Canada's “Rock to Road” Magazine

 

Winter working a reality for
Hard Rock Paving quarry

By Andy Bateman, Engineering Editor

Strong demand for its products has meant winter working several years in a row for a southern Ontario quarry operation.

A recently fitted BTI TB725X secondary breaker deals with any oversize in the feed to the Telsmith 25B gyratory primary crusher.

    The Law Quarry, located in the south-east corner of the Niagara Peninsula between Port Colborne and Wainfleet, Ont. has run through each of the last three winters, due to strong demand for aggregates from parent Hard Rock Paving as well as suppliers of the major casino and hotel development in nearby Niagara Falls. 2003 customers will include Hard Rock's Highway 402/Queen Elizabeth Way (QEW) roadbuilding contract and the company's quarry-based Port Colborne asphalt plant. Additional demand will come from 2002 internal carryover contracts, the resurfacing of Highway 20 and an area ready mix concrete plant. Operations manager Keith Porter predicts that 2003 may be a record year for the quarry, depending on overall activity demand generated by the casino development and the Niagara Region.
     From a production perspective, Porter explains that the focus now is on building inventories of granular products, in advance of a plant switch in March that will maximize the production of clear sizes. This production switch also entails a switch of quarry working as the limestone deposit here is worked in two faces. The 9.4 m high top bench is the source of most granular products, while the 11.6 m high bottom bench is the source of clear sized concrete and asphalt aggregates. Products from the top bench include Granular A base material, 19 mm clear drainage stone and 12.5 mm minus shouldering rock, while products from the bottom bench include 19 mm concrete stone, HL3 asphalt stone and HL8 asphalt stone as well as some manufactured sand for asphalt and screenings. Given the anticipated high demand for clear sizes from the bottom bench, Porter's ongoing challenge is to keep the top bench face far enough in advance of the bottom bench face to release sufficient bottom bench reserves.
     Raw feed is processed by the quarry's main stationary plant and a new separate spread, with material fed to each according to target product mix. The main plant is fed both top and bottom bench material, while the new spread is fed bottom bench stone only to maximize the overall yield of concrete and asphalt aggregates.
     Porter notes that winter conditions have impacts throughout the whole operation. From a safety perspective, the winter months naturally present increased risk from slips or falls and plant screenings are spread in pedestrian traffic areas to help reduce these risks. Screenings are also spread on haul roads when necessary to provide safer running surfaces and also fill in washboard or low areas where water can accumulate. The winter also places increased emphasis on good housekeeping as any objects hidden under snow, such as screen of conveyor parts represent a trip or injury hazard.

This Link-Belt 4300 excavator was used to remove frozen build up from the corners of the primary dump hopper, a common problem in cold weather working conditions.

     At the front end of the process, all necessary stripping is completed ahead of the winter to avoid dealing with difficult frozen or muddy conditions. Drilling and blasting continues, but can be a challenge, particularly in snow, when blast holes are difficult to mark and charge. Production blasts are timed to allow working, as far as possible, with a fresh muck pile, as a muck pile that has been exposed to snow, rain or freeze-thaw cycles for any length of time can be difficult to separate and load efficiently. Porter emphasises that the primary loader operator plays a key role in efficient winter running, by selecting newly shot, well-graded material and avoiding the frozen lumps, snow, or wet material that can soon cause headaches downstream.
     At the plant itself, process equipment is run empty for 20 minutes at the beginning of each shift to warm all conveyor belts. Any frost left on cold belts often results in slippage around drive pulleys, even if the pulley is lagged. To improve frost protection, many of the plant's process belts are covered and Porter is looking at covering all remaining exposed belts. Crushers and screens are also warmed up, aided by immersion heaters in crusher oil tanks. Once production begins, the plant feed rate is steadily ramped up to ensure material is flowing freely through the plant. Work patterns are also adjusted at the end of the shift, when plant storage bins that would be normally be left full are emptied to avoid overnight freezing of material and two plant labourers stay an extra hour to remove any material spilled at transfer points.
     Screening efficiency is also impacted by weather conditions. On cold dry days, screen efficiency is good, but deteriorates when the temperature is around freezing point. In these conditions, screening of smaller sizes is difficult as "piggy back" fines adhere to the surface of larger size stone pieces. Porter adds that good results have been obtained in these marginal conditions with four 4 mm opening Flex-Mat screens from Major Wire Industries that have been in operation for 12 months and reportedly doubled output.
     Dust suppression becomes a challenge in cold weather, mainly from vehicle tires and process locations such as crusher discharges and conveyor transfer points where material free falls. Porter is currently reviewing the set up of a number of transfer points with a view to reducing dust by enclosure, reduction of free fall height or a combination of the two. The quarry's rural location helps somewhat in this regard with no recorded complaints to date due to off site dust emissions.

