|
Canada's Rock to Road Magazine
September/October
2007 Issue
For a copy of the issue
that contains these articles with colour photos, click
here.
High
capacity B.C. quarry targets U.S. concrete markets
By Andy Bateman, Engineering
Editor
Still
in its first year of operation, Polaris Minerals Corporation’s
new quarry has major concrete aggregate customers in San Francisco and
B.C’s Lower Mainland, with more sure to follow.
Located at the northern end of Vancouver
Island on Broughton Strait, the Orca Quarry is some four kilometres
west of Port McNeill and went into operation in February 2007. Herb
Wilson, senior vice president and chief operating officer, explains
the quarry is permitted to produce six million tonnes of sand and gravel
annually and, with the expectation of strong demand for its concrete
aggregates, every aspect of the process has been designed with high
capacity in mind. In the short time since Orca’s opening, those
demand expectations have already been met with the frequent arrival
of 70 000-tonne capacity Panamax class bulk carriers bound for San Francisco
and barges on the shorter run to the Lower Mainland.
Plant capacity numbers certainly reflect
the design goals, with Wilson reporting peak and operating average throughput
rates of 1500 tonnes/h and 1200 tonnes/h, respectively. Four finished
product stockpiles, two for sand and two for gravel, each have about
125 000 tonnes gross and 44 000 tonnes live capacity to ensure adequate
inventories for rapid vessel loading. Aggregates drawn from these huge
stockpiles are conveyed to ships or barges by a 5000 tonnes/h capacity
reclaim and conveying system and loaded by a single quadrant shiploader
of similar capacity. (See “Shiploader installation goes like clockwork”,
Aggregates & Roadbuilding December 2006).
Orca’s processing plant separates
material into three concrete aggregates; coarse gravel, fine gravel
and concrete sand, and consists of primary screening with a crushing
circuit, secondary screening, washing and sand classification, product
storage stockpiles and a product reclaim system. Downstream of the sand
classification system, a sophisticated silt recovery and water recirculation
system eliminates the need for settling ponds and minimises the requirement
for process make up water.
Like any aggregate operation, good reserves
are essential for Orca’s long-term success, where “good”
is measured in terms of quantity, quality and location. Orca scores
high on all three counts. The new plant is currently processing the
East Cluxewe deposit, the first of three here, containing reserves of
121 million tonnes of high-quality sand and gravel. This deposit contains
about 70 per cent sand and 30 per cent gravel and, as most of the gravel
is already naturally sized at 25 mm or smaller, only about 12 per cent
of the pit run has to be crushed. That is good news for customers, as
concrete containing aggregates with a high percentage of natural rounds
means concrete with excellent mixing, pumping and finishing characteristics.
Production begins with scrub removal,
followed by the stripping and storage of a thin layer of overburden
for later rehabilitation. In a rare application for these machines,
both primary loading and hauling are then completed by scrapers. The
deposit is generally loose enough for the two Caterpillar 637G scrapers
to self-load, though their design provides for push pull loading or
standard push loading by dozer if required. The loaded scrapers then
discharge over a relocatable drive over hopper, under which two belt
feeders equipped with Torspec variable speed drives maintain a steady
flow of pit run onto the plant feed conveyor belt.
Pit run arriving at the processing plant
is stockpiled in a plant feed surge pile with 90 000 tonnes gross and
28 000 tonnes live capacity to provide several shifts of running without
recharge if necessary. Material drawn from the surge pile is first screened
on a pair of Metso 6x20 double-deck dry screens fitted with 50 mm and
25 mm cloths on the upper and lower decks, respectively. All material
larger than 25 mm is directed to a Metso HP 400 cone crusher, while
material smaller than 25 mm is conveyed to two Metso 8x24 double-deck
washing screens fitted with 12.5 mm and 4.75 mm cloths on the upper
and lower decks, respectively. Material sized at 25 mm x 12.5 mm retained
on the top deck is stockpiled as large gravel while 12.5 mm x 4.75 mm
material is stockpiled as small gravel.
Meanwhile, sand slurry (minus 4.75 mm
material and water) passing the bottom deck of the wet screens discharges
into a sump and pumped from there to a bank of four McLanahan LPT VD
21 dewatering screens. Finished sand product retained on each dewatering
screen is conveyed to sand stockpiles one and two, while fine material
and water passing through the screens is pumped up to LPT S 830 cyclone
separators mounted above each screen. Cyclone underflow containing recoverable
sand fractions discharges back onto the dewatering screen, falling on
top of the bed of material already on the screen to increase sand recovery.
