|
Canada's Rock to Road Magazine
November/December
2005 Issue
For a copy of the issue
that contains these articles with colour photos, click
here.
Anthony
Henday expressway section targets 2007 completion
By Andy Bateman, Engineering
Editor
According
to Alberta’s provincial government, traffic congestion in south
Edmonton will be significantly reduced by fall 2007, thanks to the construction
of the Anthony Henday Drive Southeast Leg Ring Road Project. The 11
km long project forms the southeast section of the Edmonton Ring road
and will connect Highway 2 to Highway 14/216. It incorporates six lanes
of highway between Highway 2 and 50th Street and four lanes between
50th Street and highway 14/216. It will also include twenty-four separate
bridge structures including five interchanges.
P3 promises savings
The project is Alberta’s first highway
Public Private Partnership (P3) project and will allow the road to be
built faster and sooner according to Dr. Lyle Oberg, Alberta’s
Infrastructure and Transportation Minister. In addition to earlier completion,
benefits of the P3 approach are said to include a road built to full
freeway specifications (with no stop lights) and fixed capital costs
with the province protected from inflation. The province will also be
insulated from risks such as weather delays, difficult ground conditions
and construction defects. In addition, the P3 set up will deliver a
road that will be built on time and on budget, with penalties for lateness
and responsibility for all cost overruns falling on the contractor.
There is also an extended warranty of 30 years on the work. Under the
project plan, the contractor pays for the design and construction of
the road. Once the road is open to traffic, the province will make predetermined
monthly payments to the contractor over 30 years to cover construction
costs as well as ongoing maintenance and operational costs.
Access Roads Edmonton Ltd. (AREL) was the successful
bidder chosen to design, finance, build and maintain this section of
the bypass in the 30-year deal worth an estimated $493 million in current
dollars. According to province, it would cost up to $497 million if
the same project were delivered through conventional means. In addition
the provincial spending on the project, the Government of Canada will
contribute up to $75 million through the Canada Strategic Infrastructure
Fund.
AREL is a consortium of companies from
Alberta’s engineering, roadbuilding and maintenance industries.
The AREL team includes: PCL Construction Management Inc.; PCL-Maxam,
A Joint Venture; Sureway Construction Management Ltd.; Lafarge Canada
Inc.; Marshall Macklin Monaghan; Stantec Consulting; Transportation
Systems Management Inc. and ABN AMRO Bank N.V.
PCL Construction Management Inc, a member of
the PCL family of companies, will manage all design and construction
related activities.
PCL-Maxam, a Joint Venture will be responsible for constructing the
bridges and overpasses on the project. Sureway Construction Management
Ltd. will complete the required earthworks, drainage and underground
utility works. Lafarge Canada Inc. will complete the surface works including
granular base, asphalt pavement, signage and lighting. Design services
will be provided primarily by Marshall Macklin Monaghan (MMM) and Stantec
Consulting as well as a number of specialized sub-consultants.
Operations, Maintenance and Rehabilitation will
be done by Transportation Systems Management Inc (TSMI), a subsidiary
of Lafarge Canada. TSMI was one of the first private companies to provide
highway maintenance services in Alberta. ABN AMRO is one of the world’s
largest financial institutions.
The Southeast Ring Road will be owned by the Province
of Alberta and it will become part of the provincial highway network.
Who
was Anthony Henday?
Born
on the Isle of Wight, U.K., Anthony Henday was a convicted smuggler
hired by the Hudson’s Bay Company to work as a labourer
at Fort York (York Factory), in what is now Manitoba. In 1754,
Henday answered a request from the governor of Fort York for volunteers
to travel to the western interior of the Company’s fur trading
domain. The purpose of the expedition was to convince distant
native trappers to bring their goods to Company posts on Hudson
Bay, thus deflecting business from French traders working in the
hinterland.
After a brief period of survey training, Henday
embarked on his journey on June 26, 1754. Guided by a group of
Cree who had come to Fort York to trade, Henday paddled up the
Saskatchewan River via the Hayes, and then continued along the
Battle River valley by foot. As he moved westward, he encountered
not only French traders at what is now The Pas, but also numerous
Assiniboine people. By fall, Henday and the Cree leader Conawapa,
along with their Cree companions, had reached a point just southeast
of present-day Red Deer. Here Henday became the first European
to record in writing an encounter with people the Cree called
“Archithinues” - presumably either Blackfoot or Atsina
(Gros Ventres).
