Canada's “Rock to Road” Magazine


July-August 2007 Issue

For a copy of the issue that contains these articles with colour photos, click here.


New asphalt plant geared for b.C. growth

By Andy Bateman, Engineering Editor

     A new hot mix asphalt plant is in pole position to take advantage of the development boom in British Columbia’s Lower Mainland.

     Officially described as “Columbia Bitulithic’s Port Kells asphalt facility,” the plant is located some 35 km south east of Vancouver, on the south side of the Fraser River and close to Golden Ears Bridge project. The new set up includes a new stationary drum mix plant, high capacity raw material storage, multiple feed bins, bag house, finished product storage, control tower and truck load out, together with a batch tower transferred from Columbia Bitulithic’s decommissioned Coquitlam plant. Add extensive air and water quality protection measures as well as noise reducing equipment to that list for an impressive example of modern hot mix asphalt production technology.
     Larry Howorth, the company’s general manager of asphalt plants in the Greater Vancouver Area, explains that the new location was selected to take advantage of current and projected growth south east and east of Vancouver. “The plant is well positioned to meet the increased demand for asphalt in Surrey, Langley and Abbotsford south of the Fraser River as well as Maple Ridge north of the Fraser on completion of the Golden Ears Bridge in 2009. Having both drum and batch capacity provides full market coverage. High volume contracts can be supplied from the drum plant while smaller volume retail business or specialty mixes can be supplied from the batch plant. The batch plant also provides winter operating flexibility. Here in Vancouver we tend to keep our plants open pretty well all year round, shutting down only a few weeks for winter repairs.  On many of those winter days, the batch plant comes in very handy for mixing smaller loads of the various mixes, including cold mix, which is best produced in a batch plant for safety reasons.”
     In operation, aggregates arriving on site are stored in one of six storage bays, each with a capacity of 5000 tonnes. Reclaimed Asphalt Pavement (RAP) will be stored separately in a 2500 tonnes capacity bay. Material is recovered from these bays by wheel loader to charge a bank of eight cold feed bins or four RAP feed bins. Cold feed and RAP are conveyed to the plant separately, with both conveyor systems incorporating a 4x10 scalping screen to pre screen all feed material. Asphalt cement is pumped to the plant from one of three 120 tonnes capacity tanks. The hot mix plant itself teams an Astec Double Barrel drum mixer with a Phoenix Talon PT100 burner to provide a nominal aggregate drying capacity of 363 tonnes/h. Within the drum, feed aggregates are dried and superheated in the rotating inner dryer drum of the plant. The heated aggregates then discharge into the stationary outer shell of the plant where RAP, other additives and asphalt cement are added as required, with mixing provided by paddles on the outside face of the rotating inner drum. The resulting asphalt mixture is transferred via a drag conveyor and a silo top conveyor system into four product silos, each having a rated capacity of 270 tonnes, giving a total of 1080 tonnes of finished product storage. Underneath the product silos are two 41.2 m long Pacific Industrial scales, with each scale served by two silos. After loading, trucks pull forward to the end of the scale where the driver collects a ticket from a remote printer and heads for the job site.
     General plant superintendent Reynold Amey explains the thinking behind some key design aspects of the new operation. “Having eight cold feed bins compared to the four to six of many plants allows the mixing of an increased variety of aggregates. Some of these may be the same size though from a different location and therefore necessitating a separate mix design. This mix design flexibility is expected to become increasingly important as aggregate supply tightens and sources are changed more often. By the same token, having four recycle feed bins where most plants have only one or two will allow increased RAP usage through improved control of recycled asphalt cement and rock being added to new mix. This makes good business sense, as higher RAP content means significant cost savings from reduced virgin asphalt cement and aggregate demand. Stockpile covers are provided for RAP, sand and 7 mm minus materials, that is, feed materials containing fine sized fractions. These covers keep stockpiles dry, resulting in lower drying costs. At the same time, the covers also help control fugitive dust emissions, an area that is attracting increased regulatory scrutiny in addition to odours and noise. On that note, the Greater Vancouver Regional District (GVRD) required the entire site to be paved to reduce dust emissions, a good practice in any case to eliminate mud tracking or stockpile contamination in wet weather.”