At the same time, overflow from each cyclone containing water and silt
(very fine sand less than 75 microns in size) is directed to a 18.3
m diameter McLanahan high-rate thickener via a gravity flume. Inside
the thickener, anionic flocculent is added to encourage the fine particles
to clump together and so accelerate the separation of fines and water.
Fines accumulate on the thickener bottom while clear water overflowing
from the top is recycled back to the operation’s process water
supply tanks. Settled fines are recovered from the bottom of the thickener
and pumped to a conditioning tank, where cationic flocculent is added
to disperse the fines before the fines and water mixture is fed to a
pair of 3 m wide Phoenix belt filter presses. The presses squeeze excess
water out of the slurry and the resulting silt cake is hauled back to
the pit for storage.
Wilson emphasises that the overall plant
design construction and operation has been a team effort, and in particular
points to the contribution of the local workforce: “From the beginning,
local people have been closely involved and are among the best I’ve
ever worked with. One example that comes to mind was our electrical
contractor who, on his own initiative, decided to install thousands
of metres of electrical cable one Sunday when other trades were not
working. This gave our plant completion a huge boost and was part of
the reason we were able to begin production on schedule. With construction
completed, our commitment to the local workforce continues under an
agreement with two first nations in which half the workforce is first
nations. To help achieve this, we have provided over 6000 hours of employee
job training in operations, health and safety, first aid and mine rescue.”
Major suppliers to the construction project
included Metso Minerals, who completed the detailed design of the plant
from the raw feed conveyor to the finished stockpile conveyors. The
McLanahan Corporation was subcontractor to Metso Minerals for the dewatering
screens, thickener and conditioning tank. Structural steel was fabricated
on Vancouver Island and trucked to the site, while the product stackers
were built by U.S. based Swift Manufacturing. ORCA and its contractors
completed foundations, reclaim tunnels and the load out system. The
1.37 m wide, 1.5 km long load out conveyor system was supplied by Continental
Conveyor & Equipment Company through their west coast agent and
installed by Orca employees.
The Orca operation provides some interesting
additional examples of efficient plant and process design. Its mobile
equipment fleet, for example, is relatively small compared to many other
aggregate operations of similar capacity and includes, besides the two
scrapers, just a Caterpillar D8T dozer, a 980H wheel loader, and an
IT 38 G Series II Integrated Tool Carrier. This small fleet demonstrates
the application of two established materials handling practices: once
material has been picked up, minimise the number of times it is dumped,
reloaded and hauled by mobile equipment. Secondly, when moving material
between two fixed points, conveyors provide a lower operating cost per
tonne than a loader and truck fleet of similar capacity. The Orca feasibility
study mining plan identified that four scrapers would be needed to achieve
maximum design capacity and the company anticipates adding a third unit
in the spring of 2008.
At the front end of the process, the use
of scrapers replaces a possibly bigger fleet of primary loader(s) and
haul trucks. During the process, the connection of all process stages
by conveyor or slurry line eliminates the need for intra-plant material
transfer by loader or truck. Finally, all finished products leave the
operation via the shiploading conveyor.
The availability of electricity at reasonable
cost is also an important component of the economics of an aggregate
operation. In general, operations will install mains power where practicable
as the cost per tonne of power from diesel driven portable generators
is usually significantly higher than mains power in the long run. At
Orca, mains power is provided through a 25kV line of BC Hydro, with
one connection providing power for the shiploader and the other for
the rest of the processing plant. Transformers step the power down from
25 kV to 4160 volts or 600 volts as necessary.
Polaris’ approach to community relations
and the environment was recognised in a 2007 award from the Prospectors
and Developers Association of Canada. The award recognised Polaris for
“establishing excellent community relations and environmental
practices during the exploration and subsequent construction of its
Orca Quarry near Port McNeill on Vancouver Island. The company set up
partnerships with First Nations communities that have enabled bands
to have an equity stake in the operation, and two of the largest quarries
of their kind in Canada have been successfully permitted with the support
and cooperation of the local community.”
The Award also recognised the company’s
environmental approach, noting that, “Polaris has also exceeded
expectations in its attention to the protection of the environment.