The chief of the 200-lodge “Archithinue”
encampment, while courteous, was unimpressed with Henday’s
“sales pitch” for the Hudson’s Bay Company.
He responded unenthusiastically to Henday’s assurances that
those who came to Fort York with furs would be rewarded with good
powder, shot, cloth, and fine beads. The chief pointed out that
his people could not live without bison flesh, and did not wish
to make the dangerous journey east. After wintering near the “Archithinue”
camp, Henday returned to Fort York. In 1759, he again travelled
west in the hope of attracting the people of the plains to Fort
York. Again, he was unsuccessful.
Hudson’s Bay officials described Henday as “a
bold and good servant.” Perhaps because his trade missions
failed to achieve their primary goal, however, Henday did not
receive from the Company the recognition and rewards he felt his
journeys had earned him. In 1762, he left the Hudson’s Bay
Company, probably returning to England.
Source: Calgary & Southern Alberta / The Applied History
Research Group / The University of Calgary.
|
Back to
top
Self-Consolidating
Concrete facilitates roadway construction
By Andy Bateman,
Engineering Editor
Contractors
are successfully using a Self-Consolidating Concrete (SCC) and self
levelling concrete to pour high piers and other structural elements
on the Anthony Henday Drive Southeast Leg Ring Road (AHDSERR) Project.
The mix, Lafarge’s Agilia® Architectural,
reportedly contains no special chemical or other mix constituents. Rather,
its performance is said to be the result of careful mix design utilising,
among other things, 9 mm aggregates and fly ash. Aggregates &
Roadbuilding recently witnessed the mix in action on the AHDSERR Project
where a 13 m high pier was poured in a single pour from the top of the
forms. The pier is one of the supporting structures for a three level
overpass connecting Anthony Henday Drive westbound with Calgary Trail
southbound at the Gateway Boulevard interchange.
Stephen King, Design-Build Office Construction manager
for PCL Construction Management Inc., reports that the mix facilitates
construction in a number of ways. Site safety is aided by eliminating
any need for the concrete placing crew to go down into the forms to
consolidate (vibrate) the concrete. The mix is also said to save time
and therefore cost in both the pouring and finishing processes. Here
the pier was poured to its full height in one continuous pour of about
six hours, whereas a conventional high performance mix would require
three separate lifts across a three day period.
In terms of finish, completed piers showed a sound
finished surface that would require little patching. With a conventional
mix, a good initial finish would be hard to obtain in any case in a
form so heavily congested with reinforcement. In terms of direct material
cost, King reports a premium of 30-50 per cent per cubic metre over
conventional high performance mixes.
Lafarge personnel add that the cost premium is closer
to the 30 per cent mark when compared to higher performance mixes, with
the premium often off–set by savings in placing and finishing
costs. These savings include its reduced curing and protection allowing
bridges to be opened earlier. In addition, Agilia can be pumped from
wherever access allows in spite of the possibility of air void segregation
due to placing. A full compliance test is completed on every load to
prove the flow and air contents at the point of placement due to ISO
reporting requirements.
Back to
top
Asphalt
producers, roadbuilders feel oil, natural gas pain
By Andy Bateman,
Engineering Editor
Everyone
will be aware of the devastating impact of recent Hurricanes on the
Gulf Coast and their human and economic toll on the region. Fortunately
for the rest of us, only economic waves spread far beyond the Gulf,
largely the result of interrupted crude oil and natural gas production
as well as interrupted refining capacity. For the public, the most obvious
impact on a daily basis has been the price of gasoline, where the unheard
of $1.00 / litre, still a bargain by European standards, was broken
for the first time before subsequently falling back towards pre-hurricane
levels.
To get some idea of how changes in crude oil price
have affected Canada’s aggregates and roadbuilding industry, this
initial report looks at the impact on the production and use of hot
mix asphalt - the coated material of choice on some 95 per cent of the
country’s roads and a major end use of aggregates. For hot mix
producers and users, the recent ups and downs of oil and natural gas
markets have meant more time spent watching energy markets, buying materials
and controlling production costs.
Producers report that some of the bigger cost
increases flow from higher raw material costs at source, the delivery
of those raw materials, drying and heating costs, delivery to jobsite
and placement costs. For operators of natural gas fired stationary hot
mix asphalt plants, the prospect of more expensive gas is an additional
headache.