     The extensive list of environmental protection measures continues. The asphalt cement (A/C) tanks are fully contained (along with a 6000 gallon diesel tank) and their vertical rather than traditional horizontal mounting conserves much needed space. Oil flow to the plant is controlled by air actuated valves on the A/C tanks, while vent condensers on the top of the each tank cool the exiting gases so that hydrocarbons in the gas stream are condensed and drain back down into the tank.
     On the plant, variable frequency drives on both the burner blower and the baghouse exhaust fan result in both electrical savings and a significant reduction in the noise generated by each component. As a result, it is possible to stand on the burner platform and carry on a conversation at normal volume with the burner firing at full capacity.
     Both odours and volatile organic compounds (VOC) emissions are minimized with the Double Barrel technology. The exhaust system that evacuates steam and products of combustion from the inner drum also evacuates steam and hydrocarbons from the mixing chamber. These are pulled back through the aggregate dropout holes and into the flame for incineration.
     The air emissions permit that Columbia Bitulithic was required to obtain from the GVRD included the company’s own request for a permit that would authorize a maximum of 47 tonnes of total emissions per year. By comparison, the Port Kells plant replaces two older plants that are currently authorized to emit up to 330 tonnes per year and current air emissions in the GVRD are in the order of 3.4 million tonnes per year, not including carbon dioxide. The plant will be fired by natural gas, with low sulphur diesel fuel as back up in accordance with the air quality permit.
     The baghouse is fitted with micro-denier capped Nomex bags providing much higher dust collection efficiency than standard bags. As a result, the baghouse is expected to emit less than 20mg/m3 of aggregate dust, or 50 per cent less than the current maximum outlet concentration requirement of 40mg/m3.
     The plant’s silo-top blue smoke package is designed to minimize odours and the escape of hydrocarbons associated with the filling of the product storage silos. Instead, captured hydrocarbons are ducted back to the dryer burner where they are injected into the flame for incineration.
     Surface runoff from the whole operation is directed to an oil/water separator, sediment pond, and water treatment system that chemically precipitates out and captures suspended solids, and includes a specially modified 12.2 m cargo container for the flocculent system. All run off water discharged from the site must be four times cleaner than the nearby Fraser River is today.
     Close attention has also been paid to the production process, with mix production automated by a PC based control system instead of panel mounted, push button control systems, thereby bringing all of the plant’s controls onto one computer screen. This system, together with closed circuit cameras at key process points, give the plant operator close control over mix selection, production and storage. During truck loading, the long scales mean that both tare and gross weights can be measured live, as even trucks with pup boxes are fully on the scale throughout the loading cycle. One scale is designated for internal customers and the other for external customers to provide faster service and trucking cost savings for all customers.
     Now hidden, the plant’s design and location also necessitated significant foundation works. Seismic (earthquake) concerns meant engineering for and placement of a total of 56 piles, some of which had to be driven to a depth of 33.6 m to support major plant components such as the silos, liquid AC tank farm, slat conveyor and drum mixer. The pile cap (concrete foundation constructed atop the piles) for the silos is 15.25 m. x 12.2 m x 1.22 m thick while a 225 tonnes capacity crawler was required to lift the silos themselves onto the foundation base plates. Despite these challenges, it took only 16 months from the beginning of the rezoning application to project completion and plant start up, with an actual plant construction period of just seven months.
     Columbia Bitulithic is a division of Lafarge Canada Inc.

