|
Canada's Rock to Road Magazine
March/April
2004 Issue
For a copy of the issue
that contains these articles with colour photos, click
here.
Mobile
crusher key to efficient concrete reclaiming
By Andy Bateman, Engineering
Editor
For one demolition contractor,
multiple stages of rebar removal and a track mounted crusher are key
components of a successful concrete reclaiming process.
One
of the main challenges in reclaiming concrete from a concrete structure
is the separation of the concrete from its embedded rebar. Effective
separation translates into steady output from concrete crushing plants,
uniform crushed product and maximum recovery of both concrete and steel.
Poor separation, on the other hand, can mean awkward manual work and
crushing delays while jammed rebar is removed, as well as potential
damage to rubber conveyor belting and other components.
Aggregates & Roadbuilding recently visited
the set up used by Priestly Demolition Inc. on a major job at Toronto's
Rexdale Mall, where the company's successful process incorporated rebar
removal and sorting at virtually every stage in a multi-stage reclaiming
process. Priestly's contract called for demolition of the entire concrete
structure, including a two-storey parking garage under the south end
of the mall. Reclaimed concrete was hauled to an on-site mobile crusher
for reduction into Granular B base aggregate, while the rebar was sold
for scrap.
Working space was tight, as the mall was still
partially occupied and a surface parking lot on the mall's east side
was still in public use. In the interests of public safety, the entire
concrete crushing process, including concrete feed stockpile, granular
product stockpile and a mobile crusher were all contained in a fenced
staging area at the east edge of the mall property. The resulting small
processing area necessitated frequent crusher moves to process the narrow
feed stockpile, while also limiting manoeuvring room for trucks delivering
feed material.
Down in the parking garage, three pieces of
equipment tackled the heavily reinforced concrete structure. A Komatsu
PC400LC excavator was on wrecking duty, utilising the extra reach provided
by its third member JRB shear, while a Komatsu PC300LC was fitted with
a grapple for cleaning and sorting material, including rebar. Behind
the PC400LC, a Link-Belt Quantum 8000 excavator, fitted with a pulverizer
attachment, was breaking the concrete of the collapsed slab into some
154 cm2 square pieces. Meanwhile, at the west side of the job, a Link-Belt
4300 excavator, fitted with a conventional excavator bucket, was loading
two Volvo A25C articulated dump trucks hauling pieces of previously
broken concrete to the staging area for crushing. On arrival there,
the A25Cs reversed up the steep feed stockpile and discharged in front
of another Komatsu PC400LC stationed on top of the pile. Fitted with
a pulverizer attachment, this PC400L provided further sorting and rebar
removal prior to crushing. Behind this machine, a Link-Belt 2800 Quantum
excavator was also positioned on the feed stockpile, within reach of
the mobile crusher's feed hopper. On this occasion, the 2800 was fitted
with a conventional 1.1 m3 bucket, although the bucket feeding the crusher
would normally be fitted with a thumb to provide yet another opportunity
for rebar sorting.
Priestly's mobile crusher was a track-mounted
Extec Mega-Bite 1100x700 mobile jaw crusher. During crusher operations,
two operators were stationed over the jaw feed to remove rebar by hand,
while a Master Magnets Ltd. overhead magnet on the plant's discharge
belt removed any residual rebar from the Granular B product stream.
At a 75 mm closed side setting, the jaw set was typical for a concrete
crushing application, reducing the 610 mm feed material to 100 mm minus.
Foreman Brian Priestly puts average plant throughput here at 800 tonnes/d,
adding that overall throughput rate varies considerably from contract
to contract depending on feed size and rebar content.
Now in its fourth year of service, this UK-built
plant has crushed nearly 500 000 tonnes for Priestly. The belt under
the jaw is a conventional rubber belt, and the fact that the belt has
reportedly lasted some 2.5 years without being torn or slit by rebar
underlines the effectiveness of Priestly's rebar removal process. In-house
refinements to the mobile crushing plant include the addition of aluminum
strips to the magnet's belt and the replacement of a steel plate near
the magnet with a (non-magnetic) stainless steel plate. The overhead
canopy, also an in-house addition, is removed for travel while the hinged
back and sides of the feeder are lowered.
Company president Ryan Priestly reports that
the jaw can be running within 2 hours of arriving on site and prepared
for travel in a similar time frame. Priestly adds that the crusher fits
well into job scheduling, "With this unit we can start crushing quickly
and crush material as it generated through the duration of the job.
