|
Canada's Rock to Road Magazine
March/April
2006 Issue
For a copy of the issue
that contains these articles with colour photos, click
here.
Ontario
Paver of the Year 2005
Pioneer
Construction wins Ontario 2005 Paver of the year Award
By Andy Bateman, Engineering
Editor
Every
year the Ontario Ministry of Transportation (MTO) recognises quality
roadbuilding in each of the ministry’s five regions, with one
winner receiving the prestigious Paver of the Year Award. The awards
for 2005 were presented during the 79th Annual Ontario Road Builders’
Association Convention, held at the Fairmont Royal York Hotel in Toronto
on February 6-8, 2006.
The winner of the 2005 Paver of the Year Award
was Pioneer Construction Inc., for outstanding work on MTO Contract
2004-6009 in the MTO’s Northwestern Region. Pioneer’s Thunder
Bay Operations won the 15.5-km long pavement rehabilitation contract
on Highway 11/17 between Thunder Bay and Nipigon, from 0.1 km east of
the Highway 527 Junction and extending easterly for 15.5 km. The scope
of work included the construction of a westbound truck climbing lane,
an eastbound passing lane, culvert replacement, grading, drainage, granular
base and hot mix paving for a total contract value of $8.9 million.
Work started in October 2004 and was completed in
September 2005. Pioneer’s successful project team included district
superintendent Chris Bowles, project superintendent Mike Howard, quality
control administrator Michelle Hagen and general manager Fred Hakala.
Like all contracts, this one had its challenges.
Hakala reports that heavy snow followed by spring flooding hampered
the opening of a new MTO quarry, earmarked as the contract’s source
of aggregates and location of its portable asphalt plant. On site, one
of the job’s biggest challenges was heavy traffic volume. According
to Phil Annett, the firm’s vice president for Northwestern Ontario:
“This particular stretch of the Trans-Canada Highway has the combined
traffic from both Hwy 17 and 11 and as a result created enormous challenges
in accommodating the traffic volumes during construction”.
In a co-operative effort with the MTO and the contract
administrator, Thunder Bay Testing, Pioneer undertook to perform the
majority of the paving operations at night — an operation generally
limited to multi-lane 400 Series highways in Southern Ontario, with
the switch from day to night time paving achieved within three days.”
In terms of paving, Hakala adds: “The relatively thick asphalt
lifts – a 75 mm binder course lift of Superpave 19 and a 55 mm
surface lift of Superpave 12.5 – also posed some initial challenges,
although Pioneer’s site team soon learned the right temperature
and correct time to get on the mat and achieve the required compaction.
Site conditions placed additional demands on the crew,
including the need to maintain a safe construction site, high traffic
volumes, night time work and the maintenance of erosion control measures
to minimise environmental impacts.” A number of subcontractors
contributed to Pioneer’s success. Roto-Mill Services Ltd. completed
pulverizing while Royel Paving Ltd. carried out tack coat and granular
sealing work. Drilling and blasting was done by Acadian Drillers and
Northwest Lines completed line marking. Wilco Landscaping did guide
rail, channel realignment, and landscaping work.
In terms of equipment, hot mix asphalt was supplied
by a 200-tonne/h capacity Astec Six Pack portable plant located in the
MTO’s Loon Pit No.1. Pavement milling work was completed by a
Caterpillar PM-565B cold planer, achieving an average production rate
of 100 tonnes/h. Pioneer’s paving train included a Roadtec SB-2500
Shuttle Buggy feeding a Caterpillar AP1055D paver equipped with a Topcon
averaging ski, while the compaction train included Caterpillar CB534D
XW, PS300B and Dynapac CC42 rollers making four passes each to achieve
densities of 93-94 per cent.
Material quantities included 54 831 tonnes of hot
mix asphalt, with 28 042 tonnes of Superpave 12.5 mm mix and 26 789
tonnes of Superpave 19 mm mix. The mix designs utilised Performance
Grade Asphalt Cement (PGAC) 64-34 from McAsphalt Industries and Redicote
82-S anti-strip agent. Fine and coarse asphalt aggregates were sourced
from the MTO Loon pit where crushing was completed by Gilbertson Enterprises
Ltd.
The Loon pit also provided some 25 200 tonnes
of Granular B Type II, while 95 900 tonnes of Granular A was sourced
from the Pioneer Mt. Baldy pit, again crushed by Gilbertson. Additional
material quantities included 35 100 m3 of earth moving, 21 000 m3
of rock excavation, 95 900 tonnes and 25 200 tonnes, respectively, of
Granular A and B Type 3 base material, 150 000 m2 of pulverizing, 10
000 tonnes of milling as well as culverts, pipe liner, channel realignment
and erosion controls.
The 2005 Central Region award was won by Graham Bros.
Construction Ltd. for its performance on MTO Contract 2002-2000 in Mississauga.
This contract included paving and new lane construction on the eastbound
and westbound lanes of Highway 401 from Renforth Drive to Highway 427,
as well as the demolition, replacement and widening of the bridge structure
carrying Highway 401 over Highway 27.
Additional work included the installation of thirty-six
high mast lighting poles and Advanced Traffic Management Systems (ATMS).
Valued at $24 million, the contract began in July 2002 and was completed
in December 2005, with the 42-month contract time line driven by complex
structural work.
Those closely involved in the job included Graham’s
superintendent Mark Thompson, general manager Alfredo Maggio, vice president
operations Carl Graham, operations manager (Asphalt Division) Murray
Graham, as well as Jim Vanbiesbrouk of the MTO and Terry Choo-Kang of
contract administrator Morrison Hershfield.
This job presented a number of unique challenges to
its builders. On the structural side, two existing bridges carrying
live 401 traffic had to be supported during their sequential removal
and reconstruction, a reportedly unique approach that required considerable
planning and engineering as well as a rigorous proposal and approvals
process.