Roger Walls, a director of Red Deer-based Border Paving
Ltd., reports a big jump in energy cost at the Alberta company’s
hot mix asphalt plants, with drying and heating costs at natural gas
fired plants increasing by 57 per cent since April 2005. Plants fired
by Industrial Fuel Oil (IFO) have seen a more modest fuel cost increase,
with a 17 per cent increase in average 2005 prices compared to average
2004 prices. Walls adds that tight supply in 2004 may account for this
slower increase, noting that IFO prices increased by 30 per cent from
2003 to 2004.
Turning to asphalt cement, suppliers are offering
firm prices for 2006, enabling next year’s contracts to be bid
with known prices. Asphalt cement prices through 2005 have been relatively
flat. However, the province has had a poor summer weather-wise, and
some contractors, fortunately not including Border, may be faced with
carry over work and the completion of 2005 contracts work at 2006 asphalt
cement prices. In such situations, contractors may have to absorb asphalt
cement price increases ranging from $20 - $50/tonne next year, equivalent
to between $1.00 tonne and $2.70/tonne of mixture.
Adrian Van Niekerk, Chief Estimator for Etobicoke
On based Gazzola Paving Ltd., describes recent increases in the cost
of natural gas, diesel fuel and asphalt cement as the “Perfect
Storm of three with the contractor in the middle.” The impact
of these increases on Gazzola’s hot mix asphalt production costs
at a gas fired asphalt plant in the west Greater Toronto Area (GTA)
is summarised in Table 1.
Van Niekerk explains that it requires 8-10 m3 of gas
to produce each tonne of hot mix asphalt. In spring 2005, natural gas
was running at about $6.90 per gigajoule (GJ) at Alberta’s AECO
hub. Delivery cost to Ontario varies, but typically adds about $1.85/
GJ, giving a commodity delivered price of $8.75/ GJ. There are 26.53
m3 in one GJ, so this delivered price equates to about 33 cents per
cubic metre of gas. Based on 10 m3 gas consumption per tonne, the
gas cost per tonne in the spring was therefore about $3.30/tonne. With
gas as high as $13.00 per GJ, the same calculation yields a gas cost
of $5.60 / tonne, or an increase of $2.30/tonne in drying and heating
cost alone.
Turning to diesel fuel, Van Niekerk explains that
independent truckers apply a fuel surcharge linked to the rack price
of diesel and estimates that the increased cost of hauling aggregates
to the hot mix plant has added between 50 cents and $1.00 to the cost
of producing a tonne of hot mix asphalt. On top of that, it is costing
about 25 cents per tonne more to ship asphalt back out to jobsites,
for an overall diesel increase impact of about $1.25/tonne. For asphalt
cement, prices are currently running at about $290/tonne. Assuming 5
per cent asphalt cement in a mix, the binder cost is about $14.50/tonne
of hot mix asphalt.
With prices of $325/tonne on the horizon for spring
2006 or sooner, the cost for asphalt cement alone jumps by about $1.75/tonne
of hot mix asphalt.
The combined effect of these three cost components;
natural gas, diesel fuel and asphalt cement, is therefore adding about
$5.30 to the cost of producing each tonne of hot mix asphalt.
Who pays for this increased cost? In Van Niekerk’s
view, everybody pays in the long run. In the short term, the answer
depends on which producer’s customers are being supplied. For
MTO contracts and those municipalities that have price escalator mechanisms,
contractors can recover some of the asphalt cement and diesel fuel increase.
However, for supply to developers and private customers, where no such
mechanism exists, the producer/contractor has to absorb all of these
increases in existing contracts unless new rates can be negotiated.
The customer group most likely to bear the brunt of these price increases
are third party customers who buy direct from the plant as producers
seek to recover increased production costs.
Van Niekerk argues that the current 10 per cent thresholds
in the MTO asphalt cement cost recovery formula is out of date and does
not adequately protect the contractor when base prices are so much higher.
In the past, for instance 10 per cent of $200/tonne represented an increase
of $20, but with asphalt cement at $300/ tonne, the unit price has to
increase by $30/tonne before the 10 per cent threshold is exceeded,
requiring the producer to absorb an additional $10/ tonne of the increase.
One possible solution would be to reduce the threshold for asphalt cement
and diesel fuel price adjustments to perhaps 5 per cent.
For contractors, the buying of these essential
raw materials has become a strategic decision where, like many major
purchases, timing is everything. Some producers have elected to buy
natural gas at spot market prices, while others have locked into medium
or long term supply contracts to insulate themselves against future
price shocks. While nobody can predict the future with certainty, the
past can be a guide in this difficult process. Historical pricing charts,
for instance, clearly reflect the market’s response to weather
and other events in previous years, as well as the all too familiar
impact of 2005’s unforgettable Hurricane season.