This flexibility is useful on demolition sites as we are often working
in relatively tight locations. For instance, if we attempted to use
a larger crusher, we would then have to stockpile a large volume of
feed material in advance to make the crushing process efficient. As
a result, we would have a peak in our crushing schedule as well as increased
space requirements and increased material rehandling."
Manufacturer data states that Mega-Bite 1100
x 700 crusher is fitted with a horizontal grizzly feeder 4 m long by
1.1 m wide having two stepped grizzly sections. The feeder's rated capacity
is 120-360 tonnes/h. The jaw itself is a single toggle design with a
feed opening width of 1100 mm and a gape of 700 mm (44x28 in.). The
jaw has a minimum and maximum discharge setting of 70 mm and 200 mm,
respectively. Jaw product discharges onto a conventional rubber belt
1 m wide and 9.9 m long, operated by a hydraulic drive.
Other standard equipment on the Mega-Bite includes
a 3 m or 9 m long fines side conveyor, a dust suppression system, fully
remote control, hydraulic jacking legs, and a magnet. A 6-cylinder Deutz
diesel engine powers the plant. Ready for transport, the unit weighs
less than 50 tonnes, is 2.74 m wide excluding side conveyor, 4.06 m
high and 13.9 m long. If required, the crusher's radio control system
allows a single operator to both load and manoeuvre the crusher from
the feeding excavator. Manufacturer's literature also describes a UK
application where the crusher was teamed with one of the same manufacturer's
Robotrac track mounted screening plants to produce an integrated mobile
crushing and screening system.
Priestly Demolition Inc. is based in Aurora,
Ont. Since its founding in 1963, this family owned business now has
150 employees and an extensive equipment fleet that includes 40 excavators,
10 bulldozers and 20 skid steer loaders.
Back to
top
Recycling
- part of doing business for roadbuilder
By Andy Bateman,
Engineering Editor
The recycling
of both reclaimed asphalt pavement (RAP) and concrete has been an integral
part of one Toronto roadbuilder's business for many years. The latest
process refinement, a RAP fractionating plant, has delivered further
improvements and optimized the use of RAP in recycle asphalt mixes.
Gazzola
Paving Ltd. has been recycling materials since 1985, taking advantage
of the company's large Etobicoke yard to stockpile and process reclaimed
asphalt as well as concrete. Considerable quantities of recycled asphalt
and concrete material are processed annually. RAP is received either
as surface millings from resurfacing projects or in large broken pieces
from full depth road reconstruction projects. The larger material is
crushed and screened into graded material by area crushing contractors
for subsequent use as a raw material in recycle asphalt mixes or as
granular base aggregate. Of last year's RAP total, some 50 000 tonnes
was incorporated into recycle mixes by Gazzola's hot mix plant, 30 000
tonnes utilised as granular base aggregate and about 20 000 tonnes kept
in inventory. In parallel with the RAP operation, all reclaimed concrete
brought in from highway, sidewalk and demolition projects is crushed
and screened into granular base aggregate for use in commercial applications.
RAP recycling
Speakers
at the recent Ontario Hot Mix Producer's Association (OHMPA) asphalt
seminar noted that fractionating RAP into various sizes delivers a number
of benefits. These include improved control over both the asphalt cement
content and RAP aggregate gradation in recycle mixes, as well as the
ability to select the RAP fraction for the most economical mix. As one
speaker said, "Hot mix producers wouldn't think of combining all virgin
aggregates sizes into a single feed bin to feed a hot mix plant, but
many use a single bin for RAP". Gazzola is already there, having commissioned
a RAP fractionising plant and separate RAP feed bins at its hot mix
asphalt plant last year in time for the 2003 construction season. The
fractionating plant's job is to separate recycled asphalt feed material,
either surface millings or 19mm minus granular RAP, into three fractions;
19 x 9.5 mm, 9.5 x 4.75 mm and 4.75 mm minus. Any combination of these
fractions can then be fed to the 400 tonnes-h capacity Astec/Barber
Greene DM 71 combination drum/batch/coater plant via three RAP feed
bins.