Back to top


U.K. quarry show triumphs weather
     Hillhead – the world’s largest working quarry and heavy equipment show - attracted a near record crowd despite the heavy rains that inundated most of England in the weeks leading up to this year’s event. According to show officials, total attendance at Hillhead 2007, which took place June 26-28 was an impressive 18,500, slightly fewer than the record-breaking attendance at the previous show in 2005.
     The 450 leading international manufacturers and suppliers who took part in the biennial event at Tarmac’s Hillhead Quarry, near Buxton, Derbyshire, used 140 000 m2 of showground space to exhibit their latest equipment, machinery and services for the quarrying, recycling, heavy construction and related industries.
     The largest working and static exhibit was mounted by Terex Corporation whose various divisions introduced a wide range of new products including five new Powerscreen machines - the Chieftain 1700 and 2100X mobile screens, the Horizon 5163 mobile horizontal screen, the Finesmaster 120 compact dewatering screen and the Phoenix 3300 trommel. Terex’s Finlay unit used Hillhead to demonstrate their newly introduced C-1540 cone crusher and to launch the company’s new track-mounted 1-1310RS impact crusher. Also on show was a new Finlay MP300 mobile wash plant.
     Terex Pegson brought an array of their track-mounted machines to Hillhead including an XA400 hydraulic-adjust jaw crusher, a 1300 Maxtrak cone crusher, a 1412 Trakpactor and 1000SR cone crusher.
     The company also introduced its new XV350 track-mounted vertical shaft impact (VSI) crusher which represents a collaboration between US-based Terex Canica and UK-based Terex Pegson. The new machine, which features a Canica 2050 VSI packaged on a Terex Pegson tracked chassis, can produce a range of fine products at capacity of up to 318 tonnes/h. The 37-tonne XV350 is powered by a Caterpillar C13 Tier III ACERT diesel engine that is rated at 440 hp.
     Terex’s large two-storey hospitality suite provided a viewing deck for visitors to watch two Terex articulated haulers, a new TA30 with independent front suspension and a the top-of-range TA40, being loaded in the adjacent demo area by a TC240 hydraulic excavator and one of Terex’s new high-capacity TL450 wheel loaders.
     Volvo CE took advantage of Hillhead 2007 to include a number of compactors, pavers and cold milling machines from the newly-acquired road development business unit of Ingersoll-Rand alongside their lineup of heavy and compact construction equipment for the first time. Among the new Volvo CE machines at the show was the 50-tonne L350F wheel loader. The 6.2 m3 face loader, which replaces the L330E, features the latest Volvo D16E Tier III-compliant V-ACT diesel engine and a complete Volvo powertrain.
     Another major Hillhead exhibitor was JCB which showed the largest machine it has ever built, the 51.4 m long-reach JS460LR hydraulic excavator. Featuring an Isuzu 305 hp six cylinder turbocharged diesel engine, the JS460LR boasts an impressive 24 m reach. JCB also showcased its range of heavy-duty machines and specialized attachments tailored specifically for the quarrying industry. The machines displayed comprised hydraulic excavators (including the manufacturer’s flagship 46-tonne JS460), wheeled loading shovels, wheel loaders and articulated dump trucks. A new Tier lll JS255LC excavator was joined by a JS260XD demolition-spec’d excavator, 436 and 456 high-torque wheel loaders and 722 articulated trucks in the working area for live demos.
     The Sandvik exhibit at Hillhead 2007 offered visitors with their first opportunity in the United Kingdom to meet the various members of the Sandvik “family” since it was extended by the purchase of Extec Screen and Crushers Ltd. and Fintec Crushing and Screening Ltd. at the end of April. Sandvik used four separate stands at the show to display the company’s comprehensive range of equipment and solutions for all stages of the extractive industries from drilling, blasting and breaking, through crushing and screening, to recycling and reprocessing.
     Extec displayed a total of six machines, including the new S-6 Doublescreen and C-10+ jaw crusher. The S-6 incorporates a larger frame size, increased screen area and longer conveyors than the previous S-5 model, while the C-10+ has numerous advanced features designed to increase its versatility and durability.
Fintec unveiled its new track-mounted 1440 track-mounted impact crusher which is equipped with a feeder and separate two-deck pre-screen. Powered by a Cat C13 Tier lll-compliant engine and equipped with a Sandvik PR301D horizontal shaft impact crusher with a feed opening of 900 mm x 1360 mm, the 1440 offer throughput of 300 tonnes/h to 350 tonnes/h depending on the feed material. Fintec also introduced its newly redesigned 1080 track-mounted cone crusher.
     Canadian aggregate machinery manufacturer, McCloskey International Ltd. presented their 407, 512, 616 and 621 trommel screeners as well as their 123, 302, Kompaq flatdeck and Minisizer vibrating screeners at the company’s stand. Several McCloskey machines were also part of the live demonstrations including the newest product, the R155 High Energy™ three-way-split screener. According to McCloskey, the 16x5 top deck and 15x5 bottom deck screen boxes offer a full 14.39 m2 of screening area for maximum production in heavy screening applications. The R155 is designed to complement the company’s new S-Series flatdeck screeners. The R155 can handle primary screening for feeding a crusher while the S190 or S130 screen finished products.
     Metso Minerals showcased their new LT60 track-mounted mobile crusher and ST458 four-way-split mobile screen. The LT60, which forms part of the company’s newly upgraded range of track-mounted mobile crushers, can generate up to 500 tonnes/h, while the ST458 offers a maximum throughput of 400 tonnes/h.
     Other major manufacturers exhibiting and/or demonstrating machines at Hillhead 2007 included Finning/Caterpillar, Komatsu, Liebherr, Atlas Copco, Hazemag and Cummins.
     Established in 1982, the Hillhead show is organized by QMJ Publishing Ltd.