GTA
aggregate delivery prices up sharply
As part of this focus report, Aggregates
& Roadbuilding has estimated the overall cost of increased diesel
fuel prices on the delivery of aggregates to the Greater Toronto Area
(GTA) as Canada’s biggest aggregate market. The GTA currently
consumes some 60 million tonnes of aggregates annually, of which over
half (56 per cent) is supplied from within the GTA and the balance (44
per cent) is imported from outside the GTA. The numbers in Table 2 indicate
that every 10 cents/ litre increase in the price of diesel fuel adds
nearly $11.5 million to the total delivery cost of this 60 million tonnes,
or an average of nearly 20 cents/tonne.
As high as these numbers might sound,
they are indicative of the supply situation only in the short tem and
likely to get higher still in the future. In “The Implications
of Restricting Aggregate Supply in the GTA” by Clayton Research
and MacNaughton, Hermsen, Britton Clarkson Planning Ltd., it was concluded
that “for every 3 tonnes of aggregate produced in the GTA in the
past 12 years, only 1 tonne of replacement supply was licensed. Based
on expected demand, existing licensed reserves in the GTA will be exhausted
within the next decade – and the impacts of scarcity are already
emerging. Additional reliance on imports to fill the supply gap is not
the answer. Over a 10-year period, additional imports to replace local
GTA production would consume 820 million litres of fossil fuel and generate
over 2.25 million tonnes of additional greenhouse gas emissions.
There would also be price implications for consumers as
transportation costs alone associated with importing more aggregates
to replace amounts produced in the GTA today would be about $4 billion
over a 10-year period. Base prices of aggregates would also be expected
to increase in response to product shortages and higher costs of developing
new supply areas.”
GTA
aggregate prices continue to climb
Discussions on hot mix asphalt production
costs would not be complete without looking at the price of aggregates
which typically make up about 95 per cent of an asphalt mixture. In
the GTA, major aggregate consumers report that prices have increased
significantly, with clear sized limestone aggregates typically increasing
by about $5.00/tonne ((FOB or ex-quarry) over the last five years. Gravel
aggregates have increased by about $4.00/tonne (FOB pit) over the same
period. Anecdotal evidence also indicates that that the price of premium
aggregates in the GTA has typically increased by about 50 per cent in
the last four to five years. Aside from these indicators, available
national data on aggregate pricing is scarce. In Ontario, the Aggregate
Producers’ Association of Ontario (APAO) collects pricing information
through its annual member survey, but the results of this survey are
available only to survey participants and even then only in a consolidated
regional format.
Editor’s Note: In the next issue, Aggregates
& Roadbuilding will present an overview of how high energy
costs are affecting aggregate producers across Canada.

How
are the provinces dealing with rising fuel price increases?
One method for dealing with changes in
the cost of materials on construction contracts is to apply a price
adjustment based on some form of monthly price indexing or escalator
formula. Aggregates & Roadbuilding contacted provincial transportation
agencies across the country to see how managers of public funds are
handling price jumps in two oil derived products - asphalt cement and
diesel fuel. Overall it was found that some agencies have escalator
clauses in construction contracts for both asphalt cement and diesel
fuel while others have clauses for one and some none at all.
In Ontario, contractors bidding on Ontario
Ministry of Transportation (MTO) contracts have the option to opt into
the payment adjustment based on changes in the MTO’s performance
grade asphalt cement price index. This index is based on the price,
excluding taxes, FOB from depots of the main suppliers in the Toronto
area for PG Grade 58-28 asphalt cement or equivalent. For contractors
who have opted to use the payment adjustment system, adjustments are
based on the PGAC price index for the month in which tenders were opened
for the contract. To calculate any adjustment, the tender opening index
is compared to the PGAC index for the month in which paving occurred.
For any adjustment to occur, the index for the paving month has to differ
from the tender opening index by at least 10 per cent. Where the 10
per cent threshold is exceeded, the contractor receives additional compensation
for the increase in excess of 10 per cent. Likewise, the owner receives
a rebate when the paving index is less than 90 per cent of the tender
opening index. The same PGAC price index is applied to all asphalt cement
grades. Most of Ontario’s asphalt cement is sourced from Toronto
depots with the exception of imports near provincial borders with Quebec
and Manitoba.