Laboratory supervisor Solomon Andualem explains
that the fine RAP fraction contains the highest percentage of asphalt
cement, as the particles in this fraction have the highest surface area
originally coated with asphalt cement. After laboratory analysis to
confirm the asphalt content and gradation of each fraction, the RAP
is incorporated into a recycle mix design. For instance, a mix design
may originally specify a 5 per cent virgin asphalt cement content (50
kg/tonne) and 40 per cent virgin sand. The available RAP contains 5
per cent asphalt cement in its 4.75 mm minus fraction. If this RAP fraction
is utilised to replace half of the required sand, the fine aggregate
content of the resulting RAP mix will consist of 20 per cent RAP and
20 per cent virgin material. As a result, the RAP provides a 1 per cent
reduction in the amount of virgin asphalt cement required (20 per cent
of 5 per cent), as well as a 20 per cent reduction in the virgin sand
required.
With typical virgin asphalt cement costs of
about $300/tonne, the RAP use translates into asphalt cement savings
of about $3.00 per tonne of new hot mix asphalt, and up to $2.00 in
virgin sand savings. These savings in virgin material costs are offset
by the costs associated with hauling and processing RAP, but the overall
result is still a significant saving in hot mix raw material costs.
To further improve the efficiency of their
RAP operations, some users are storing RAP in open sheds, thereby keeping
its moisture content as low as possible. RAP's moisture absorption is
high compared to virgin aggregates as it consists of various particle
sizes cemented together by the original asphalt cement. According to
one OHMPA speaker, a 1 per cent increase in RAP moisture content increases
material drying costs by up to 13 per cent. Where stockpiles are exposed,
a large conical pile provides more effective drainage than long straight
or flattened piles. To some extent, exposed RAP piles are self-covering
as a surface crust forms over time. This crust can easily be broken
through with a loader or backhoe bucket to expose loose material when
required.
Concrete
recycling
Granular base aggregates produced from crushed
reclaimed concrete are popular with site crews as the fine cement fractions
already present in the concrete facilitate compaction into a dense base
with a smooth surface. At Gazzola's yard, crushing contractor Robert
Young Construction Ltd. was recently producing Granular A base from
a stockpile of reclaimed concrete containing slabby pieces up to 1.2
m wide and 450 mm thick. On top of the stockpile, a Daewoo 280LC-III
excavator sorted and loosened material, while a Caterpillar 950G wheel
loader baled the loosened material over the edge of the stockpile. From
there, it was fed to a Cedarapids crushing spread at a reported average
rate of 250 tonnes/h by a Caterpillar 980G.
Like all of Young's primary units, the Cedarapids
30x42 primary jaw was fitted with a custom designed telescopic tower
carrying a Breaker Technology Inc. boom and breaker system to deal with
jammed or bridged material. The jaw itself was run at a tight setting,
reducing material to 102 mm minus. From there, crusher run was transferred
onto the secondary plant feed conveyor, where any plastic, wood or other
waste material was removed manually and an Eriez magnet removed any
remaining rebar. Material arriving at the Cedarapids 855 secondary plant
discharged onto a small pre-screen where product already smaller than
25.4 mm was directed through side chutes to the spread's product conveyor.
Meanwhile, any larger material fell onto a grizzly that distributed
material between the upper and lower screen cloths on the secondary's
main 1.22 m x 4.27 m screen. Material larger than 64 mm retained on
the upper screen passed through a 12x42 jaw crusher, while material
larger than 25 mm (retained on the lower screen) was directed to a 3030
roll crusher. Material from both crushers was returned to the secondary
feed conveyor on a common return belt and elevating wheel for further
processing into finished product.
Back to
top
Camaro
Enterprises garners Ontario Paver of the Year Award
By Andy Bateman,
Engineering Editor
Excellent
roadbuilding was again recognised at the Annual Ontario Roadbuilders'
Association (ORBA) convention, held this year at the Fairmont Royal
York Hotel in Toronto on February 2-4, 2004. Award winners, including
the provincial Paver of the Year, received awards for their performance
on contracts in each of the Ontario Ministry of Transportation's five
regions.
Camaro Enterprises Ltd. has won the prestigious Ontario Paver of the
Year Award and Northwestern regional award for an outstanding performance
on its first Superpave job, MTO contract 2002-6012. Most of this $10.2
million contract was located on a 24.5 km stretch of Highway 17 east
of Dryden beginning on December 14, 2002 and completed by September
19, 2003. By all accounts the award was well earned, with a quality
job completed despite difficulties posed by severe winter weather, existing
pavement conditions and even utility pole locations. The extensive scope
on this job included two curve revisions, 137 607 m3 of earth excavation
and 46 243 m3 of rock excavation, while hot mix asphalt quantities included
41 872 tonnes of Superpave 12.5 mm mix and 36 024 tonnes of Superpave
19 mm mix. Additional quantities included 170 180 kg of granular sealing,
225 584 m2 of in-place full depth reclamation, 22 286 tonnes of partial
depth reclaim asphalt.
