $32 million
and included grading, drainage, granular base, hot mix paving and structures
on a stretch of Highway 69, from 2.0 km north of Muskoka Road 12 northerly
for 10 km.
The majority of this project is new alignment
and was constructed in primarily closed road conditions over a two-year
period from November 2000 to October 2002. Extreme weather swings over
the course of 2001 included a bitterly cold winter, hot dry summer and
wet fall. Aecon's Brian Morris attributes the overall success of this
project to the efforts of the project's construction team, consisting
of the Carillon Construction Canada, Aecon Construction and Materials
Ltd. and Leo Alarie and Sons Ltd. joint venture (CAAJV), the contract
administration team of Tulloch Engineering and Surveys, as well as the
contract control team of the MTO. Morris highlights extraordinary cooperation
within this team that enabled quality control to be managed in a collaborative,
rather than confrontational, environment. One of the project's many
challenges was its location in an environmentally sensitive area containing
the endangered Massassauga rattlesnake. Working closely with Ontario's
Ministry of Natural Resources, the CAAJV implemented several measures
to protect the snakes and was rewarded for its efforts with the presentation
of an environmental award by the MTO. To tackle the major excavation
work on this project, heavy equipment was brought in including an Hitachi
EX 1100 excavator supplied by JV partner Leo Alarie and Sons Ltd. Morris
reports that mass rock excavation work continued round the clock in
order to expedite the job schedule, improve site access, and facilitate
work dependent on subgrade completion such as structure construction,
culvert placement, and granular placement. 
Roadtec SB-2500 Shuttle
Buggy feeding Caterpillar AP-1000 paver on award-winning contract.
Innovative solutions on the job included
layout and grade control utilising the latest Trimble Global Positioning
System (GPS) survey technology instead of the traditional staked survey.
GPS technology was also used in a dozer application where Trimble's
survey system supplied the operator with finished subgrade elevations
in relation to the dozer blade. Here, the GPS survey system was said
to be particularly useful during the initial stages of the job when
survey points were difficult to both locate and access. Trimble's BladePro
system, installed on a grader, was an additional grade control innovation
used on the project. This system provided elevation control of the grader
blade during fine grading by utilising signals transmitted from a known
point. In operation, the system was said to be extremely accurate and
to have made a direct contribution to the overall smoothness of the
pavement.
Hot mix asphalt was produced by Aecon's
360 tonnes/h capacity portable Gencor drum plant utilising aggregates
manufactured on site by Leo Alarie and Sons Ltd. Paving equipment for
the job consisted of Aecon's Roadtec SB-2500 Shuttle Buggy feeding two
Caterpillar AP-1000 pavers working in echelon and fitted with Topcon's
grade control system. The Caterpillar compaction fleet behind the paver
included a CB-634 dual unit in the breakdown position, a PS-300 rubber
tired secondary compactor and a Cat CB-534 finishing roller. Each completed
two passes to achieve 94 per cent average density. Materials quantities
included 52 000 tonnes of HL-3 Modified surface course hot mix asphalt
and 25 000 tonnes of HL-4 Modified base course as well as 173 000 tonnes
of Granular A and 267 000 tonnes of Granular B. Concrete volumes included
1 500 m3 of 50 MPa and 1100 m3 of 35 MPa mix, supplied by Parry Sound
Ready Mix Concrete. Additional job quantities included 290 000 m3 of
earth excavation, 900 000 m3 of rock excavation and the placement of
1100 m of 1800 mm x 1200 mm precast culvert. Key Aecon people involved
in the project were Cara Peters, project engineer and asphalt paving
superintendent Glen Pye.
Southwestern Region Award
Aecon Construction and Materials Ltd.
is certainly doing something right, also taking the Southwestern Region
award for its performance on MTO contract 2001-3004 to scoop two awards
for the second year running. This contract, on Highway 400 at Barrie,
was valued at $6 Million and extended from 1.0 km south of Essa Rd.
northerly to 0.5 km north of Willow Creek. The job took just two and
a half months between April and July last year, with the majority of
work completed at night. It involved milling all lanes of the highway
to a depth of 50 mm, plus the milling of lane two (the centre lane)
a further 50 mm for most of the length of the project. 