Paul Sosney, head of estimating in the
MTO’s Construction & Operations Branch, has compared laydown
prices for HMA for 2004 with the projected numbers for 2005 and estimates
that all HMA will be about 11 per cent more than 2004 in finished (laydown)
price. Of this increase, only about 2 per cent of the year over year
increase in laydown price is attributable to increases in asphalt cement
price. Sosney puts the year over year increase in asphalt cement price
from 2004 to 2005 at 6.8 per cent, with a similar increase expected
for 2006 over 2005. In Sosney’s view, price swings in asphalt
cement do not have a major impact on the laydown price of asphalt as
asphalt cement typically comprises only about 5 per cent of the asphalt
mixture. At least in Ontario, the increasing price of aggregates, the
energy required to produce asphalt and increased haulage costs are accounting
for most of the increases in laydown price.
For diesel fuel used on MTO contracts,
a payment adjustment mechanism is in place to adjust payments to contractors
based on the Ministry’s fuel cost adjustment index. The index
is based on the rack price, including taxes, of low sulphur diesel fuel
at terminals in the Toronto area and is also used by contractors to
calculate the flow through to truckers, subcontractors and other shippers
or suppliers. Monthly payment adjustments are based on changes in the
fuel price index, either positive or negative, and the estimated monthly
fuel consumption for specific types of work completed on a contract.
So how do increases in cost impact on
the current year’s roadbuilding budget? The MTO’s Noris
Bot, manager, Investment Planning and Programming, reports that a number
of options are available if more money is needed in the current year.
Firstly, the current year’s budget includes a buffer based on
historical costs. In addition, funds may also be available for transfer
from the mix of current ongoing and completed projects, although such
transfer is subject to controls. If additional funding is still necessary,
the MTO can make a special request to the Ministry of Public Infrastructure
Renewal.
In Manitoba, Lance Vigfusson, executive
director of Construction & Maintenance Engineering & Operations
Division, explains that Manitoba Transportation & Government Services
takes a different approach to many other provinces. Here, the agency
purchases asphalt cement and supplies it to contractors for a particular
contract. By purchasing the asphalt cement directly, Vigfusson explains,
the province removes the risk of price fluctuations from the contractor.
In doing so, the province believes that the province obtains better
value for money for its contract dollar as contractors do not have to
hedge (allow) for unexpected increases asphalt cement price when bidding
for work. Turning to diesel fuel, no escalator mechanism was in place
until price shocks this summer became a major issue. As a result, the
province has introduced fuel escalation measures for contract work from
October 2005 onwards. The escalation mechanism is based on consumption
rates for specific types of work such as hot mix placement or excavation.
Bill Pacholka, director of Materials and
Testing for Saskatchewan Highways and Transportation, reports that the
province has no price index mechanism for increased asphalt cement costs.
Like Manitoba, SHT purchases its own asphalt cement and thereby assumes
the risk for changes in rack price. Increase in asphalt cement price
have not had much impact on 2005 contracts, while diesel fuel increases
have been a contributory factor in a modest increase in contract prices.
The province is introducing measures to protect contractors against
increases in the price of diesel fuel in excess of 7 per cent by comparing
the month of consumption with the month of tender opening. Likewise,
the agency receives a rebate if diesel prices fall by more then the
7 per cent threshold. Pacholka adds that future year contracting budgets
are including above inflation increase in material cost which will have
an impact on the how far the province’s contracting budget dollar
will go.
Alan Maynard, director of Highway Maintenance
for Prince Edward Island Transportation and Public Works, reports that
a one off adjustment was made for truck haul only was made in 2005 subsequent
to the normal pre season negotiations for this and other rates. For
asphalt cement, an indexing mechanism is in place and is applicable
to material price on capital works. Maynard adds that asphalt cement
prices were volatile in 2004 but less so in 2005.
In Nova Scotia, Gerard Lee, operations analyst, Nova Scotia Department
of Transportation & Public Works, reports that the province has
no current diesel fuel indexing system for construction contracts, although
a 5 per cent across the board increase in truck haul rate was implemented
in July of this year in response to rising diesel costs. Since that
time, the province has tracked diesel prices and is reviewing the possibility
of introducing a fuel escalation clause for both truckers and contractors
on construction work. In addition, contractors have requested a price
escalation clause for asphalt cement. Under the existing system there
is provision for contractors to recover increases in asphalt cement
price for work that carries over from one construction season into another,
provided the delay in work completion was outside the contractor’s
control.
Chuck McMillan, director - Surface Engineering
and Aggregates with Alberta’s Infrastructure & Transportation,
reports that the agency is looking at potential escalation clauses for
asphalt cement and diesel fuel, with none in place at present. Historically,
the risk associated with price increases in these items has been considered
by their department to be relatively small and borne by the contractor.