Vice president of operations Derek Walker explains
that the contract closed on September 18, 2002 with a September 19,
2003 (one year) completion date. Camaro had the necessary documents
in place and signed to begin work on October 30, 2002 but did not mobilize
as the frost was already setting in and daylight hours were limited.
As a result, the company had to complete aggregate crushing and begin
earth and rock excavation in very unfavourable conditions in order to
meet the completion deadline. Extremely cold winter weather made any
outside work very difficult. "Crushing of the bituminous materials and
granular occurred when temperatures dropped to a frigid Æ50ÁC. Several
crushing shifts were suspended due to crusher inoperability in the freezing
temperatures and equipment maintenance was especially difficult. Traffic
control was also a challenge, with personnel requiring breaks as frequently
as every 20 minutes due to wind chill. Finding personnel willing to
work in such conditions was difficult."
The cold winter turned to a cold spring, with
the result that Camaro was ditching in sub-zero temperatures throughout
March and April. This necessitated the use of heavy hydraulic excavators
such as John Deere 450 and Caterpillar 345 and 330 machines to complete
scratch ditching in the frost hardened ground. Most of the rock work
was also completed between February and April.
The cold weather also impacted on hot mix asphalt
production, as aggregates stockpiles at the asphalt plant were found
to contain layers of snow and frost. In response, it was decided to
excavate and re-stockpile the aggregates to ensure uniform feed for
the Superpave mixes, a process that also entailed the testing of stockpile
working faces several times a day. Fortunately, the summer was unusually
dry and no days were lost to rain between May and September, although
the resulting heavy summer tourist traffic did require careful handling.
A typical day saw six separate operations working on the 24-km section
of highway, necessitating precise co-ordination of traffic crews to
both minimize traffic delays and maintain productive truck cycle times.
Further difficulties were posed by hydro pole relocations. Walker explains,
"The utility relocates required for the contract were completed in the
2002 construction season. However, as blasting operations progressed
it was noted that several stretches of utility poles in the work area
were close to the planned rock faces in the blast areas. In some cases,
poles were within 2 m of the blasts, while others were actually inside
planned blast area. Poles were relocated where possible, with one rock
cut bypassed until July while waiting for pole relocation. In other
areas, where relocation was impossible, the blasts were kept small and
well controlled. However, the overall impact was reduced production
by the rock excavation crew and further scheduling conflicts in an already
tight schedule."
When in-place pulverizing began, Camaro and
subcontractor Hard Rock Pavement Recycling Inc. discovered that the
existing asphalt depths were as much as 300 mm thicker than stated in
the plans. Rather than the anticipated 100 mm of Granular A base underneath
the existing asphalt surface, Hard Rock encountered 200 mm minus cobble
material as well as granular material in the existing roadbed. Not surprisingly,
this oversize material and thick asphalt reduced the production rate
of Hard Rock's CMI RS-800 cold planer by 30- 50 per cent, an unanticipated
slow that meant rescheduling of the Granular A placement and asphalt
crews. To assist Hard Rock, Camaro cored ahead of the cold planer and
attempted to partially reclaim areas where excessive asphalt depths
were encountered, although there were still variations in asphalt depths
of 50Æ300 mm from centreline to shoulder. As a result, Camaro received
permission to apply a minimum of 100 mm of Granular A on top of the
reclaimed surface to provide an adequate base for the subsequent asphalt
lifts.
Walker attributes the overall success of the
project to excellent communication and teamwork between project superintendent
Jeff Tait, Thunder Bay Testing and Engineering (the consulting engineers)
and the contract's various supervisors and sub-contractors. "The numerous
challenges faced could have stopped work, had Camaro and its subcontractors
been unable to respond as quickly and efficiently as they did. All of
the operators and drivers on the project did an excellent job, especially
in the cold winter and spring months. A special mention goes to the
survey crews who were able to stay ahead of the operations, as well
as traffic control crews who kept traffic moving through the busy 24-km
section. The successful asphalt placement operation was due to excellent
communication and teamwork displayed by asphalt supervisor Darryl Boulanger,
laboratory supervisor Simone Haquoil, plant operator Greg Bucas and
screed operator Russ Carlson."