For example, the processing plant at the Orca Quarry will feature a
closed circuit water recycling system to ensure that no process water
will be discharged into the environment. The system includes a filtering
process that eliminates the use of settling ponds, minimizes silt handling
and clean-up costs and allows for the silt to be used to beneficiate
the soils during reclamation.”
Polaris
enters long-term alliance with CEMEX
Mexico’s
CEMEX, Inc. and Polaris Minerals Corp. have announced that they
have entered into a long-term supply and distribution agreement
for marine transported construction aggregates in the states of
California, Oregon and Washington.
For this three state area, the parties
have agreed that CEMEX will be the exclusive marketer for Polaris
and Polaris will be the exclusive supplier to CEMEX of marine
transported construction aggregates for CEMEX’s internal
use and for sales by CEMEX to third parties.
Polaris has already commenced sand
and gravel shipments from the Orca Quarry to the two existing
CEMEX terminals in San Francisco Bay. In addition, the two companies
have entered into an alliance for the development of future construction
aggregates import terminals in the same territory.
Included in the strategic alliance is an expectation that Polaris
will develop its 70 per cent owned Eagle Rock Quarry at a time
to be determined by market demand.
The parties have agreed to cooperate
in the pursuit of markets and terminal capacity for Eagle Rock
crushed granite products. The existing Polaris construction aggregate
supply and distribution agreement covering the four northern California
counties of Marin, Sonoma, Mendocino and Napa is unaffected by
this alliance.
“In a market where the long-term
availability of construction aggregates is not assured, the realization
of this transaction with Polaris secures the availability of high
quality aggregates for our customers as well as our affiliate
ready-mix operations for many years ahead,” said Gilberto
Perez, president of CEMEX USA.
Commenting on this new relationship,
Marco Romero, president & CEO, Polaris Minerals Corp., said,
“Since the creation of Polaris, we have focused on three
principal elements in order to achieve our business plan: the
ownership of high quality and long-term aggregate resources, the
securing of cost effective shipping capacity, and the establishment
of gateways into the market through strategically located port
terminals. Through this landmark agreement with CEMEX, we have
made a quantum leap in the third vital component.
“As a result, we now expect
that the anticipated volume of sales through existing terminals,
coupled with the expectation of new terminal development in southern
California and sales to existing customers, should exceed our
earlier sales projections for the Orca Quarry, all at market prices.
Additionally, we are closer to making the Eagle Rock Quarry a
reality.”
He continued, “CEMEX is a
leading consumer, producer and distributor of construction aggregates
in California and, in common with other major companies in the
aggregate industry, relies on the availability of long-term high
quality aggregate resources to best serve its customers. At a
stroke, both Polaris and CEMEX have achieved many strategic objectives
and we look forward to a long and mutually rewarding relationship
with our new partner.”
Polaris Minerals Corporation owns
88 per cent of the Orca Quarry with the remaining 12 per cent
participating interest held by the ‘Namgis First Nation.
Polaris Minerals Corporation is a publicly traded company based
in Vancouver, B.C. and listed on the Toronto Stock Exchange in
Canada. |
Back to
top
Contractor
digs deep for returning troops
By Andy Bateman, Engineering
Editor
An
infrastructure upgrade project at a Canadian Forces Base places unusual
demands on excavation and sewer installation equipment.
The
months of July and August 2007 saw soldiers based at Canadian Forces
Base (CFB) Petawawa returning from their mission in Afghanistan. Those
returning to the Married Quarters at the base found significant construction
activity, with an infrastructure upgrade project underway to replace
aging water and other services. For its contractor, the project’s
deep excavations have posed some unusual challenges requiring significant
digging, lifting and pulling capacity.
CFB Petawawa is described as one of Canada’s
leading military bases, closely linked to its host community of the
Town of Petawawa, as well as the City of Pembroke and the sixteen other
municipalities that make up Renfrew County. Established in 1905, personnel
numbers for the base include 5,100 military, 7,700 family members and
1,000 civilian employees for a total of 13,800. Of these, approximately
6,000 live in local communities of the Ottawa Valley, with the majority
living between Deep River and Pembroke.