That situation may have changed on some existing contracts, where for
instance, contractors may consume large volumes of diesel fuel on dirtmoving
contracts. Looking to next year, contractors are offering prices for
2006 and McMillan recognises that contractors may have hedged material and
fuel prices in these bids to protect themselves against weather related
or other factors.
Mike Oliver, chief, Geotechnical &
Materials Branch with the British Columbia Ministry of Transportation,
reports that the province has no index mechanism to deal with creasing
asphalt cement or fuel prices and does not have any plans to introduce
any indexing systems. Oliver adds, however, that the province will be
cutting back somewhat on this year’s budget at least in part from
the effects of increases in crude oil prices.
Terry Hughes, paving engineer with the
New Brunswick Department of Transportation, reports that the province
has adopted the payment adjustment mechanism for asphalt cement used
by the Ontario Ministry of Transportation (MTO), although New Brunswick
has no mechanism in place for diesel fuel. To make adjustments for asphalt
cement, reference is made to the asphalt price index posted on the MTO
and Ontario Hot Mix Producers Association (OHMPA) web sites, whereby
adjustment payments are made or recovered from the contractor based
on changes in the index in excess of a 10 per cent threshold.
Asphalt
Cement: refining, price and supply
In
“Refining 101”, Tom Day, general manager at Petro-Canada’s
Edmonton refinery describes crude oil as a mixture of hydrocarbons formed
from organic matter. Crude oil varies significantly in colour and composition,
with variations in composition including sulphur content, density, total
acid number, the contained sediments and water. Crude is classified
as light, medium or heavy according to its API gravity, a relative measure
of crude oil density. Crude is described as sweet if it has a sulphur
content of less than 0.7 per cent sulphur content and sour if the sulphur
content exceeds 0.7 per cent. High sulphur crude requires additional
processing to meet regulatory specifications. Acid content is measured
by total acid number (TAN). High acid crudes have a TAN in excess of
0.7 and acidic crudes are highly corrosive to refinery equipment.
Naturally occurring hydrocarbon molecules
do not meet customer needs, so the refining process must adjust the
molecules, reshape them and remove contaminants to ensure products meet
requirements for both end use and environmental performance. For instance,
Canadian market demand requires about 40-45 per cent gasoline while
a light crude may contain just 20-30 per cent gasoline. For heavy crudes,
the gasoline content may be even lower at 5-15 per cent gasoline.
Basic refinery operations include separation,
conversion and treatment/blending. At the conversion stage, the shape
or size of molecules are changed. Reshaping is utilised to improve product
quality while upgrading involves breaking larger molecules into smaller
molecules. During the treatment/ blending stage, on specification products
are produced by the removal of impurities and the mixing of components
to meet specifications.
For a refiner the two areas of safety
and reliability cannot be compromised. After that, economic optimization
is a series of trade-offs with refinery production considerations including
feedstocks, crude rate, products and operations. Feedstock factors include
the availability and cost of crude and the fit with refinery characteristics
such as refinery complexity, product flexibility and constraints. Crude
process rate should be maximised to spread fixed costs while the resulting
products should meet market demands and profitability goals. At the
operational level, the goal is to maximize yields from a given feedstock,
while minimizing giveaways (nil value product) and optimizing energy
use.
Husky
Lloydminster
As an example of how refining works in
practice, Husky Energy’s asphalt refinery and terminal in Lloydminster,
Alberta refines and produces over 30 different types and grades of road
asphalt, ranging from simple dust-laying road oils to asphalt used to
pave highways. Asphalt products are shipped to markets in Canada and
the United States for paving, or to be processed further into building
products. Crude oil for the Lloydminster Refinery comes from extensive
deposits of heavy oil in the region. The composition and properties
of crude oil vary greatly from one area to another, with crude from
the Lloydminster area being black in colour and viscous (slow to pour).
It contains materials such as water, sand, and a number of salts, including
magnesium, calcium, and sodium. It has a relatively high specific gravity
(one litre weights 970 grams in contrast to other crudes, which on average
weigh 850 grams per litre) and is known as “heavy oil”.
Based on 2004 volumes, the Lloydminster
refinery processes 4,250 m3/day (26,745 barrels/ day) of Lloydminster
blended crude. From this blend, more than half of the refinery’s
output (2,250 m3/day) consists of the asphalt for the paving industry.