Back to top


Successful B.C. quarry adapts to remote location
Adaptable employees and a flexible production process are behind the long term success of a remote B.C. quarry.

By Andy Bateman, Engineering Editor

    The Jervis Inlet operation of Jack Cewe Limited is located on B.C.’s Sunshine Coast, some 100 km north west of Vancouver and accessible only by water. Location has certainly not prevented its solid growth however, with 700 000 tonnes of aggregates shipped annually to customers in B.C’s Lower Mainland, Alaska and other North American coastal markets. The operation must also a strong contender for record distance shipped, having supplied aggregates to a U.S. airbase on Wake Island, a Pacific atoll located over 7000 km from the Sunshine Coast. Plant manager Mike Dusenbury explains that the operation’s successful development over many years can be attributed to two main factors; the people working there and a flexible production process. For employees, cross training and the ability to perform multiple jobs are the norm. On the process side, a versatile set up allows a full range of aggregates to be produced in response to changing market demands.
     Officially known as the Treat Creek Pit, the operation’s ability to produce a wide product range is due in part to the availability of two distinct raw materials. A consolidated granite outcrop and an unconsolidated granitic sand and gravel deposit are both worked here, with key elements of the production process reflecting the dual sources. A primary jaw crusher reduces shot rock from the quarry as well as oversize from the pit, while a separate wash plant produces a range of washed aggregates from the pit deposit.
     Downstream of these two plants, the majority of material processing takes place at the secondary plant, known on site simply as the crusher and utilising material from jaw and wash plants as feedstock. The secondary plant circuits integrate three screens, two vertical shaft impact crushers and two flow control splitter boxes to make a wide range of cubical (well shaped) products.
     At the time of Aggregates & Roadbuilding’s visit, raw material was being extracted from the quarry and pit at the same time. In the quarry, drilling and blasting contractor Pacific Blasting was utilising a tight blast pattern to maximise the yield of 89 mm minus product for a specific customer.
     After blasting, shot rock was loosened and baled out by a John Deere 450D LC excavator before loading and hauling to the plant. Meanwhile, pit run in the sand and gravel deposit was being loaded a Caterpillar 988H wheel loader, with some pre-sorting to cast out boulders larger than 750 mm. The pit run was then hauled to the plant by two Caterpillar 730 articulated dump trucks (ADTs), with a smaller Caterpillar D250 ADT added to the haul fleet when required.
     At the plant, the trucks dumped pit run into a feeder hopper with grizzly bars set at a 102 mm opening. Material passing through the grizzly was conveyed to the wash plant where a Deister 8x24 dry screen first separated the feed at 25 mm. Material larger than 25 mm was conveyed to the secondary plant surge pile, while material smaller than 25 mm was conveyed to the wash plant surge pile. Material drawn from the wash plant surge pile was then directed over the wash plant’s Deister 8x20 rinsing screen separating three washed coarse sized products; 25 mm concrete rock, 12.7 mm washed rock and 4.8 mm birds eye stone.
     The sand (minus 4.75 mm) fraction passing the wet screen’s bottom deck was directed to a Kolberg computer-controlled classifying tank producing concrete sand and a by-product sand, the latter being used directly in dyke construction or blended into crushed aggregate base. Back at the raw feed hopper, large pieces up to 750 mm retained on the grizzly were conveyed to a separate stockpile and from there loader fed into the same Hewitt-Robins 3048 primary jaw that was crushing quarry shot rock. The resulting 152 mm minus crusher run was conveyed (together with the 102 mm x 25 mm material from the wash plant) to the secondary plant surge pile.
     At the secondary plant, material from the surge pile passed over a Telsmith 6x16 double-deck screen from which 76 mm minus was stockpiled as finished product and 152 mm x 76 mm oversize was conveyed to a Terex Canica 125 Vertical Shaft Impactor (VSI). The 76 mm minus well graded crusher run from the VSI was directed to a splitter box. This splitter box allowed the plant operator to direct the material to a second Telsmith 6 x 16 Telsmith double-deck screen separating 25 mm minus, a Deister 8x24 triple-deck screen or a combination of the two screens.