Aecon used two pavers
in echelon to carry out the asphalt surfacing operations on their award-winning
contracts.
Existing guide rail was also removed
and replaced. Two interchanges, Essa Rd. and Dunlop St., required full
depth removal of asphalt and curb and gutter, and this work was completed
during full interchange closures over two weekends. After milling, the
pavement was reinstated with a 50 mm lift of heavy duty binder course
(HDBC) in those areas of lane two that were milled the extra 50 mm,
followed by a 50 mm lift of dense friction course (DFC) covering the
entire highway. Milling and asphalt quantities included 360 000 m2 of
asphalt milling, 11 000 tonnes of HDBC and 52 000 tonnes of DFC. Here,
Morris cites cooperation between the Ministry of Transportation, the
Contract Administrator (HCIO) and Aecon as one of the main reasons the
project was completed successfully. For example, a change proposal initiated
by Aecon and accepted by the Ministry, improved project safety, both
for construction zone workers and the travelling public.
The contract was originally staged such
that either the northbound or southbound lanes would be closed entirely
each night, with traffic in the closed direction detoured through the
median. This scenario would result in opposing traffic being on the
same side of the highway and separated only by plastic TC-54 barrels.
After several discussions and positive input from both the Ontario Provincial
Police and the Ministry of Labour, it was decided that Aecon's change
proposal was the safest and most cost efficient method of constructing
the highway, particularly with the night work involved.
Under the agreed staging change, both
northbound and southbound lanes remained open and work was completed
utilising lane restrictions in the conventional manner. The staging
change delivered several other benefits besides improved safety. For
motorists, the change allowed on and off ramps throughout the city to
remain open, while for Aecon, it facilitated timely delivery of asphalt
and other materials to the site. A second asphalt paver was brought
on site, allowing echelon paving (initiated and accepted under another
change proposal) to be done wherever possible. At other times, one paver
could complete intersection tie-in work while the other paver continued
main line paving.
Roto Mill Services Ltd. of Brampton completed
the milling job utilising two CMI pavement profilers. Unit 1 was a CMI
PR-1050, powered by a 783 kW (1050 hp) engine making a 3.81 m wide cut,
while Unit 2 was the 1050's smaller stablemate, the PR-800, powered
by a 597 kW (800 hp) engine and milling a 2.18 m wide cut. Aecon's paving
train was similar to the equipment spread utilised on the Northern Region
Paver of the Year contract and consisted of a Roadtec SB-2500 Shuttle
Buggy feeding Caterpillar AP-1000B pavers fitted with Topcon grade control
systems. The Caterpillar compaction fleet following the paver included
a CB-634 breakdown roller in the breakdown position, PS-300 pneumatic
unit in the secondary position and a CB-534 finishing roller. Each completed
two passes to achieve 94 per cent average density. Morris notes that
the average production rate of asphalt placed on this job was just over
200 tonnes/h, adding that the SB-2500 facilitated maximum productivity.
Hot mix asphalt was supplied from Aecon's portable asphalt plant, a
Gencor drum mix unit rated at 360 tonnes/h and strategically located
at the intersection of Highways 11 and 93 near the north end of the
project.
Aecon's senior project superintendent
on this contract was Gary Kmith, with Jim Young in the dual roles of
daily site superintendent and quality control plan administrator. Junior
Lake was asphalt superintendent responsible for paving operations.
Northwestern Region Award
The MTO's Northwestern Region award was
won by Bruno's Contracting (Thunder Bay) Ltd. for contract number 2001-0215.
This contract involved reconstruction of a section of Highway 17 northwest
of Thunder Bay, from 14.3 km west of the Raith West Junction westerly
for 18.8 km. Valued at $4.56 million, the job lasted six months from
April to September last year and included grading, drainage, granular
base and paving. The job was noteworthy as the first contract in Northwest
Region to include a heavy duty binder course (HDBC) asphalt mix.