After the asphalt has been removed the remainder of the crude emerges
as a series of semi-finished products: light distillate, kerosene distillate,
atmospheric gas oil, light vacuum gas oil, and heavy vacuum gas oil.
The light distillate is used as diluent to be mixed with the heavy crude
before it is transported via pipeline. The gas oils are sent to the
Husky Lloydminster Upgrader (HLU) to be processed into synthetic crude
oil. Husky currently does not produce finished gasoline or fuels at
the Lloydminster Refinery.
Trends
in asphalt cement price
Long term, Lyle Kajner, regional manager
asphalt, refined products for Husky Energy, expects the North American
asphalt cement market to tighten due to a number of factors. These include
consolidation within the asphalt refining industry, increased transportation
costs, and increased production of petroleum coke instead of asphalt
cement. Some larger integrated contractors have recognized the
coming supply trend and are seeking increased security of supply
through long term contracts and supply alliances. Kajner adds that a
refiner’s decision to produce asphalt cement is largely an economic
one, based on the difference between input costs (crude cost plus refining
costs) minus the revenue generated from the sale of light-end product
streams. Additional considerations include available production
capacity, available storage capacity, and the need to dovetail into
other integrated refining/logistical/marketing operations.
Ray Legault, president of Markham Ont.-based
Canadian Asphalt Industries Inc., points out that there are many factors
driving asphalt cement price such as refining capacity, supply, the
market place and the differentials between light and heavy crude oil
prices. Legault expects to see higher asphalt cement prices in 2006
but much less than we might have anticipated with crude prices up to
or above US$60/barrel.
Natural
Gas - North American Market overview
Natural gas is made up of hydrocarbon
gases, primarily methane. It is usually found deep below the earth’s
surface, often with deposits of oil, and is removed by wells that are
drilled to access the petroleum deposits. After it reaches the surface,
the gas is separated from any oil or water that may have been present
in the petroleum deposit. It is then processed to remove impurities,
other gases such as propane and butane, and any remaining water or water
vapour.
Natural gas accounts for almost a quarter
of United States energy consumption and the NYMEX Division natural gas
futures contract is widely used as a national benchmark price. The New
York Mercantile Exchange, Inc., (NYMEX) describes itself as the world’s
largest physical commodity futures exchange and the pre-eminent trading
forum for energy and precious metals. Future contracts on NYMEX are
traded in units of US$ per 10,000 million British thermal units, rather
than the Cdn$ per GJ. The price is based on the Henry Hub in Louisiana,
the hub of 16 pipeline systems that draw supplies from the Gulf Region’s
deposits. From here, markets are served throughout the US Gulf Coast,
East Coast and Midwest and up to the Canadian border.
Because of the recent rapid changes in
natural gas prices, a vigorous market has developed in the pricing relationships
between Henry Hub and other important natural gas market centres in
the continental US and Canada. These include Alberta’s AECO Hub™.
The AECO Hub™, EnCana’s commercial natural gas storage business
in Alberta is comprised of three gas storage facilities: Suffield (South-eastern
Alberta), Hythe (Northwest Alberta) and Countess (South-central Alberta).
EnCana is described as the largest independent natural gas producer
and the leading owner and operator of independent, non-utility natural
gas storage assets in North America.
Trends for natural gas price
Rising natural gas prices are nothing
new. Back in February 2004, the Calgary Herald’s Scott Haggett
noted, “After years as a low-value commodity, natural gas has
ascended into the spotlight as demand for the fuel to fire power plants,
heat homes and serve as a chemical feedstock outstrips the petroleum
industry’s ability to tap new reserves.”
George Eynon, Senior Director, Research
– Natural Gas for the Calgary based Canadian Energy Research Institute,
(CERI), provides an industry specialist’s recent viewpoint: “Natural
gas prices have virtually doubled in the last year while current prices
are about four times higher than four to five years ago. Prices are
following the basic demand supply relationship; demand has steadily
increased while supply has topped out or declined in recent months due
to Hurricanes Katrina and Rita. I don’t expect any big increase
in supply, with short-term supply levels at best recovering to their
pre-hurricane levels. Longer term, 5-7 years away at best, supplies
may come on stream from currently undeveloped sources such as the Arctic
but there are significant barriers. Huge capital investment would be
required to extract and transport gas from these remote sources in addition
to the complex regulatory process involved. The big question now is
whether or not demand will fall in response to the recent jumps in price.
I believe demand will remain strong despite the price hike.”