On the paving side, work was done on one of the narrowest
and busiest sections of Highway 401 in the Greater Toronto Area. This
stretch has no collector lanes and, until its reopening, had only three
express lanes each direction. No mainline closures were allowed during
the daytime, while daytime construction access to mid-road closures
was restricted due to potential traffic congestion. All mainline repair
work and paving was done at night. In order to keep the 401 open during
the day, the job also called for fast-track concrete patching, a process
that required close coordination between concrete supplier James Dick
Concrete and Graham Bros. Thompson explains: “The 401 pavement
here includes asphalt on top of concrete. Once the existing asphalt
had been milled off, a Falling Weight Deflectometer (FWD) was used to
test and identify areas of concrete requiring replacement.
“The replacement involved the cutting
and removal of concrete sections, dowel drilling and installation into
adjacent sections, plus the pouring of new concrete, all in a four-hour
window. Road closures were allowed from 10 pm to 6 am, with penalties
for late opening. This meant that the new concrete had to be in place
by about 2 am each night to allow sufficient time for it to gain strength
and take traffic loading by 6 am. The approach worked well in practice
as we obtained high early concrete strengths of up to 20 MPa within
four hours.”
When it came to asphalt paving, it was found that
the allowed closure times were not long enough to be productive during
weeknights. As a result, almost all the top course paving was done over
two weekends on Friday and Saturday nights. To meet the echelon paving
specifications and keep longitudinal joints to a minimum, the shoulders
were paved first then the longitudinal joint ramp was removed to allow
two full lane paving per shift.
It was found that the job required two full seasons
of night work for the fast track concrete repairs and paving, along
with daytime work on structures and road widening in order to keep on
schedule. All in all, the job schedule required work to continue around-the-clock
for six days each week in the summer seasons.
Asphalt mix design changes also impacted on Graham,
with the contract’s surface course asphalt originally specified
as Dense Friction Course (DFC), but later changed to Stone Mastic Asphalt
(SMA) by the MTO. As this was Graham’s first experience with SMA,
the change triggered the addition of a new mineral filler silo, a 136
000-litre capacity upright AC tank and Krendl Fibre metering machine
with a Merrick Controller to the company’s Brampton asphalt plant
set up.
The Graham team attributes the contract’s success
to co-operation and communication between contract administrator Morrison
Hershfield, the MTO and Graham as prime contractor, as well as excellent
planning and scheduling of daytime, night-time and subwork crews. Another
likely factor is Graham’s depth as a vertically integrated construction
materials and contracting business able to draw on an extensive operational
team and equipment fleet.
Aggregates were supplied from a company
pit, among others, while hot mix asphalt was produced at the company’s
plant, delivered by company trucks and paved with company equipment.
Specifically, hot mix asphalt for the job was produced by a 400-tonnes/h
capacity double barrel drum/ batch plant located in the company’s
Brampton yard. The asphalt was delivered to site by a mixed company
truck fleet that included Mack five-axle live bottom units each hauling
43 tonnes, Kenworth and International tri-axle and pup units hauling
47 tonnes as well as Mack and Western Star tri-axles carrying 24 tonnes.
On site, milling equipment included Terex CMI
PR 800-7 and Roadtec RX60B cold planers as well as a smaller Ingersoll
Rand MW175. The company’s paving train included a Roadtec SB-2500C
Shuttle Buggy feeding Caterpillar AP 1000 B and Roadtec 180-10 pavers
working in echelon. Breakdown compaction was completed by two Caterpillar
CB634 units followed by a Hamm GRW18 pneumatic roller in the secondary
position and a Caterpillar CB534C finishing roller to achieve overall
Mass Relative Density (MRD) densities of 92 - 96 per cent.
The contract called for a number of asphalt
mixes totalling 51 400 tonnes including 17 000 tonnes of HL8 mix combined
Performance Grade Asphalt Cement (PGAC) 58-28 with internally supplied
fine aggregates, coarse aggregates and 20 per cent reclaimed asphalt
pavement (RAP). The contract’s Heavy Duty Binder Course (HDBC)
totalled 16 000 tonnes and combined PGAC 70-28 with high stability sand,
HL3 stone and 19 mm clear stone from Dufferin Aggregates. The 4 400
tonnes of Dense Friction Course (DFC) combined PGAC 70-28 with fine
and coarse aggregates from Lafarge Canada’s Coldwater quarry.
The SMA mix totalled 14 000 tonnes and
combined PGAC 70-28 with fine and coarse aggregates from Ontario Trap
Rock, filler from Carmeuse Lime and cellulose fibres from High Tech
Asphalt Solutions. Asphalt cement for all of these mixes was supplied
by McAsphalt Industries, while the SMA mix design was completed by DBA
Engineering. Additional material quantities included 58 000 tonnes
of Granular A and 19 000 tonnes of Granular B road base materials, both
from Grahams’ Caledon pit.
Concrete was supplied by the Etobicoke
plant of James Dick Concrete and included 3 000m3 of 30 MPa mix and
1 000 m3 of 35 MPa Fast Track Concrete. Additional job quantities included
18 000 m2 of base widening, 3 300 m2 of full depth base, 700 m
of sewers, 120 000 m2 of asphalt removal and 6 200 m of barrier wall.
The MTO’s Eastern Region Award was won
by R.W. Tomlinson Ltd. for hot mix paving and safety improvements on
Highway 416 in Ottawa from Fallowfield Rd North to Hunt Club Rd. Contract
2004-4011 was 7.3 km long and valued at $2.948 million. Work lasted
from July 13 to November 15, 2005 and included grading, milling and
hot mix paving as well as the installation of various safety measures.