Contract PA045511 provides for extensive
infrastructure upgrades to the Married Quarters (MQ) at the base, some
of which date back to the 1950’s. Officially described as the
Parental Marriage Quarters Municipal Upgrade, the contract is valued
at $1.77 million and includes full replacement of sanitary sewers, storm
sewers and water mains, as well as service replacement to each unit
on Moreuil Wood Blvd., Dieppe St., Liri Ave. and Ortona Ave. (War historians
will recognise that street names at CFB Petawawa are named after famous
conflicts). Following pipeline installation, surface work has included
road reconstruction, asphalt paving and sidewalks and is on target for
completion in November 2007 after a July 5th 2007 start. Construction
conditions are typical of the area, with loose sandy soil and generally
dry working. At shallow depths, these conditions make for easy digging,
but it has been a different story in some locations due to excavation
depths of up to 10 m and large diameter storm sewer installation.
To tackle the deep excavation work, contractor
R.G.T. Clouthier Construction Ltd. put the company’s new Liebherr
954 excavator into service and reports good results. Besides excavating
duty, the excavator has had the necessary capacity to handle heavy items
such as double trench boxes as well as the reach to place pipe bedding,
cover material and 6 m long sections of storm sewer pipe.
Occasionally, more lifting power in the
shape of a 90 tonnes capacity Liebherr LTM1090 mobile crane has been
necessary to deal with the installation of heavy precast concrete pipe
sections. A Hanson STC 6000 precast concrete stormceptor (storm interceptor),
for instance, weighed in at 12 tonnes and was lifted with the LTM1090
set well back from the edge of the deep excavation to ensure a safe
and uneventful lift.
R.G.T. Clouthier Construction Ltd. is
Pembroke Ontario and activities of this vertically integrated business
include heavy civil, as well as municipal and road construction. The
aggregates side of the business includes aggregate production and delivery,
custom crushing, screening and asphalt and concrete recycling with some
10 company owned pits and 10 leased pits. The group’s affiliated
companies include Valley Crushing and the Pembroke Machine Shop.
Canadian
Forces Housing Agency
The
Canadian Forces Housing Agency (CFHA) notes that CFB Petawawa
has 1685 Married Quarters (MQs), located in two areas known as
the North and the South Townsite. The CFHA was established as
a provisional Special Operating Agency (SOA) of the Department
of National Defence in October 1995. The Agency’s mandate
is to operate and maintain the portfolio of approximately 15,000
military family housing units (married quarters) at Canadian Forces
bases and wings across Canada. This includes allocating housing
to Canadian Forces members and their families, carrying out maintenance
and repairs, administering the rent system and managing the housing
assets on behalf of the Department. Funds are distributed amongst
Housing Management Offices on a pro-rata basis by portfolio size
and condition in relation to others nationally, and on average
occupancy rates at each site. |
Back
to top
Green
sand recycling program pays big dividends for Edmonton
An
award-winning processing system for decontaminating and recycling winter
street sand rather than disposal in a landfill is being used by the
City of Edmonton to save millions of tax dollars while generating significant
environmental benefits.
Depending
on the severity of winter, approximately 165 000 tonnes of sand and
salt are spread on the city’s 15 000 lane-km of paved roadways
as traction aids to keep traffic moving and stopping safely. Roughly
70 per cent of these materials are subsequently picked up each spring
through street sweeping operations. Historically, only about 25 per
cent of the street sand has been recycled, usually by blending the recovered
sand with new sand. Most of the remaining street sweepings, containing
sand, salt, clay, leaves soil and other debris were deposited in a Class
3 (unlined) landfill.
In
2001, it was determined that the street sweepings exceeded new stricter
Alberta Environment guidelines for salt contamination by five to 10
times the permissible levels and, as such, had to be disposed of in
the city’s Class 2 (lined) Clover Bar landfill facility. That
year, more than 115 000 tonnes of winter street sweepings were recovered
– an amount equal to 50 per cent of the total weight of contaminated
materials delivered to the Clover Bar facility in an average year. It
was clear to city officials that landfilling of winter street sweepings
would have a negative impact not only on the life of Clover Bar and
the city’s finances, it also accelerated the depletion of valuable,
non-renewable sand resources.
Due
to high construction demand in the past 20 years, all of the local sand
deposits have been depleted. Edmonton’s nearest sources of raw
sand are currently more than 100 km from the city limits. According
to Barry Belcourt, director of roadway maintenance for Edmonton, the
city was spending up to $3 million annually buying sand for its winter
sanding operations. A less costly and more environmentally acceptable
alternative to existing practices had to be found.