A caterpillar 988B wheel loader is shown loading a Caterpillar 771D haul truck at the Law quarry. The loader operator plays a key role in efficient winter runnign by selecting newly shot, well-graded material and avoiding the forzen lumps, snow, or wet material that can slow production.


     At this operation, dewatering operations are relatively unaffected by cold weather, with two Flygt 152 mm pumps running year round to dewater the quarry.
     Winter working also means that production of granular base finished product is a fine balance between making sufficient product and avoiding unnecessarily large stockpiles. Unprotected stockpiles absorb water from snow and rain, resulting in hard to work icy piles and potentially dangerous steep faces when product is finally shipped from the centre of a large stockpile, sometimes months after it was produced. For MTO work, the quarry has elected to use the process chart method to monitor granular product quality, thereby avoiding the building of 4000-tonne lots of product that require testing and approval prior to shipment.
     In terms of the overall impact on productivity, Porter reports that the plant's average production rate drops from 375 tonnes per available operating hour in warmer weather to about 325 tonnes/h in the winter, reflecting the accumulative effect of the morning warm-up period, ramp-up period and other weather induced delays. On the day of Aggregates & Roadbuilding's visit, for instance, production was halted for about 30 minutes while a rental Link-Belt 4300 excavator removed frozen build up out of the corners of the primary dump hopper.
     Primary loading and hauling at the Law quarry is completed by Caterpillar fleet including a 988B loader fitted with a 5.3 m3 bucket, and two Caterpillar haul trucks, 771D and 769D units having 40.7 and 37.4 tonnes maximum payload capacities, respectively. These units haul to the primary dump hopper where feed to the primary crusher is regulated by a 1.8 m x 4.5 m Simplicity pan feeder. The primary itself is a Telsmith 25B gyratory primary crusher with a recently fitted BTI TB725X hydraulic rock breaker.
     The radial primary surge pile allows top and bottom bench stone to be stockpiled separately. From there, two 1524 mm x 914 mm Syntron feeders regulate the flow of material to a 5x16 Tyler double-deck scalping screen. The scalping screen separates the feed into three sizes. Oversize is first reduced by a Kleemann Reiner impact crusher and then screened over 6x16 ElJay and 4x8 Tyler screens. Material larger than 19 mm from these screens is returned back to the initial scalping screen, while 19 mm x 6 mm concrete stone is stored in product bins under the screens and 6 mm minus is pulled off via an overflow chute for blending into granular base. Meanwhile, material retained on the bottom deck of the scalping screen is reduced by a 41/4 Nordberg cone crusher, and screened over four 5x16 Tyler screens. Here, 19 mm plus material is directed to a 41/4 Nordberg Short Head tertiary cone crusher, while 19 mm clear and HL3 asphalt aggregates are sorted in product bins and 6 mm minus screenings are stockpiled separately. The smallest product from the scalping screen, 25 mm minus, is stockpiled as granular A finished product during the winter months. During the construction season, the 25 mm screen cloths on the on the bottom deck of the scalping screen are replaced by 50 mm opening cloths and 50 mm minus passing this bottom deck becomes the feedstock for the new plant. On arrival at the new plant, this 50 mm minus is first screened over a 6x16 ElJay screen. 50 mm x 25 mm oversize is directed to an Allis H3000 Hydrocone crusher, while 19 mm minus concrete aggregate passes through a Ward Industrial twin-screw 914 mm diameter coarse material washer and 6 mm minus is passed through a Ward fine material screw washer.
     Support equipment at the operation includes a Caterpillar 972G materials handling loader, a Bobcat 763 skid steer on clean up and a full-time water truck (in the summer months) for dust suppression.
     Drilling and blasting at the Law quarry is contracted out to Grand Valley, Ont.-based St Lawrence Explosives Inc., who in turn subcontracts drilling to Gibbons Contracting Ltd.. Gibbons utilises a Gardner-Denver Hydratrac rig to drill 101 mm diameter production holes. The Law Crushed Stone Division is part of The Hard Rock Group. Hard Rock Paving Co. Ltd. has owned the Law quarry since 1978.
     Keith Porter is operations manager - Materials for Hard Rock Paving's Law Quarry, asphalt plants at Port Colborne and Fort Erie, portable crushing operations and the company's CCIL approved laboratory.

January/February 2003 issue

Aggregates and Roadbuilding Magazine
4999 St Catherine Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca

Back to Library