Tomlinson’s Bert Hendriks explains
that the work had to be done at night in a rural area, with the absence
of streetlights creating potential safety issues and a big demand for
portable lighting equipment. In addition, the paving crew had to be
trained to be much more aware of small blemishes in the asphalt surface
that would be more visible in better light conditions.
The job was also the first Tomlinson project
where a single lift of asphalt was paved on a milled surface and payment
made by the square meter rather than by the tonne. In this situation,
Hendriks emphasises the importance of site teamwork between the site
crews, project engineer Garry Carriveau and field project manager Gary
McLaurin. “Good teamwork by our employees is an essential aspect
any successful project, especially where milling is done by our own
grinding crew. This provides more flexibility as well as the ability
to try some innovative ideas that a subcontractor couldn’t do
for you.” Still on teamwork, Hendriks notes that “MTO staff
worked in partnership with the contractor on this job and made many
things happen. Area construction engineers such as Ken Polson took the
project to heart.”
The job was not without its challenges however,
including an MTO switch from day paving to night paving. The effect
of this change was felt in October when low evening temperatures “started
to play havoc” with asphalt compaction. After discussion with
the MTO, a single warm 24-hour period was selected in which 5300 tonnes
of Superpave 12.5 mm FCII Category D mix friction course mix was paved
non-stop. This mix was produced by Tomlinson’s 3630-kg capacity
Barber-Greene batch plant, equipped with three product silos and a lime
mixing system.
The same plant produced a total of 19 000 tonnes
of Superpave 12.5 mm FCII Category D mix for the contract, while a 360-tonnes/h
capacity Gencor drum mix plant supplied 9 500 tonnes of Superpave 12.5
mm RAP mix.
On site, Tomlinson’s paving train consisted
of a Roadtec SB-2500 Shuttle Buggy feeding a Cedarapids CR451 Stretch
20 paver, while compaction was completed by a Bomag BW205 double-drum
unit, a Caterpillar PS 300B rubber tired roller and a Bomag BW164 vibratory
finishing roller. Advance milling was completed by a Roadtec RX60B cold
planer that had been modified to obtain smoothness on the first machine
pass.
Performance grade asphalt cement for the hot mix asphalt
mixes was supplied by Bitumar (Hamilton) Inc., with PGAC 64-34 and PGAC
58-34 utilised in the Superpave 12.5 mm FC2 and Superpave 12.5 mm RAP
mixes respectively. Dolomitic sandstone skid resistant aggregates for
the friction course were supplied by Tomlinson’s Rideau Quarry,
while the company’s Moodie Drive quarry supplied other asphalt
aggregates in addition to Granular A and O base materials.
R.W Tomlinson Ltd. scored a double in this year’s
awards by also winning the MTO’s Northeastern Region Award. Russ
Perry, manager of Tomlinson’s highway division reports that MTO
Contract 2004-5002 was valued at $7.94 million and included grading,
drainage, granular base, hot mix paving, temporary traffic signals and
structure rehabilitation. Tomlinson was subcontractor to Cruickshank
Construction Ltd. on this contract.
The work was located on Highway 35 between Minden
and Carnarvon, extending from 0.5 km north of Haliburton County Road
121N junction, northerly for 12.3 km to 0.3 km south of Highway 118.
Additional work was done on Highway 118 near Haliburton, from 0.7 km
west of Highway 121 extending westerly for 3 km.
The job began in September 2004 and was
completed a year later. Tomlinson’s successful team on this project
included Perry, asphalt foreman John Byrnes, asphalt plant foreman Mike
Dunphy and Bonnie Robertson on asphalt quality control. According to
Perry, the sourcing and supply of quality materials by Cruickshank played
a role in a successful project, notably imported asphalt sand from CBM
Aggregates’ Sunderland pit and “perfect” crushing
by Danford Construction. “Good pavement smoothness was achieved
by a combination of steady production and excellent materials, allowing
extremely high ERS (End Result Specification) results to be achieved”.
Perry reports that Tomlinson’s team dealt effectively
with extremely hot weather throughout the summer, as well as intense
rain storms that caused major washouts. To reduce traffic delays, particularly
for heavy weekend cottage traffic, road closures were limited to a maximum
of three closures per day with closures also subject to minimum spacing
and maximum lane length. Hot mix asphalt was supplied from a Gencor
400 UltraDrum Portable plant rated at 360 tonnes/h and located in the
Taylor pit near Madoc.
Tomlinson’s site paving train consisted
of the familiar Roadtec SB-2500B Shuttle Buggy feeding material to a
Caterpillar AP 1000B rubber-tired paver equipped with Topcon System
Five automatic controls and achieving an average paving production rate
of 200–300 tonnes/h. Compaction was achieved by a Bomag BW205
Breakdown compactor, Caterpillar PS 300B secondary compactor and a Caterpillar
CB534C finishing roller, with these units making two passes each to
achieve densities of 93.5 per cent. Some 45 000 tonnes of HL4 mix was
placed in all, utilising PGAC 58-34 from Bitumar (Hamilton) Inc., fine
aggregate from the CBM Aggregates Sunderland pit and coarse aggregate
from the Taylor pit.
Winner of this year’s Southwestern Region
Award was E. & E. Seegmiller Ltd. for quality work on Contract 2003–3019.
This two-year contract was located east of Sarnia on Highway 402, where
Seegmiller was asphalt subcontractor to the Bot Construction Group.
Road reconstruction work focussed on the eastbound lanes during year
one and the westbound lanes during year two, with detours providing
traffic free construction zones.
Seegmiller’s Les Coulas explains
that pavement reconstruction work included removal of all underlying
road base earth and clay subgrade in addition to existing asphalt and
concrete, making the job particularly weather sensitive while the clay
bed was exposed. This required careful materials delivery and staging
as site storage space was at a premium and the Granular A gravel for
the new road bed was shipped from London, 90 minutes away by truck.