Turning to equipment, hot mix asphalt was produced
by Camaro's portable CMI UVM 1700 plant with a capacity of 320 tonnes/h.
Micro Motion controls added to the asphalt pump and belt on this hot
mix plant are said to provide AC delivery accuracy within 0.01 per cent.
On site, a Cedarapids CR551 RX Remix paver
achieved peak and average production rate of 380 tonnes/h and 270 tonnes/h,
respectively. Behind the paver, Camaro's compaction train included a
Caterpillar CB-634 dual steel drum breakdown roller making two passes.
A Dynapac CP-21 pneumatic roller in the secondary position made three
passes, while a Bomag BW164 AC-2 combination finishing roller was used
as required. Asphalt cement was supplied by
McAsphalt Industries Ltd.'s Thunder Bay terminal, while both fine and
coarse asphalt aggregates were sourced from the MTO pit, Dyment 48.
The same pit supplied over 200 000 tonnes of Granular A base material,
in addition to over 200 000 tonnes of Granular B base.
Project superintendent Jeff Tait concludes
with a few salient comments on the company's first experience with Superpave.
"The coarse texture of Superpave asphalt is conducive to heat retention.
This combination of heat and strength made paver stops and starts very
manageable as the screed did not sink and rise as noticeably as with
conventional mixes. On the down side, the coarse nature of Superpave
created excessive wear on the asphalt plant and paver. It was also found
that the Superpave mix responded best to compaction equipment at a road
temperature of 130ÁC, so we ran the roller train closer to the paver
than on conventional mixes." To that Walker adds, "The stringent criteria
in place for Superpave asphalt mean that consistent material production
is critical. Ideally, Superpave contracts would be tendered in a manner
that would allow paving to be completed during good spring and summer
weather and so avoid late fall paving."
Northeastern
Region
Miller Paving Northern won the MTO's Northeastern
regional award for quality roadbuilding on MTO Contract 2002-5115, a
Superpave contract that has the added distinction of incorporating the
MTO's cold temperature test site. The purpose of the test site is to
assess the cold weather performance of a number of different asphalts
and provide data for improved low temperature asphalt cement classification.
The overall contract was located on a stretch
of Highway 655 between Timmins and Cochrane, beginning 27.4 km south
of Highway 655's junction with Highway 11 and extended northerly for
13.4 km. Prime contractor M.J. LaBelle Company Ltd. was responsible
for construction, while Miller Paving was responsible for all of the
paving, acquisition of the modified asphalt cements, asphalt cement
transport, storage, hot mix production and the staging of the paving
work for the test sections. Asphalt quantities included over 15 000
tonnes of Superpave 19 mm binder course mix and over 12 500 tonnes of
Superpave 12.5 mm surface mix.
The test site itself included seven test sections,
each 500 m long and two lanes wide, with paved shoulders and curve widening
in some cases. A different manufacturer supplied the Performance Grade
Asphalt Cement (PGAC) for each section. A control section utilised unmodified
52-34 PGAC, while the other six utilised different modified asphalt
cements graded at 64-34, except one where a 58-34 PGAC was used. All
seven sections used the same job mix formula (for each lift) as the
rest of the contract.
Andy Desmarais, Miller's asphalt superintendent,
explains that one of the biggest challenges faced in the construction
of the test sections was learning how to handle the asphalt cement products
supplied by different manufacturers. "Each mix had its own characteristics
and mixing temperatures and reacted differently to production, placement,
and compaction procedures." In addition, Miller's quality control staff
faced the additional challenge of obtaining and testing an unusually
large number of samples for acceptance testing and research purposes.
Each test section was considered to be a lot with three sublots, with
a sample required from each sub-lot and from both binder and surface
courses. Under normal paving conditions, only one sample from each lift
would have been required for the equivalent area of each of test section.