In
2003, the City of Edmonton’s Transportation and Streets Department
established, in partnership with the Edmonton Waste Management Centre
of Excellence (EWMCE), a two-year pilot project to determine the feasibility
of reclaiming and recycling winter sand. The goal was to produce a cost-effective,
environmentally acceptable product that was as clean as the original
material while meeting the city’s gradation specs for street sand.
The pilot project was partially funded by a grant from the Federation
of Canadian Municipalities’ Green Fund. EWMCE is a North American
leader in developing, commercializing and providing training in sustainable
waste management technologies.
Through
its contract partner, Sand Recycling Ltd., of Edmonton, a research and
development program was carried out in 2004 at the Clover Bar landfill
site using a portable spread of newly-purchased screening and washing
equipment. The Sand Recycling team, led by John Mundy, formerly general
supervisor, Technical Services and Gravel Operations with the City of
Edmonton’s Transportation and Streets Department and now the private
company’s operations manager, started the pilot project with 70 000
tonnes of contaminated street sweepings. The recycling target was 65
to 75 per cent of reusable sand. After experimenting with several different
concepts and equipment configurations, Sand Recycling developed a five-phase
wet processing system. A dry processing alternative was rejected at
the outset due to the high cost of the equipment as well as concerns
regarding fugitive dust emissions from the processing operations.
Following
completion of the pilot project’s in September 2004, the results
revealed an 80 per cent clean sand recovery rate from the street sweepings,
10 per cent clean fine sand, 4.5 per cent contaminated fine sand, 4
per cent litter, and 1.5 per cent oversize gravel for reuse by the city’s
aggregate recycling program.
Aggregate
recycling program
Since 1980, the City of Edmonton
has recycled the concrete and asphalt and waste granular material
that is created when its roads and sidewalks are repaired or replaced.
The concrete and asphalt is crushed to 63 mm and 25 mm size and
then recycled for new roadway base and sidewalk construction.
In 2006, the concrete/asphalt recycling
program recycled 180,000 tonnes of base material for new roadways,
further contributing to the diversion of waste from landfill. |
Physical
testing of the recovered sand by the city’s laboratory did not
indicate any difference between the recycled and virgin winter sand.
Chemical analysis also indicated that most of the contaminants (salt,
hydrocarbons, heavy metals, etc.) contained in the fine sludge could
be removed for disposal in a Class II landfill. The success of the project
exceeded the city’s expectations by a substantial margin and clearly
showed that Sand Recycling’s process could recover and decontaminate
street sand to new sand specs at a cost well below market value for
new sand. Based on the technical and economic success of the initial
stage of the pilot, the city and EWMCE entered into a six-year agreement
to recycle more than 900 000 tonnes of street sweepings in Edmonton.
The
pilot project was expanded in 2005 to process some 115 000 tonnes of
street sweepings. A number of modifications were made to improve the
efficiency of process system and to further reduce the quantity of litter
and contaminated material directed to the landfill.
In
2006, Sand Recycling relocated its spread of portable equipment to Edmonton’s
Poundmaker Snow Storage facilities in the city’s west end. Here,
the plant produced approximately 120 000 tonnes of recycled street sand
from approximately 150 000 tonnes of sweepings.
According
to John Mundy, this is believed to be the largest street sand recycling
program in the world. The success of the project is generating annual
savings of more than $3 million for the city while reducing some 700
000 km of truck haulage from outlying sand pits. Fewer trucks on the
road hauling sand is lowering greenhouse gas emissions by up to 1400
tonnes per year. In addition, street sweepings are now being collected
from neighboring municipalities including the County of Strathcona,
the City of Fort Saskatchewan and the City of St. Albert.
The
revolutionary street sand recycling program has recognized by the Transportation
Association of Canada (Environmental Achievement Award) and by the American
Public Works Association - Alberta Chapter (Technical Innovation Award,
Project of the Year). It is also a key component in Edmonton’s
EcoVision program to protect the environment.
During
Aggregates & Roadbuilding’s recent visit to Sand Recycling’s
operations at the Poundmaker site, the plant was running at full capacity
processing a record amount of street sweepings. Last winter’s
severe weather saw 180 000 tonnes of street sand and salt spread on
city’s streets and parking lots to deal with the icy road conditions.