Coulas adds that “having to schedule
trucking to receive aggregates continually through-out the job was a
headache while access to and from job site was limited with virtually
one-way traffic. Asphalt haulers also had to deal with increased
haul distances in the absence of an exit from the job site to Highway
402. On occasion, asphalt haulers had to reverse over 1km with traffic
restrictions.
With limited area for stockpiling and
continual haul in, extra care by Bryan Foulem, Seegmiller’s plant
foreman and AME Materials Engineering’s Jim Wright on Quality
Control helped to minimize any segregation of product stockpiles.”
Still on materials delivery, Coulas reports good work by Lafarge Canada’s
Ryan Wall and Jim Forbes of Ontario Trap Rock with respect to scheduling
of materials into Sarnia docks as well as the loading and off-loading
of all materials.
Hot mix asphalt quantities on the contract
totalled 116 000 tonnes, with 32 000 tonnes of Superpave 25 mm,
60,000 tonnes of Superpave 19 mm, 18 000 tonnes of Superpave 12.5 mm
FC (Friction Course) and 6000 tonnes of Superpave 12.5 mm. Coulas notes
that compaction of the 80 mm deep Superpave 25 mm base cover lift was
a challenge at first, with the challenge met by a novel rubber, steel,
rubber rolling pattern. A Bomag 20R pneumatic compactor was used
in the breakdown position, followed by a Bomag BW205 dual steel drum
unit steel unit making two vibratory passes and two static passes.
The mat was then finished by a second
visit by the 20R pneumatic unit. A similar approach was used to compact
the Superpave 19 mm mix where two 50 mm lifts were paved in echelon.
Here, 93 per cent densities were achieved by initial compaction with
the 20R rubber tired unit, followed by three vibratory passes plus one
static pass by the Bomag BW205 and final surface finishing with the
20R.
The 40 mm surface lift of Superpave 12.5
mm FC mix was paved in echelon, with cooler temperatures requiring vigilance
by Seegmiller paving foreman Rod Heimpel to achieve the required marking
and workmanship. Frequent checks were also made with quality control
personnel to ensure proper compaction was being maintained.
For this mix, Coulas utilised the three
vibratory, one static pattern for the Bomag BW205 that had proved successful
on the Superpave 19 mm mix. To complete the paving job, the Superpave
12.5 mm mix was paved in a 3 m wide mat to provide fully paved shoulders.
Coulas notes that this mat was somewhat easier to compact, thanks to
its narrower width and 40 mm depth, with required densities achieved
by two vibratory plus one static pass by the Bomag BW205.
The asphalt mixes utilised Performance
Grade Asphalt Cement (PGAC) from the Port McNichol depot of McAsphalt
Industries, while aggregates for the Superpave 25 mm, 19 mm and 12.5
mm mixes were supplied via Sarnia docks from Lafarge Canada’s
Manitoulin Quarry.
Aggregates for the Superpave 12.5 mm FC
mix included product from R.W. Tomlinson’s Ontario Trap Rock operation
at Bruce Mines, also shipped via Sarnia. Hot mix asphalt for the job
was produced by a portable CMI PVM 10X drum plant and paved by Caterpillar
AP1000B and Barber-Greene pavers fed from a Roadtec SB-2500 Shuttle
Buggy.
Back to
top
Asphalt
show breaks records
By Robert L.
Consedine, Editor
The
World of Asphalt 2006 Show and Conference set attendance and exhibit
space records during its run March 13-16 at the Orange County Convention
Center in Orlando, Florida.
More than 4,145 asphalt, highway and maintenance industry professionals
from over 50 countries attended the show, a 26 per cent increase compared
to the last event, held in 2004, and more than 250 per cent over the
attendance at the inaugural 2001 World of Asphalt. Among the attendees
were approximately 340 Canadians who made up the largest number of international
visitors at the show.
A record 6391 m2 of space was used by
221 exhibitors to showcase the latest equipment models, product innovations
and services. Show officials report that this is a 26 per cent increase
in the amount of space taken at the 2004 show. The five largest exhibitors
in terms of exhibit space were: Terex Roadbuilding (446 m2); Roadtec
(348 m2); Bomag (334 m2); Ingersoll Rand (278 m2) and, Astec Industries
(260 m2).
“More than numbers, this year’s
World of Asphalt had such positive energy and was truly an industry
gathering place where we could exchange experiences and learn from each
other,” noted R. Wayne Evans, World of Asphalt 2006 Chairman and
Senior Vice President of Business Development for Hubbard Construction
Company in Orlando, Florida.
“Attendees found all they needed
to keep up to speed on what’s happening in the asphalt industry
today – from the latest equipment on the show floor to the latest
trends discussed in the education sessions and live equipment demonstration
event,” he added.
The education sessions also set records,
with 4,185 tickets sold for the People, Plants and Paving Training Programs
and the Asphalt Paving Alliance’s (APA) Asphalt Paving Conference.
This represented a 62 per cent increase compared to the last show and
a 74 per cent gain compared to the first World of Asphalt educational
programming, in 2003.
The live equipment demonstration involved
a wide range of paving machinery that included milling machines, material
transfer vehicles, sweepers, asphalt sprayers, rubber tire and tracked
pavers, vibratory compactors and quality control testing systems. The
machinery operated across six lanes of the convention center’s
parking area and attendees got a close-up look at some of the real-life
problems associated with asphalt paving projects when several technical
glitches created some minor production bottlenecks during the event.
The next World of Asphalt will be held
March 19-22, 2007 in Atlanta, Georgia.