     Material going to the Deister screen was separated into 9.5 mm crusher dust (100 per cent crushed), 25 mm crushed clear and 12.7 mm crushed clear finished products and stockpiled. At the same time, oversize from the Deister screen was directed to a Terex Canica 2350 VSI. In this circuit, crusher run from the 2350 discharged into a second splitter box which allowed the operator to control material flow rates back to the Deister screen, the 125 VSI or a combination of both. Material handling duties on site were completed by a Caterpillar wheel loader fleet that included two 980G’s, three 988B’s, a 966G, a 988H and two 980B’s. Excavation work was completed by the John Deere 450D LC or a newly-arrived Hitachi 270LC-3 excavator.
     Dusenbury adds that water-only access certainly adds operational challenges that might not suit some. “With no nearby communities, all our plant operators get here by crew boat each day from a dock near the village of Egmont. So, whether it’s a belt repair or operating a different piece of equipment, it’s important that our people know how to keep things running. Over the years, we have designed and built most of this plant ourselves and, during that time, many of our operators have learned plant repair and maintenance as well as equipment operation.
     A similarly flexible approach is essential for other people on site, such as our drilling and blasting contractor, who may have to deal with special or new situations. In terms of supplies, there is regular barge traffic leaving here with product and arriving with supplies and heavy equipment on an as needed basis. However, deliveries can take several days, so we maintain an inventory of critical spares and consumables at all times. To illustrate the point, we have two 1000 kW generator sets plus two smaller units to supply electricity here, as mains power transmission is not a practical proposition. To keep those generators and all the mobile fleet running, we have diesel fuel storage capacity totalling 48 000 gallons, or much more than would normally be stored by an urban operation of comparable size.”
     Similar adaptability is apparent in the production process. The wash plant and secondary plants each have their own surge pile of feed material to allow independent operation when required. In addition, a number of the operation’s finished product stockpiles are located over a long reclaim tunnel to facilitate barge loading and final product blending if required. As a final process step, a rewash screen circuit at the end of the product reclaim conveyor allows certain products to be rewashed prior to barge loading.
At the secondary plant, the screen, splitter box and crushing circuits provide a high level of control over the percentage of crushed surfaces in the finished product. Dusenbury adds that other quarry operators were highly sceptical when Cewe first installed VSI’s at the Jervis Inlet location, expecting rapid wear rates in the abrasive granite. However, these crushers have now been in service for several years and, according to Dusenbury, deliver very good finished product shape with few flats and elongations at reasonable unit wear cost.
     The addition of the large Deister 8x24 screen into the VSI circuits was also a good move, as it has significantly increased the production rates for smaller sized products. At the wash plant, the current range of coarse and fine sized products contain only natural rounds (absent any crushing) so are well suited for concrete production. That could change with changing specifications if, for instance, the operation was called upon to make a manufactured sand having 100 per cent crushed surfaces. In that event, the Jervis Inlet team would no doubt find ways of adding crushing capacity to the wash plant circuit.
     According to published industry literature, VSI’s can deliver high output tonnage, portability, versatility, cubical particle shape and accept larger feed sizes than other finishing crushers, all at relatively low capital cost. Another group of producers utilise VSI’s to beneficiate otherwise good deposits containing soft or friable material. Like all equipment, some care is needed to ensure the application is appropriate for a VSI. These crushers are sensitive to oversize feed, tramp metal, and overspeed, all of which can damage their hard but relatively brittle high chrome iron or tungsten carbide wear parts. Contrary to popular belief, medium or higher feed abrasiveness does not necessarily rule out the use of a VSI. Wear rate is influenced by the silica content of the feed, the accepted guideline of abrasiveness, as well as other factors such as moisture content, impeller speed and tonnage.
     
Advance sampling is always recommended to select the best crushing chamber for a particular application and confirm that the cost of wear parts will be reasonable. The Terex Canica 125 VSI at Jervis Inlet has a rated maximum feed size of 203 mm. Its maximum throughput capacity and impeller speed are 680 tonnes/h and 1050RPM respectively, with both dependant on feed size. Recommended motor size is 700 hp.The somewhat smaller Canica 2350 VSI has a maximum feed size of 152 mm and a maximum throughput capacity of 544 tonnes/h. Its power requirement for maximum throughput is 500-800 hp, depending on application.