Unusually cold spring temperatures coupled
with severe flooding in the region hampered early site work. The weather
also impacted on aggregate delivery, as the supplying quarry was a substantial
distance from the highway with difficult access. At the quarry itself,
another challenge was the familiar problem of effectively screening
wet feed material to produce spec fine aggregates. During the summer
months, additional challenges came in the form of heavy construction
zone traffic as this section of the Trans-Canada Highway is close to
a cottage area and subject to weekend holiday traffic.
Materials for the job included 95 000
tonnes of Granular A and 19 000 tonnes of Granular B, followed by nearly
50 000 tonnes of hot mix asphalt. Mix quantities included 22 600 tonnes
of HDBC and 26 300 tonnes of HL4 (modified), produced by a quarry based
Barber Greene portable drum plant rated at 250 tonnes/h. On site, Bruno's
paving train consisted of a Roadtec SB-2500 Shuttle Buggy feeding a
Vùgele America Pro-Pav Swiftrac paver, followed by a Hamm HD 110 roller
for breakdown and a pneumatic Caterpillar PS-300B finishing roller.
The compactors made two to three passes each to achieve densities of
94%. Company secretary-treasurer Silvio DiGregorio reports that a dedicated
team of employees including superintendent John Arnosti, assistant superintendent
Danielle Bartlett and Quality Control manager Bernie Prevost take the
credit for delivering success on this project.
Eastern Region Award
Dufferin Construction Company was the
MTO's Eastern Region award winner was for its work on Highway 401 near
Morrisburg. MTO contract 2001-4018 covered a section of the Eastbound
Lane (EBL) from 0.9 km east of Carmen Rd. easterly to 0.95 km west of
Upper Canada Rd. and was valued at $5.4 million. Lasting from May 5th
to October 15th 2002, Dufferin's work included drainage, milling, grading,
bridge rehabilitation and paving. Hot mix was supplied by Dufferin's
360 tonnes/h capacity portable CMI drum plant, set up at Iroquois, and
delivered by Red River LB (Live Bottom) trailers having 35 tonnes of
payload.
On site, Dufferin's paving equipment
included a Roadtec SB-2500 Shuttle Buggy, a Caterpillar AP-1055 Paver,
Bomag BW202AD and Bomag BW201AD compactors in the breakdown position,
a Dynapac 271 secondary compactor and a Bomag BW154AD finishing roller.
Asphalt mix quantities totalled 22 889 tonnes of HL1 (Modified) and
43 207 tonnes of heavy duty binder course (HDBC). Raw materials and
suppliers for this contract included 64-34 Performance Grade Asphalt
Cement (PGAC) from McAsphalt Industries Ltd., HDBC and base aggregates
from Cornwall Gravel Co Ltd., HL-1 (Modified) aggregates from Lafarge
Materials & Construction Inc.'s Brockville quarry and HL-1 Blend sand
from Charlie Moore Sand. Cruickshank Construction Ltd. supplied clear
stone covering sub-drains and was also subcontractor to Dufferin for
drainage work. Hard Rock Paving Co. Ltd. completed surface milling.
Key Dufferin people involved on the contract included district manager
Michel Rodrigue, superintendent Peter Gamble and assistant superintendent
Dan Beneteau.
Central Region Award
Warren Bitulithic Ltd. won the MTO's
Central Region Award for paving on the Highway 404 extension near Newmarket
under MTO contract number 2000-0077. Featured in the October/ November
2001 issue of Aggregates & Roadbuilding, this paving contract marked
the first time that hot mix asphalt designed to full Superpave specifications
has been utilised on an Ontario 400 series highway. The paving job extended
2.4 km, from 800 m south of Davis Dr. in Newmarket, northerly to 150
m north of Green Lane (formerly Herald Rd.). Additional work included
Green Lane, from Leslie St. to 74 m east of Woodbine Ave. The total
value of Warren's Bitulithic's work was over $3 million and focussed
on paving, while grading, drainage and other work was carried out by
prime contractor Carillion Construction Canada.