Back to
top
The
price of not knowing costs
As
more customers switch from prioritizing purchase price to life-cycle
costs, knowing how to calculate the total financial burden of operating
equipment is increasingly important. Volvo CE’s Dr. Govi Kannan
explains ‘cradle to the grave’ arithmetic.
Construction equipment is often the biggest
investment many operations make. But knowing quite how big an investment
is not always easy. If a study of construction equipment by Virginia
Tech in the U.S. is to be believed, then owners on average spent the
same on repairs during the life of their machines as they spent on the
initial purchase price. The problem is that many of these costs lie
obscurely hidden under a raft of operating cost variables.
Knowing the real cost of owning machines
is of interest to more people than just the company accountant. It can
also help answer such dilemmas as: ‘How should I pay for my machine
– savings or finance?’, ‘How long should I keep it?’,
‘What do I need to charge for it to make money?’, and: ‘What
should my maintenance strategy be?’
The fact is that having the optimal equipment
policy in place can play a significant part in determining profitability
and competitiveness – and yet few users of construction equipment
are sufficiently aware of their costs to do it effectively. It’s
easy to see why: equipment managers have to juggle lots of variables,
such as asset management, job costing, analysis of fleet performance
(age, cost, reliability), ownership period and economic decisions (repair,
replace, rebuild, retire), financing methods, preventative maintenance
programs and repair guidelines. Added to this, the only aspect of this
mix that is known with certainty is the purchase price. All other costs,
such as residual value, repair, maintenance and wear parts are, at best,
guesstimates.
Total
cost of ownership
As can be seen, working out all the costs
of a machine ‘from cradle to grave’ is not easy - but it
can be done. Likely costs in the future can be discounted back to give
a present value, so that units of work such as production per hour (tonne/hr
or m3/hr etc), cost per hour ($/hr etc) or unit cost ($/tonne etc) can
be calculated. Establishing the unit cost is especially useful as it
can compare dissimilar machines (gauging cost with output) – so
it can compare small loaders and small trucks against large loaders
and large haulers, etc.
The costs of a machine can be classified
as either ‘fixed’ or ‘variable’. Things like
purchase price, depreciation, and interest are fixed, as they arrive
when the machine is bought and vanish when it is sold. In-between these
two points you need to pay these costs regardless of whether the machine
is being used or not. On the other hand operating costs are those incurred
only when the machine is put to work (e.g. fuels, tires, wear parts,
repairs etc). Unfortunately, it is often only fixed costs, such as purchase
price that tend to be considered when deciding the type and brand of
machine to buy. But with equipment costing tens, and sometimes hundreds
of thousands of dollars, operating costs as well as fixed costs need
to play a part in the evaluation process.
It’s
good to guess
‘The way equipment is operated has
the largest impact of all on operating costs’
The only certain way to calculate the
hourly owning and operating cost of a machine is to wait until you have
sold it, add up all the money spent on it and divide by the hours worked.
However, it is better if you can estimate what the costs may be rather
than what has happened (and the money has been spent). Good estimating
requires the use of data, realistic assumptions as to what may happen,
and an understanding of the uncertainties involved. Fuel consumption,
tire wear and preventative maintenance can be estimated using modern
tools and techniques. You can use auction results to establish the fair
market value. Even repair costs can be estimated, on the basis that
they rise as the machine grows older and are a function of application
and environment.
The ideal ownership period is one based
on costs (ownership and operating) rather than physical condition. How
long you keep a machine should include a discussion on the likelihood
of component failure versus average lifespan. But one of the most important
factors is the role played by the operator. The way equipment is operated
has the largest impact of all on operating costs. How well an operator
uses the equipment is a function of knowledge and commitment –
do they know how to use the machine properly and are they motivated
enough to do so?
Preventative maintenance is an unalloyed
good, and should be seen as an investment rather than a cost. It acts
as ‘the eyes and ears in the field’ and helps avoid breakdowns.
The worse thing about breakdowns is the collateral damage it causes.
A $500 bearing can ruin a $7,000 transmission – and then there
is also the cost of lost production through the machine’s unplanned
downtime. It is hard to measure this collateral damage but its impact
is undoubtedly huge. When it comes to preventative maintenance: “If
it isn’t broken, don’t fix it” becomes “Change
it before it gets broken”!
The
calculation
Despite the fact that there are many variables,
when it comes to creating an actual calculation we find that we are
not ‘data poor’ but rather lack a structure of turning the
available data into the information we need. A lot of useful information
is captured by machines’ on-board computers and manufacturers
can also help provide the necessary data. By using a computer it becomes
easy to create a simple but very useful spread sheet.
It is important to collect data on ownership
and operating costs separately, and when creating the spreadsheet to
use well known categories (depreciation, fuel, insurance, tires etc).
Also, don’t always assume the ‘worst case scenario’,
as bidding for work on such a conservative basis may mean the resulting
costs leave you uncompetitive when tendering.
Here is an example of how to construct
a total cost of ownership spread sheet:
A
Purchase price (inc. options, delivery & set up costs). Often
these are the only cost known with certainty.
B Purchase price minus tires/tracks (best estimate).
Tires and tracks are operating costs and so should be removed from
the owning costs.
C Ownership period. The intended life of the machine
in the fleet is the period over which depreciation is divided. This
can be based on economic life or physical life, or a compromise of
the two.
D Residual value. The future market value of the
machine – discounted back to a present value. Here, trade magazines
and auction results can help to find a reasonable estimate of final
realizable value.
E Annual depreciation cost. This is calculated by
deducting the residual value from the purchase price and dividing
the remaining amount by the number of years the machine is to be kept.
F Interest rate – used to work out the cost
of capital. (Can vary depending on whether own funds are used or borrowings).
G Calculation of interest cost based on average annual
value.
H Machine tax, if any.
I Insurance costs (annual).