Back to top


Riding the development wave

Paving contractors in British Columbia’s Fraser Valley are being kept busy by the region’s development wave.

By Andy Bateman, Engineering Editor

    Superior Asphalt Paving Ltd. is a familiar name in the Fraser Valley contracting world. This established mid-size paving contractor has 30 experienced employees and, equally important, a solid reputation for quality paving on commercial, industrial and residential paving contracts from facilities in Langley, Abbotsford, Chilliwack, Maple Ridge and Vancouver. Superior’s Harvey Lalli confirms that the company’s order books are being kept full by the region’s solid growth which, if some of the latest development statistics are anything to go by, seems set to accelerate still further. (See Langley industrial permits break annual record in six months).
     Aggregates & Roadbuilding saw the company’s crew in action on a recent commercial paving contract in Langley. This particular job was located on Highway 10 in Langley, where Superior was paving the forecourt of the new Wolfe’s Langley Mazda dealership as subcontractor to Teck Construction Ltd.
     Mainline paving crews in particular will appreciate the challenges of achieving a smooth tight mat on a job with runs as short as 5 m, frequent changes of direction, tight space, several wedge shaped infills, hand work and numerous joints. Before paving, the relatively deep base under the surface mix included 300mm of pit run and 150 mm of granular base material. Lalli explains that base material is typically laid to this thickness in the area to avoid soft spots. Once the base material was compacted, hot mix asphalt supplied by Imperial Paving Ltd. was placed and compacted to a finished thickness of 50 mm by a LeeBoy 8515 conveyor asphalt paver. Compaction equipment working with the paver included Ammann AV16K and AV12 tandem vibrating rollers as well as a Caterpillar CB335E compactor.
     Superior Asphalt Paving’s fleet of four pavers from the LeeBoy range includes one 8816, two 8500’s as well as the 8515 used on this contract. Specifications indicate that the 8515 conveyor asphalt paver weighs 7.2 tonnes, has a 2.44 m to 4.6 m paving width and is powered by a 74 hp Hatz silent pack engine. Its specifications include a 6.8 tonnes capacity receiving hopper, dual 914 mm wide conveyors and 305 mm diameter augers with sonic auger controls. The heavy duty vibrating Legend screed is equipped with electric heating as an option, while its 1067 mm front-mounted hydraulic screed extensions are said to be easily adjustable to deliver a seamless mat. Manufacturer’s data adds that cut-off plates enable varying paving widths as small as 305 mm and as wide as 4.58 m. The 8515 is available with high deck or low deck dual operator stations in which a joystick controls forward and reverse electronically and the operator has electronic steering controls from either side of the paver. Electronic mat control options include single electronic grade control, electronic grade control, grade & slope control and laser tracking. The heavier 8816 weighs 11.3 tonnes and is powered by a 130 hp Cummins engine. Its specifications include a 9.1 tonnes capacity receiving hopper, twin 457 mm independent slat conveyors and 356 mm variable speed augers with independent auger and conveyor control.

Back to top


The value of intelligence
How documentation from intelligent Compaction saves money - now and later

     Success and confidence are two entities that usually go hand in hand. Whether it’s a football team, a multi-million dollar corporation or a road contractor, very rarely does a person or group succeed without first having the confidence to believe that success is possible. Conversely, having overconfidence in a faulty premise can often lead to failure.
     Contractors specializing in soil or asphalt compaction could probably talk a lot about confidence and success, depending on their individual experiences. What they might say is that confidence comes in varying degrees.
     Until recently, a contractor’s confidence relied entirely on the expertise of a roller operator, in combination with density tests taken from random positions on a job site. After completion of several successful projects, a contractor’s confidence would justifiably grow. But even with the best work done by the best workers, there was simply no way to know for certain that optimum compaction had been achieved over the entire area of a project.
     From time to time, projects failed due to improper compaction of a surface or sub-base. And in the construction business, failure can mean having to redo small or large portions of a project, leading to wasted time and expense.
     It would be ideal for a person in any profession to possess a tool that could help guarantee success. Fortunately for contractors in the compaction business, there is such a tool in the form of rollers with Intelligent Compaction systems. This technology has just begun to take off in the United States in the past several years, and for good reason, because it gives the contractor 100-percent confidence that the job was done correctly. A closer look at Intelligent Compaction will illustrate exactly why the system is so valuable.