The MTO also required no less than twenty samples from each test section
for research purposes, with ten samples taken from each course. To tackle
this massive sampling job, Miller constructed a trailer mounted sampling
bin that worked well and allowed all the samples to be taken without
any interruption to paving operations. Use of the sampling bin also
meant that samples could be collected without disturbing the freshly
placed mat, thereby eliminating the need for any handwork in the sampling
areas. Due to the complexity of scheduling and coordinating the delivery
of the different PGAC's to the hot mix plant, just two test sections
a day of one lift each could be paved. After each test section, any
binder remaining in the plant's AC storage tank had to be purged in
readiness for the next AC, some of which had arrived very cool after
a long haul in a small tanker. As a result, Miller had to heat jacket
all of the plumbing from the storage tank right to the tanker's off
loading hose, using the shortest hose possible. The weather did nothing
to make the AC delivery and construction scheduling task any easier,
with company records showing rain for at least 40 per cent of the contract
duration.
Equipment used on this project included the
company's Cedarapids 360 tonne/h capacity 8828 portable drum mix plant,
set up 3 km south of the contract. On site, a Roadtec SB 2500 Shuttle
Buggy fed material to a Cedarapids CR-451 paver and the sampling bin
as required. The CR-451 was fitted with Topcon System 4 automatic grade
and slope controls to facilitate placement to the required elevation
and cross fall. Miller's compaction fleet included a Bomag BW211D dual
steel drum vibratory compactor and two Caterpillar PS300B pneumatic
units. Asphalt superintendent Desmarais credits the uniform finished
pavement to the combination of a dedicated paving crew and the SB 2500.
Miller achieved full bonus for smoothness under the MTO's End Result
Specification (ERS) system, as well as bonuses for mix properties and
compaction.
Miller personnel also involved in this successful
contract included Eric Desbiens, general manager, Herb Villneff, senior
quality control manager, Shayne Toye, asphalt foreman, Al Pascoe, plant
foreman, Steve Lescom, portable plants manager and Britt Herd, chief
estimator. Credits also go to subcontractor M.J. Labelle for a key role
that included all earth excavation, granular grade raises and road widening
as well as aggregate crushing and supply. Miller Paving Northern is
a division of the Miller Group.
Southern
Region
Huron Construction Co. Ltd. won the Southwestern
Regional Award for its work on MTO contract 2003-3021 on Highway 401.
This $2.2 million resurfacing job on Highway 401's eastbound and westbound
lanes called for a Recycle Premium Dense Friction Course (DFC) mix to
be laid on a 13 km stretch, beginning 0.6 km west of Belle River Road
and extending east to 1.2 km west of Highway 77. Additional work included
rumble strips and granular sealing. The contract lasted just 35 working
days from July 21 to September 25 last year, including 4 days lost to
rain.
Contract manager/plan administrator Joe Doyle
reports that designing a Recycled Premium DFC Mix from the existing
Reclaimed Asphalt Pavement (RAP) proved to be a challenge. "We found
it difficult to obtain the necessary mix voids content utilising the
DFC RAP from this contract in the required 30 per cent recycle/70 per
cent virgin aggregates ratio. However, we were successful in designing
a mix with the somewhat lower recycle ratio of 20 per cent RAP. Once
on site, all the construction processes including milling the RAP, producing
the recycle mix, paving, painting and reopening to traffic were subject
to tight time constraints. Due to traffic volumes, we had to be off
the road by noon of Fridays so in practice we found it most effective
to work four long days." Doyle adds that contract specifications also
included a smoothness specification for the finished surface, although
the job consisted solely of the single 40 mm resurfacing lift.
The successful completion of this job is credited
to the hard work of everyone involved including administration staff,
shop mechanics, crushing crews, paving crews, lab crews, with special
mentions to assistant plan administrator William Snowdowne, contract
superintendent Andrew Lawrence and paving foreman Joe VanVaerenbergh.
Doyle highlights the role played by the traffic control crew, whose
constant adjustments to traffic control devices kept traffic moving
while maintaining safe construction zones. Additional credits go to
excellent communication, job planning and teamwork between subcontractors,
Delcan Consulting and Ministry staff.
On site, subcontractor Miller Paving Ltd. utilised
Wirtgen 2200, 2100 and 1000 milling machines to first remove the top
35 mm from the existing surface. The 29 106 tonnes of 20/80 DFC Premium
Mix required for the job was produced by Huron's 250 tonnes/h capacity
Boeing 200 drum mix plant utilising McAsphalt Industries Ltd.'s 64-28
PGAC combined with fine and coarse aggregates from Ontario Trap Rock
(R.W. Tomlinson Ltd.). Hot mix arriving on site was fed into a rental
Roadtec SB-2500B Shuttle Buggy that in turn discharged into a Cedarapids
CR451 Remix paver fitted with Topcon automatic screed control and a
non contact ski. Compaction equipment included a Caterpillar CB543C
breakdown roller, Caterpillar PS-360B pneumatic roller and Bomag BW161AD
finishing roller.