Superpave mixes were used on the southbound
lanes as this section of Highway 404 will be an increasingly popular
route for loaded aggregate trucks heading south to Toronto from Stouffville-area
aggregate operations. Two southbound lanes, plus acceleration and deceleration
lane for Green Lane and Davis Dr. respectively, were paved with three
lifts totalling 180 mm. A 90 mm thick Superpave base lift of 25NMS (25
mm nominal maximum size aggregate) was followed by a 50 mm Superpave
base lift of 19NMS and a 40 mm surface lift of Dense Friction Course
(DFC).
The northbound lanes were paved with
the same combined thickness of hot mix asphalt as the southbound lanes
(180 mm), but instead utilised conventional mixes throughout; a 50 mm
lift of HL8, 50 mm of lower HDBC, 40 mm of upper HDBC and 40 mm of DFC.
A fixed Astec batch plant and Standard-Haven counterflow drum plants
at Lafarge Canada's Maple Yard successfully produced the Superpave asphalt
mixes. On site, a Roadtec SB-2500 Shuttle Buggy fed a Caterpillar AP-1055B
tracked paver fitted with a hopper insert and a 10-20B Extend-a -Mat
screed. Behind the paver, an Ingersoll Rand DD110HF compactor made two
passes on high amplitude and frequency, followed by a Caterpillar PS-300B
rubber tired compactor making six passes and a Bomag BW164AD in the
finishing position making six passes in static mode. Hot mix types and
quantities included 5100 tonnes of HL8, 23 700 tonnes of HDBC, 11 000
tonnes of DFC, 3800 tonnes of 19NMS and 4700 tonnes of 25NMS mix, as
well as 6300 tonnes of HL 3 on Green Lane. Fine aggregates and coarse
aggregates were supplied from Lafarge Materials & Construction Inc.'s
Dundas quarry while its Lafarge's Coldwater operations provided coarse
aggregate for the DFC mix. Warren's team found that the treatment of
Superpave mixes was generally similar to other mixes, although some
adjustments were necessary to deal with the relatively coarse mixes
and lift thicknesses almost double those of traditional Marshall mix
types.
Modifications at the asphalt plant yard
included cold feed screen changes, while in terms of paving, Warren's
Andrew Pahalan reports that the remixing provided by the Roadtec SB-2500
was reportedly essential for dealing with the Superpave mixes. In addition,
rolling patterns were adjusted to achieve the required in situ compaction
and an innovative hopper sampling system was developed to obtain representative
samples of the thick Superpave lifts. Key people involved on the project
included Rick Logozzo, construction manager-Special Projects & MTO;
Mike Greco, general manager; Doug McDonald, asphalt plant manager; Dan
Gillis, field superintendent; Carlo Fallavollita, general superintendent;
Brian Samulewitch, Quality Control manager; Mix Designs & Sampling Hopper;
Paul Lum, Superpave Mix Designs; Andrew Pahalan, Quality Control co-ordinator;
Robert Bernardi, paving foreman; Phil Digiorgio, paving foreman and
Rob Belanger, plant foreman.
 |
From
left to right: Gary Kmith, Aecon Construction & Materials Ltd.,
Southwestern Region Award Peter Gamble, Dufferin Construction Co.,
Eastern Region Award Hon. Norm Sterling, Ontario Minister of Transportation
Tom Dziedziejko, Aecon Materials Engineering, Aecon Construction
& Materials Ltd., 2002 Paver of the Year (Northern Region Award).
Dan Gillis, Warren Bitulithic Ltd., Central Region Award (Absent
from photo - Bruno's Contracting (Thunder Bay) Ltd., Northwestern
Region Award winner). |
March-April 2003 issue
Aggregates
and Roadbuilding Magazine
4999 St Catherine
Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca
Back to Library
|