Consistent, uniform results
     To fully appreciate the advantages provided by Intelligent Compaction, it’s important to first understand the fundamental differences that the technology presents in comparison with standard rollers. Work on a job site begins much the same way with or without Intelligent Compaction rollers. Both situations may involve making successive passes with a roller over a test strip or test lane of material. A nuclear or non-nuclear testing device is then used to determine if the specified density for that particular job has been achieved. But in terms of what the two roller types are trying to accomplish with this process, the similarities end there.
     When using a basic roller, the test procedure is intended to define the maximum number of passes needed to achieve proper compaction, with the assumption being that if there is no deviation in the material and from that rolling pattern and operating speed, the same end result will be achieved throughout the entire project. With Intelligent Compaction, the initial control test is not performed to establish a set number of necessary passes to be made, but rather is used to determine an energy measurement that correlates with the specified density to be achieved over the whole area.
     As it moves along the work surface, an Intelligent Compaction roller measures vibratory energy reflected from the material being compacted. The energy numbers attained have a direct correlation with density readings from a proven testing device. Most Intelligent Compaction systems include some form of visual display that shows stiffness measurements as the roller moves over the material. All the roller operator has to do is achieve the same energy value from the material over the entire surface.
     A conventional roller isn’t able to give any quantifiable feedback, so the operator must rely on observations and experience to make compaction as uniform as possible. And in many cases today, unseasoned roller operators are often forced into duty, making it more difficult to achieve consistent compaction. Once the job is complete, density tests are taken manually from randomly selected positions. Because the testing is random, it is impossible to guarantee uniform or proper compaction over the entire job site. Even if every tested position was compacted properly, there’s no way of knowing if soft spots exist in other locations.
     This is in sharp contrast to an Intelligent Compaction system, which monitors the compaction process consistently over 100 per cent of the area that’s being compacted. Whether it’s a 40-year veteran or a first-time roller operator, no guessing is needed. The operator actually knows when proper compaction has been achieved in any given location.

Smarter than the average roller
     Intelligent Compaction systems have the ability to achieve consistent, uniform compaction because they are intuitive machines. In fact, the design of the system requires that it be built into the roller to function because it is the roller itself that monitors the vibrational energy, or stiffness, of the compacted material. Material stiffness equates directly to density. And based on the stiffness readings that the machine receives, it will automatically adjust the output energy that the roller’s drum is putting into the work surface. The roller makes this adjustment through a process called vectoring, which involves changing the angle of the energy delivered from the drum. For softer areas, the drum will direct energy at a straight vertical angle. As the material stiffens, the roller directs the drum’s energy at a more horizontal angle, eventually becoming fully horizontal as the surface reaches optimum compaction. By delivering the appropriate levels of compactive effort into the material at all times, Intelligent Compaction not only ensures that the required density is achieved, but also prevents material from being over-compacted.
     Over-compaction can be just as problematic as under-compaction. Once the material has achieved maximum density, continuing to deliver additional force can be destructive and cause the material to lose density. The feedback from some Intelligent Compaction systems will let the operator know that enough work has been done on a given area. For other systems, the roller adjusts force automatically even if the operator isn’t paying attention.
     In addition to avoiding the damaging effects of over-compaction, Intelligent Compaction also prevents roller operators from wasting time in areas that no longer need attention. Knowing exactly when to stop allows the operator to move on to another part of the surface where further compaction is needed. For a contractor, this immediately translates into cost savings for labour and fuel, and it also prevents unnecessary wear and tear on the machine.
Intelligent Compaction rollers can expedite jobs even further because the system’s design allows it to physically produce more energy.      Conventional rollers have a dual amplitude system and are essentially limited to two different force values that can be delivered. Only one amplitude is available on Intelligent Compaction systems, but it is a higher amplitude that produces more force. Unlike a conventional roller, Intelligent Compaction uses the vectoring process to regulate how much of that force is actually delivered to the material. The roller is not limited to one force value, but rather can adjust to any value necessary.
     In some cases, rollers with Intelligent Compaction will produce up to 30 per cent more centrifugal force than their counterparts without the technology. Putting 30 per cent more energy into the material means achieving density about 30 per cent faster. For example, a job that previously took 10 passes to achieve proper compaction could potentially be completed in only seven passes.
     Depending on the job and the material to be compacted, the higher energy output provided by an Intelligent Compaction roller could also allow for compaction of thicker material. Being able to place deeper lifts in fewer layers is another way for a contractor to save time and money.
     With fewer passes required to compact the work surface – or greater lift depths that can be placed and compacted – Intelligent Compaction rollers can achieve the end result much sooner, allowing the operator to move forward to other areas of a project.