More than 140 000 tonnes were subsequently picked up during the sweeping
operations in April, May and June.
The
plant normally produces 1200 to 1400 tonnes of clean, decontaminated
street sand per day. Mundy states that the plant operates 11 hours a
day, seven days a week. The target is to run the plant 110 days a year
to produce around 150 000 tonnes of recycled street sand.
The
continuous processing operation begins with recovering the street sweepings
from a stockpile using a 3 m3 New Holland LW170 wheel loader. The loader
dumps the material into a 1.5 m dia. x 4.2 m long McCloskey 14R trommel
screen, fitted with 25 mm openings, which separates the sand and miscellaneous
debris from large litter. A second, larger New Holland LW230 wheel loader
equipped with a 3.6 m3 bucket, transports the sand and small size litter
discharged from the trommel to an ELRUS 7.6 m3 capacity variable speed
grizzly feeder. The material is conveyed from the feeder onto an ELRUS
7x16 triple-deck screen with 25 mm, 15.8 mm and 10 mm openings on the
top deck, middle and bottom decks, respectively.
The
top deck is used to remove litter such as leaves, twigs, wood, plastic
and metallic fragments including coins, keys and other small objects.
The plus 10 mm material retained on the second and third decks are taken
off and stockpiled for the city’s aggregate recycling program.
The minus 10 mm bottom deck throughs are conveyed to a pair of Ortner
Series 4000 material classifiers which wash and separate the coarse
and fine particles. Each machine is powered by a 15 hp electric motor
and has a capacity ranging from 108 to 190 tonnes/h. Sand Recycling
has configured each machine to achieve an output at the lower range
of the 4000’s capacity due to the unique nature of the application.
The
operating principal of the Ortner 4000 is fairly straightforward. Material
is fed to a slowly revolving pan on an incline and vibrated at high
speed. The high-speed vibration separates the various sizes of material
with the fines and water rising to the top and flowing over the pan’s
edge to the discharge. The coarser particles sink to the bottom. The
rotating pan carries the settled particles up the machine and out of
the water, where a stationary plow diverts the dewatered material to
a center discharge spout. The driving and vibrating mechanism is mounted
under the pan, preventing any contamination with the water and processed
material, thus increasing the life of the components. It is possible
to vary the angle, speed, and vibrations of the pan. This, claims the
manufacturer, gives the Ortner a wide range of flexibility and increases
its capacity and efficiency. Another advantage of the Ortner is its
relatively low water usage compared with a conventional sand screw.
The
overflow with the 300 micron material goes to a slurry box for further
processing while the clean sand is conveyed to two 6x12 Sizetec VDS410-4
intensive dewater screens that reduce the moisture content to approximately
10 per cent. The sand is stockpiled for additional drying by both gravity
and air. At the end of the 30 to 60-day drying cycle, the moisture content
of the stockpiled sand is less than 5 per cent.
The
slurry box material is pumped to four 254 mm diameter Krebs model DSF10LB
hydrocyclones that remove 75 per cent of the water. The remaining solids
are discharged onto a 4x10 Sizetec fine sand dewatering screen. The
resulting material is sold to mudjacking contractors or used as fillcrete.
The
plus 80 micron material goes to a Terex Finlay Siltmaster 45. The Siltmaster,
with the aid of a flocculent, allows the continuous removal of clay
and silt from waste water before it is discharged into the two seepage
bays. Each bay holds 300 tonnes of solids. Approximately 150 tonnes
of the material is removed daily by wheel loader to an adjacent field
where it is air dried to achieve a moisture content of about 30 per
cent. The material is then sold as landfill cover. Virtually all of
the 4.1 million l of water used per day in the street sand recycling
process system is recycled.
Mundy
estimates the cost of buying new sand and landfilling the street sweepings
was approximately $70/tonne. The winter street sand recycling program
has reduced costs dramatically to between $15 and $18 per tonne. Other
snow belt areas across western Canada faced have indicated interest
in the processing system. He adds that Sand Recycling is exploring marketing
opportunities to extend the company’s operations to these communities.
Key
personnel involved in Sand Recycling’s winter sand recycling project
are business manager Phil Haug and operations supervisor Jason Mundy
who is responsible for the day-to-day production activities.
Back
to top
September-October
2007 issue
Aggregates
and Roadbuilding Magazine
4999 St Catherine Street West.
Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca
|