Huron Construction is part of the Miller Group.
Central Region
The MTO's Central Region award went to K. J.
Beamish Construction Co. Ltd. for quality workmanship on MTO contract
2002-3020. This contract, valued at $4,026,660, was located east of
Orillia on Highway 12 and County Rd. 44, extending from 0.5 km west
of Creighton St. easterly to 0.2 km east of Balsam Rd. and lasting from
April 22, 2003 to October 27, 2003. Beamish's Paul Hayward reports that
the contractor had to deal with high traffic volumes, as County Rd.
44 leads to the popular Casino Rama gambling complex. Contract conditions
stipulated that two lanes had to be maintained for through traffic at
all times, with all work done during daytime hours only. As a result,
it was decided to complete the job in stages, seven in all, necessitating
careful planning and cooperation by all involved. Hayward notes, "This
was a well run project that reflected a very good working relationship
between the contractor and the project administrator. A team approach
was the key to good co-operation between construction and quality control
personnel in keeping the project on schedule while maintaining good
quality standards at all times." The Beamish team included construction
manager Rick Geary, site superintendent Darryl McDonald, paving supervisor
Dave Fralick and QC plan administrator John Miller.
Hot mix asphalt for the job was supplied by
Beamish's Orillia plant, a Hetherington-Berner Model 50 batch plant
with a rated capacity of about 200 tonnes/h. Site paving equipment included
a Caterpillar AP- 1055B rubber-track paver fitted with an Extend-A-Mat
10-20B screed. The compaction train comprised a Caterpillar CB-534C
breakdown compactor, a Caterpillar PS-360 pneumatic unit and a Ferguson
steel drum finishing roller. Hayward adds that compaction was monitored
daily by the company's QC technician to maintain optimum rolling patterns,
with these efforts rewarded by nearly full End Result Specification
(ERS) bonus achieved for all mix lots.
The total hot mix asphalt tonnage on the contract
was 19 798 tonnes and included Medium Duty Binder Course (MDBC), HL4,
HL1, and temporary hot mix. PGAC 58-28 and PGAC 64-28 was supplied by
Canadian Asphalt Industries Inc., while fine aggregates were sourced
from Beamish's Midland Pit (sand and screenings) as well as manufactured
sand from the Carden Quarry of Markham Sand & Gravel, a division of
Miller Paving Ltd. Coarse aggregates for the MDBC and HL4 mixes were
supplied from Nelson Aggregates' Uhthoff Quarry while HL1 aggregates
were hauled over 150 km from Beamish's own approved source, Bark Lake
Quarry near Irondale. Beamish's Orillia Pit supplied all granular base
materials, totalling nearly 120 000 tonnes.
Eastern Region
R.W Tomlinson Ltd. won the MTO's Eastern Region
award for a successful job on MTO 2002-4003, Hwy #41, Bancroft District.
The job extended from Griffith northerly for 22.5 km to 0.6 km north
of the intersection of Hwy #132 at Dacre, beginning on August 1, 2002
and completed on Sept 26, 2003. In addition to grading, drainage, granular
base and hot mix paving, the scope of work also included structure rehabilitation
and an unusually large quantity of guide rail installation.
Weather conditions were challenging in fall
2002, with very wet and rainy conditions, coupled with early cold weather.
Fortunately conditions improved in 2003 with sunny and warm summer weather
that generated significant volumes of weekend cottage traffic on this
two lane highway. General manager Bert Hendriks points to good work
done by highway division manager Tom Smith, paving foreman Jodie Giesler
and plant foreman Mike Dunphy.
Hendricks also praises quality work by the
operating crews at both the hot mix plant and on site. "The asphalt
plant and crew produced quality bonus mix consistently while on site
the paving crew produced a quality mat." Hendriks adds that one of the
most difficult aspects of this contract was finding asphalt and base
aggregates of sufficient quantity and quality to complete the project.
In the event, these came from a number of sources. Coarse aggregates
for the 41 150 tonnes of HL4 hot mix asphalt were supplied by the MTO
pit at Dacre, Crozier's pit at Renfrew and Tom Smith's pit Foymount
pit. Asphalt sand came from the Ralph Selle pit at Douglas.