J Fuel cost (e.g. per litre/gallon). Assume the present
cost of fuel – as it can vary wildly over the lifetime of a
machine and is almost impossible to predict accurately. It can be
changed easily once the spreadsheet is created.
K Fuel consumption per hour. (Based on application,
environment, operator skill/commitment and machine design.)
L Preventative maintenance cost. (Including material,
labour, travel time and mileage.)
M Interval in hours (corresponding to cost as stated
in ‘L’).
N Tires/tracks (the cost of a complete set).
O Lifetime of tires/tracks for a given application
(in yrs).
P Repair cost for the intended life. (This is worked
out by setting up a separate spreadsheet showing all major components’
lifespan, parts and labour costs). The life of components and wear
parts typically depend on the environment, application and competence
of the operator. The rise in repair costs is the single most important
factor in determining how long to keep a machine.
Q Operator cost (on an annual basis). These can be
left out if only a machine cost is needed.
R Expected use in terms of working hours per year.
Once
the spread sheet is constructed, you can quickly see a variety of useful
information; such as real ownership costs per hour, real operating costs
per hour – as well as a total overall hourly cost for owning and
operating the machine. The sensitivity of individual variables can then
be identified, by adjusting the assumptions and noting the impact changes
have on costs (e.g. what happens if the price of fuel rises by $0.10
per litre?). By focusing on the elements that have the biggest impact
on results, and taking extra effort to ensure these figures are as accurate
as possible, users can make investment decisions with a good deal more
confidence.
Knowing the true cost of running a machine
allows customers to have the most appropriate fleet for their need,
bid more accurately for jobs and also choose their optimum point for
replacing equipment. It is possible to lift the shroud of uncertainty
regarding total cost of ownership and make the ambiguous seem –
if not quite crystal clear – then at least a lot less foggy.

Back
to top
What's
new in asphalt pavers
Spray
paver offers unique capabilities
Roadtec
has unveiled its latest innovation, the SP-200 asphalt spray paver.
The unit is a new paver which gives the contractor the ability to spray
asphalt cement or emulsion (tack) directly in front of the asphalt mix
before it is laid for NovaChip® applications or traditional paving.
NovaChip (sometimes called ultrathin HMAC wearing course application)
paving can be used on asphalt or concrete pavements as preventive maintenance
or as a surface rehabilitation treatment.
Equally useful in conventional, thicker-lift
paving, Roadtec says that the SP-200 spray paver solves the problem
of truck traffic on tack coats because the tack and hot mix are applied
in one operation by the paver. The SP-200 is claimed to perform equally
well in the construction of thicker lifts, and the spray function can
be switched off all together for jobs where no tack coat is needed.
The gravity-fed SP-200 has a heated 7949-litre
capacity asphalt cement/emulsion tank and three rows of spray nozzles
for delivering A/C or emulsion, giving it the largest tank capacity
of any spray paver available today. An onboard microprocessor controls
the rate of flow or it can be manually controlled. The SP-200 can be
equipped with an Eagle 10™ extendable 3.0 m screed as well as
any of the other available Roadtec® and Carlson® 3 m screeds.
|
Close-coupled
paving conept
Roadtec is promoting
close-coupled paving, a method of resurfacing roads which minimizes
the time that lanes are closed to traffic, is used by roadbuilders
to reduce inconvenience to motorists. Done correctly the process
also allows contractors to operate more profitably and results
in a better quality road.
Traditionally, lanes are closed before paving begins while milling
machines remove the old surface. Haul trucks are filled one by
one with the old pavement, which is trucked to an asphalt plant
to be recycled into new hot mix. When it is time for paving and
the job requires a tack coat, tack trucks come along and spray
a bonding agent onto the milled surface before the paver can begin
laying new mix. Then, another line of haul truck appears, this
time filled with hot mix asphalt. One by one they fill the paver’s
hopper and return back to the asphalt plant for refills. And usually
there are either too many trucks full of mix, meaning they have
to wait to empty, or there are not enough trucks and the paver
has to wait for mix. Meanwhile traffic is rerouted and restricted
longer than necessary, and trucks are utilized inefficiently.
It does not have to be that way.
Close-coupled paving offers an alternative. In ideal close-coupled
paving the paving train follows the milling machine, and haul
trucks do double duty; they bring hot mix to the paving operation
and carry off milled up pavement from the milling operation. Using
material transfer vehicles eliminates the line of trucks waiting
their turn to dump straight into a paver hopper. Material transfer
vehicles are used to provide a hot mix storage buffer at the paver
so trucks can unload and keep moving. Material transfer vehicles
not only reduce truck waiting, they also can also reduce the number
of trucks needed. And, owing to the material transfer vehicles
remixing action, a better quality mix is delivered to the paver.
With dump trucks and other construction vehicles manoeuvring in
front of the paver, tack coats sprayed ahead of pavers would soon
be damaged and get tracked all over the place by truck tires.
New pavers capable of spraying tack as part of the paving operation
remedy that situation.
Methods and material that will enhance close-coupled paving are
paving inlays instead of overlays, using interlocking stone mixes,
and quick-curing binders. When it is possible to mill the old
road surface leaving existing edges, and thus the possibility
of creating an inlay of new pavement, pavement quality will be
better because the new pavement is contained on both edges, giving
uniform density across the roadway. Moreover, mix made from rock
that is crushed in a way that creates angular, interlocking surfaces
will require much less roller compaction and the roadway can be
opened to traffic that much faster. |
Vögele
updates paver line
Within
the last year, Vögele America, Inc. has completely
updated its lineup of “lane-width” asphalt paver models
with product improvements, new model numbers, and external paint schemes.
The renewed line features two main-line
pavers, two commercial-class pavers, and one utility-class paver that
can double in commercial work. All of these models are built at the
company’s manufacturing facilities in Chambersburg, Pa.