According to the Washington D.C. based
US Energy Information Administration (EIA), “the Mackenzie Delta,
located in the Northwest Territories, holds an estimated 9-10 Tcf of
recoverable natural gas reserves. Natural gas from the region could
begin flowing to southern markets by 2010, if natural gas companies
can complete the Mackenzie Gas Pipeline according to plan (see below).
There are three large, proven natural gas fields in the Mackenzie Delta:
Imperial Oil’s Taglua field with 3 Trillion cubic feet (Tcf) ConocoPhillips’
Parsons Lake field (1.8 Tcf), and the joint Shell Canada-ExxonMobil
Niglintgak field (1 Tcf). Nearly every Canadian natural gas company
has conducted exploration activities in the region.”
The EIA database also shows reports from
the Louisiana Office of Conservation on the current status of natural
gas production. As of October 28, the Office had received reports indicating
912 million cubic feet per day (MMcf/d) of onshore and offshore (in
State waters only) natural gas production has been restored, which is
40.8 per cent of total production before the hurricanes.
Still in the U.S., the Cambridge Energy
Research Associates (CERA), notes that: With September 2005’s
hurricane-related natural gas production shut-ins approaching 250 billion
cubic feet (BCF) – almost 7 per cent of the Gulf of Mexico’s
yearly production – and rising, the spotlight is on liquefied
natural gas (LNG) imports as the “supply of last resort”
for natural gas users during the coming winter heating season. Michael
Zenker, CERA analyst is quoted as stating that “The rising demand
for gas, coupled with flat production, has tripled prices in the last
four years. Relief should arrive then in the form of liquefied natural
gas, imported to alleviate shortages of the increasingly popular fuel.
Liquefied natural gas, or LNG – gas chilled to a liquid then shipped
in tankers like oil – will provide a breather, experts said. It
is expected to begin making an impact on the U.S. market as soon as
some of the 59 proposed LNG terminals are approved and come online.
That is expected no sooner than 2008.”
Back home, SaskEnergy, Saskatchewan’s
natural gas distribution company, illustrates how gas distributors are
playing catch up with rapidly increasing natural gas prices. On October
11, 2005 SaskEnergy revised its commodity rate request before the Saskatchewan
Rate Review Panel, in light of significantly increased market prices
for natural gas. This revised application was only a month or so after
its original application on September 9, 2005. “Since SaskEnergy
filed its original rate application, the natural gas market has felt
the full effect of two category five hurricanes, Katrina and Rita, which
have severely disrupted production in the North American natural gas
market,” Crown Management Board Minister Pat Atkinson said. “SaskEnergy
has to ask for a higher rate increase to reflect the cost it pays for
gas, which it passes on to customers at no mark-up or profit.”
Under the October 11, 2005 application, the commodity rate of $10.88
per GigaJoule (GJ) would be applied effective Nov. 1st, 2005. As a result,
General Service class customers (which include hot mix asphalt plants
and other industrial users) would see monthly bills increase by more
than 40 per cent. On October 24th 2005, the Saskatchewan Rate Review
Panel recommended approval of a lower commodity rate, but also left
room for the distributor to make application again January 1, 2006 with
this commodity rate if necessary.
How crude prices
affect asphalt cement, diesel fuel and natural gas?
One might expect the price of crude oil
and asphalt cement to be closely tied together. After all, asphalt
cement is a product of the crude oil refining process and was sometimes
regarded as a simple and convenient way to use residual material
from the refinery operation. In recent years, however, the relationship
between crude oil and asphalt cement price has weakened, with other
factors such as crude availability, refinery optimization, inventory,
production allocation, Superpave implementation and the supply/demand
relationship all impacting on refinery practice and asphalt cement
price. Like gasoline, diesel fuel prices are generally in step with
crude oil prices, although regional factors affect the price differential
between diesel fuel and gasoline. Perhaps surprisingly, there is
a close correlation between crude oil and natural gas price. According
to ENMAX Corporation, Alberta’s billion dollar energy company,
“natural gas is a North American commodity, so even if there
are no significant changes in supply or demand (in Alberta), Canadians
are affected by what happens in the North American market. The demand
for natural gas increases with economic growth and weather elements
such as tropical storms, hurricanes and cold weather. On the supply
side, the amount of natural gas available increases with oil rig
activity, oil well completions, and is affected by the production
rates of wells. Supply is also affected by the amount of gas transported,
weather patterns and long term capital investment.” |
Back to
top
November/December
2005 issue
Aggregates
and Roadbuilding Magazine
4999 St Catherine Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca
|