Standing by your work
     The day-to-day cost savings that Intelligent Compaction affords a contractor certainly help to justify the cost of purchasing the more expensive system. But also important is what the technology provides to the contractor well after the last day of the job. Intelligent Compaction systems not only monitor the compaction process for the purpose of adjusting to changing densities of the material, but they also provide documentation of the work done over 100 per cent of the project.
     This documentation can be stored electronically or printed on a piece of paper. The printout shows the travel speed of the machine, the distance traveled, the force value produced by the machine, and the compacted material’s vibrational energy reading. But more than simply showing raw data, the information illustrates a progression of compaction results achieved throughout the project. This gives the contractor documented proof to qualify that the work was done correctly in the event that other problems are discovered at a later time.
     In the case of a failed road, excavation could determine the exact cause of the failure. If it’s found that a certain area did not receive proper compaction, the contractor could be held at fault if he can’t prove the job was done correctly. If a roller without an Intelligent Compaction system was used, the only available documentation is the random density testing from the site. And if the failed area wasn’t tested, the contractor could be held financially responsible for every aspect of the road’s repair.
     The performance and accuracy of Intelligent Compaction has earned the technology high credibility in the construction business. Documented results from Intelligent Compaction systems are widely accepted by departments of transportation at the federal and state levels. In situations where a warranty issue comes into question or goes into litigation due to some sort of later failure on a project, contractors have the ammunition to show that their end of the job was done correctly.

Value on many levels
     A contractor’s job will never be stress-free. With looming deadlines and unexpected setbacks, there will always be some reason for concern. But Intelligent Compaction can alleviate several of those worries and provide versatility in the process.
     An asphalt contractor could utilize the technology to test the density of an existing road or previously compacted base before placing and compacting asphalt, providing further insurance that a project will succeed. Intelligent Compaction also allows a contractor to work in a variety of different materials and applications, creating more opportunities for profit.
     Getting good value out of a product isn’t always easy. But Intelligent Compaction systems take care of this on their own by providing the ability to produce improved, uniform results. And the subsequent profits, labour savings and the insurance of documentation all create direct monetary benefits for the contractor.
     It’s these benefits and the end result of proper compaction being achieved over 100 percent of the job that make for a truly confident contractor. And with that full confidence firmly in place, success is sure to follow.

Back to top


Heavy Construction Show reflects western growth

Billed as Western Canada’s biggest show for the heavy construction industry, the 9th biennial Heavy Construction Show was a big hit with visitors, manufacturers and distributors.

By Andy Bateman, Engineering Editor

     The Heavy Construction Show targets those involved in construction, public works and road maintenance, with the 2007 exhibitor list totalling 125 suppliers of equipment, accessories, wear parts and support services. This approach certainly seems to be working, with show growth mirroring strong industry growth in the Western Canada. Organizers report a 25 per cent increase in attendance for 2007, with a total of 5615 visitors over the course of the two day event, held June 1-2, 2007 in Abbotsford, B.C. The static part of this year’s show was held at the Tradex exhibition centre at Abbotsford International Airport, while a simultaneous live equipment display was held at the nearby “Demo Zone”. According to its promoters, it is this two-shows-in-one format that sets the Heavy Construction Show apart by giving visitors the opportunity to both view and operate new equipment.
     While some preferred to take a close look at exhibitor offerings in the comfort of the Tradex exhibition halls, excellent weather spurred most to take the 7 km shuttle bus ride to the 25-acre Demo Zone. Here, visitors lined up to operate equipment in a specially prepared terraced area that provided a good simulation of working loose material in a pit or excavation application. With perhaps 40 machines working at any one time, the impressive outdoor show included several excavators from most major manufacturer’s product lines, with dozers, skid steers, ADT’s and special attachments rounding out the action scene.

Back to top

July-August 2007 issue

Aggregates and Roadbuilding Magazine
4999 St Catherine Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276

EMail: rocktoroad@sympatico.ca