These five models replace five existing
models, and are being introduced with improvements in reliability and
durability, new model nomenclature. and new paint scheme.
The lineup includes two 2.44 m rubber-tired
machines, the 2111W (replacing the 780 WB), and 2116W (replacing the
880 WB); and one 3 m rubber-tired machine, the 2219W (replacing the
1110 WB).
Rounding out the line are 2.43 m and 3
m rubber-tracked machines, the 2116T (replacing the 880 RTB), and 2219T
(replacing the 1110 RTB), respectively.
Vögele America’s prime commercial-class
models are the 2.43 m 2116W (replacing the 880 WB), and 2116T (replacing
the 880 RTB). The utility-class paver, the 2.44 m 2111W (replacing the
780 WB), can do double-duty as a commercial paver.
To ensure a longer and more reliable life
in the rubber track bands, Vögele America has beefed up the size
of the cables, increasing track strength by 50 per cent. Likewise, the
track frame was bolstered to enhance rigidity, longevity and alignment.
In addition, the drive motors are mounted
on the outside ends of the torque hub. Should a leak in a seal or hose
occur, it will be immediately detected before it has a chance to damage
the machine or ruin the asphalt mat.
Also, if a problem occurs, the unit can
be serviced without removal of the track.Vögele America telescoping
pre-strike-offs, on screeds with rear-mounted extensions, maintain flow
of material to the complete screed extension width, regardless of width.
This is unique to Vögele America.
Unlike the single drive motors used on
the final drives for most competitive pavers, Vögele employs two
hydraulic motors on the 2219T. The use of a single drive motor limits
other pavers to a two-speed hydraulic shift, or two-speed mechanical
shift. When a paver is shifted mechanically, the paver must be halted.
But for the 2219T final drive, all four shifts may be done hydraulically,
permitting smoother and more efficient shifting, including shift-on-the-fly
at any speed.
In addition to the paver tractor models,
four Vögele America-manufactured screeds were introduced in the
last year, including the first electric-heated screeds from Vögele
America. They are:
• HR500E, an electric-heat, 3 m main screed with hydraulic-extendable
rear-mount extensions.
• HR500D, a diesel-heat, 3 m main screed with hydraulic-extendable
rear-mount extensions.
• HF400E, an electric-heat, 2.44 m main screed with hydraulic-extendable
front-mount extensions, and the
• HR400D, a diesel-heat, 2.44 m main screed with hydraulic-extendable
rear-mount extensions.
Depending on the size of the screed mounted
on a paver, all models from Vögele America will pave 3 m wide sections.
Large doors allow instant ground-level access for all major serviceable
components, daily maintenance items, and check points.
New spreading
and auger design for RaodMix MTV
Terex/Cedarapids
has introduced a new generation Remix System for its CR662 RoadMix material
transfer vehicle (MTV). According to the manufacturer, the updated system
generates a more aggressive reblending of material, delivering a homogeneous
asphalt mix to the paver to virtually eliminate material and thermal
segregation.
Inside the CR662RM’s
receiving hopper, two sets of two counter-rotating auger assemblies
incorporate a constant 30 mm diameter shaft with variable-pitch flighting,
in which the pitch increases toward the rear of the hopper. This design
enables the augers to draw down material from directly above the entire
shaft length, resulting in a more uniform pull from all areas of the
hopper. The interleafing auger sets aggressively reblend material as
is moves from the hopper, through the feed tunnel and into the conveyor
system.
Positioned at or below
hopper wing level, the augers offer a three-inch slope downward from
front to rear, ensuring more efficient material flow and eliminating
material build-up in the feed tunnel. The larger, 305 mm diameter augers
provide 42 per cent more carrying capacity than 254 mm augers and turn
slower for reduced wear. Completely filling the hardened steel-lined
feed trough, the auger design minimizes material build-up, reduces wear
and facilitates clean-up.
Asphalt is immediately
channelled from the 15-tonne receiving hopper to the rear of the machine,
providing reduced handling time and virtually eliminating the temperature
losses common with other MTV designs. Material passes through a stationary
940 mm wide lift conveyor to a 762 mm wide swivel conveyor. This second
conveyor swings 55 degrees to the left or right of center and offers
a hydraulically variable discharge height from 1859 to 2942 mm.
A sonic sensor at the end of the swivel conveyor senses mix height in
the paver’s hopper and automatically stops and starts the hopper
augers and transfer conveyor system as needed.
The CR662RM RoadMix is
powered by a new 260 hp Cummins QSB6.7 diesel that features the latest
in emissions control technology. A single-width, triple-element radiator
efficiently cools engine water, charge air and hydraulic oil.
Equipped as an MTV, the
CR662RM meets all requirements for continuous, non-contact and off-set
paving. The machine’s rubber track drive system evenly distributes
RoadMix’s 24 495 kg over a larger area, resulting in a relatively
low ground contact pressure.
New
pavers deliver more power, few emissions
The new Terex/Cedarapids
CR500 Series mainline pavers from Terex Roadbuilding feature a new Cummins
diesel engine that boosts power ratings to 260 hp, while meeting stringent
Tier 3, C.A.R.B. Tier 3 and Stage IIIA emissions standards. The 6-cylinder,
24-valve engine varies the fuel stream to use only the amount of fuel
needed, resulting in a significantly quieter engine. Increased power
enables the new pavers to more efficiently handle full-width paving
applications and delivers the required power to keep electric screeds
at operating temperatures while working.
A significantly quieter
new cooling fan design boasts a deeper blade curvature for improved
air movement, so the engine and hydraulic systems run cooler. Air is
drawn from above the hood rather than ground level for cleaner air quality.
The system’s variable-speed fan runs only when necessary, further
reducing noise levels and fuel consumption. A single-width, triple-element
radiator efficiently cools engine water, charge air and hydraulic oil.
The CR500 Series consists
of the rubber tire CR552, rubber track CR562 and steel track CR562S
pavers. Base hopper capacity for these 3 m pavers is 15 tonnes. Available
hopper inserts provide up to a 22.7-tonne capacity, delivering the extra
surge necessary to effectively tackle mainline paving.
The CR552RX and CR562RX
Remix Anti-Segregation System pavers feature two sets of two counter-rotating
augers in the hopper to aggressively reblend material. The augers uniformly
draw down material from all areas of the hopper to reduce occurrences
of both particle and thermal segregation. This, claims the manufacturer,
leads to a more homogeneous texture and consistent temperatures across
the mat, allowing rollers to readily achieve final spec densities.
Volvo
launches new G900 motor grader range
Aggregates
& Roadbuilding Magazine was among the international construction
publications from nine countries invited to attend the global launch
of Volvo CE’s new G900 motor grader range in Goderich, Ontario.
All models in the new range were designed
from scratch and, according to Volvo Construction Equipment, their design
integrates field proven components such as Volvo engines and transmissions
with the results of extensive operator input. The G900 range is built
on two distinct but integrated platforms, with seven models designated
G930, G940, G946, G960, G976 and G990, including two all-wheel-drive
machines.
Graders are one of the most sophisticated
pieces of earth moving equipment and place unique engineering demands
on their designers. Versatile performance must combine heavy earthmoving
power with the precision to finely grade road pavements within strict
tolerances. Graders are also the traditional home of some of the most
senior, skilled and demanding equipment operators in the construction
business. Recognising this, Volvo hosted numerous “Voice of the
Customer” clinics where experienced operators were asked to comment
on and rank a number of grader attributes including visibility, “feel”
of the hydraulic controls, performance and operator comfort. The result
is said to be a grader that meets the requirements of customers and
users worldwide.
The four smaller models were engineered
with Volvo’s 7.2-litre D7E engine, while the three larger models
are equipped with Volvo’s 9.4-litre D9B engine. All models have
three-range engine power control, depending on the transmission gear
selected, as standard equipment. Both engines are EU Stage IIIA and
US Tier 3 compliant and utilise Volvo Advanced Combustion Technology
(V-ACT). These engines reportedly run cleanly without the service requirements
of additional equipment or after treatment of exhaust gases.
A grader’s transmission plays a
central role in the machine’s ability to transfer engine power
into useable traction and control across a wide range of operating duties
and speeds. G900 owners have the choice of Volvo’s HTE840 or optional
HTE1160 transmission. The HTE840 transmission has selectable manual,
autoshift (optional) and travel modes. In autoshift mode, the operator
selects the target gear and the transmission shifts automatically through
turns and grades as needed. In addition, the transmission’s shuttle
shift feature allowing shuttling between selected forward and reverse
gears in a single motion without clutching or pausing to reduce both
cycle times and operator fatigue. The HTE1160 transmission offers the
industry’s first 11-speed motor grader drive train and comes with
autoshift and travel mode as standard equipment. With its eleven forward
and six reverse speeds, the HTE1160 transmission offers more control
at low speeds, more efficient travel at high speeds and more precision
in normal working speeds.
The G900 range has two all wheel drive
models, the G946 and G976, with the latter described as the industry’s
largest all wheel drive grader. On both machines, the all wheel drive
system provides three drive systems in one, including four wheel tandem
drive, six wheel drive for traction and snow clearing, together with
Volvo’s exclusive front-wheel creep mode for exceptional fine-grading
control. The creep mode allows the operator to grade using only the
hydrostatic front-wheel drive, delivering smooth starts and stops while
the rear wheels roll freely behind to minimize scuffing and rework.
Company literature states that the G900’s
wide stance blade lift cylinders coupled with the low angle side shift
cylinder provides the most stable grading platform in the industry.
Proportional Demand Flow (PDF) intelligent load sensing hydraulics and
a powerful twin-gear, direct drive circle turn system result in a precise,
instantly responsive earthmoving tool. It also provides high strength
to hold or turn the mouldboard (blade) smoothly while moving under full
load. This accuracy of control and performance results in more “one
pass” finishes for improved productivity and cost saving. To extend
machine duty, available attachments for the new graders include a dozer
blade, front mounted scarifier, mid mounted scarifier, rear mounted
ripper/ scarifier and a front mounted push block.
For operators, expansive glass areas offer
exceptional visibility from the ground up, aided by six mirrors. Extensive
noise and vibration suppression, abundant filtered air, slide and tilt
adjustable centre pedestal, low effort pedals and short throw levers
are all designed to maximise operator comfort and productivity. Safety
features include illuminated steps and handholds as well as ground level
refuelling. There is no daily greasing or weekly servicing, as the standard
oil change interval on the G900 is 500 hours. Tandem and final drive
sight glasses provide fast level checks.
Volvo’s motor grader manufacturing
plant in Goderich is the sole source of the company’s grader line.
This plant is a vertically integrated operation that takes the product
from plate steel to finished machine under one roof in only eight working
days. The 32 000 m2 facility has over 650 employees, and has a steel
throughput of 13 600 tonnes annually with 2 700 parts on average per
grader.
Volvo Motor Graders is a division of Volvo
Construction Equipment (Volvo CE), itself part of the worldwide Volvo
Group. The Volvo Group is a publicly held company headquartered in Gothenburg,
Sweden with 2005 sales of $31 billion. Volvo’s business areas
include heavy trucks, buses, construction equipment, marine and industrial
drive systems, aerospace and financial services.
Back to
top
March/April
2006 issue
Aggregates
and Roadbuilding Magazine
4999 St Catherine Street West.
Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca
|