Granular A base materials, totalling nearly
110 000 tonnes, were supplied by Thomas Cavanagh Construction Ltd. (Granular
A) and the MTO pit at Dacre (Granular A and Granular B). Hot mix asphalt
was produced by the company's portable 360 tonnes/h Gencor Ultraplant,
while on site a Roadtec SB2500 Shuttle Buggy fed hot mix to a Caterpillar
AP-1000 rubber-tired paver fitted with Topcon grade controls at an average
rate of 225 tonnes/h. The Caterpillar compaction fleet included CB-634,
PS-300 and CB-534 units with each machine making three passes. Advance
surface preparation work at intersections was completed utilising a
Roadtec RX-60C cold planer.
|
Ontario
Paver of the Year Award

Left to
right: Ed Kalnins, Miller Paving Ltd., Northeastern Regional Award;
Paul Hayward, K. J. Beamish Construction Co. Ltd., Central Region
Award; Hon. Harinder Takhar, Minister of Transportation; Derek
Walker, Camaro Enterprises Ltd., Paver of the Year and Northwestern
Regional Award; Joe Doyle, Huron Construction Co. Ltd., Southwestern
Regional Award; Bert Hendriks, R.W Tomlinson Ltd., Eastern Regional
Award
|
Back to
top
Superpave
experience provides valuable insights
By Andy Bateman,
Engineering Editor
The
recent Ontario Hot Mix Producer's Association (OHMPA) annual asphalt
seminar featured three interrelated presentations on new developments
concerning Superpave implementation.
Paul Lum, director of new product commercialisation
and quality assurance at Lafarge Canada Inc., explained in his paper
"What mix designers have learned" that recent work included an
evaluation of current asphalt aggregates to assess their fit with Superpave
requirements. It was found, among other things, that the percentage
of crushed faces required was dependent on mix design based on the number
of gyrations and location of a mix in the pavement elevation. On the
issue of using local aggregate deposits for Superpave mixes, Lum explained
that local sources have been successfully used in the 50 and 75 (N design)
gyration Superpave mixes that are generally required for lower traffic
volumes. In locations subject to heavier loading however, 100 and 125
gyration Superpave mixes typically require washed screenings or manufactured
(crushed) sand to retain the necessary air voids in the mixture. Lum
added that this requirement does not represent a major change, as these
high gyration Superpave mixes are used in applications similar to the
MTO's existing Heavy Duty Binder Course (HDBC) and Dense Friction Course
(DFC) mixes which require 100 per cent manufactured fine aggregates.
According to Lum, there has been no difficulty
in introducing RAP into Superpave mixes.
Superpave mixes have been classified according
to the nominal maximum size (NMS) of the aggregate, where NMS is one
size larger than the first sieve to retain more than 10 per cent of
the sample. The asphalt cement (AC) content of Superpave mixes may be
determined from the Asphalt Institute manual SP2 which sets out AC content
for a particular mix classification.
Turning to equipment and testing, Lum stressed
the importance of gyratory compactor maintenance and calibration, noting
that sampling and sample handling, equipment calibration, equipment
maintenance, internal angle and mould wear can all cause variability
in test results between different gyratory compactors. A Dynamic Angle
Validator (DAV) can be utilised to calibrate the internal angle of gyratory
compactors and proper angle calibration will minimise variances in test
results caused by differences in internal mould angles between different
compactors. See sidebar, "The gyratory compactor angle issue".
Lum concluded by describing a situation in
which all calibrations and procedures, including internal angle, had
been confirmed for a gyratory compactor, but where a study still obtained
1.5 per cent higher air voids. Careful measurement revealed that the
internal diameter of a compactor mould had increased due to wear, with
the resultant increase in mould volume largely accounting for the variance
in test results.
Kai Tam, manager of the Bituminous Section
of the Ontario Ministry of Transportation (MTO) and Gary Moore, manager
of the design section at the City of Hamilton, described their respective
Superpave experiences on the theme "What Owners have learned".
Tam's "MTO 2003 Update on Superpave"
summarised early findings and challenges of Superpave implementation
and provided an overview of a related cold temperature trial. In 2002,
the MTO awarded 11 contracts with a combined total of 625 000 tonnes
of Superpave mixes, of which 106 000 tonnes was placed. These numbers
increased in 2003, with 16 contracts awarded (plus 1 negotiated) with
860 000 tonnes of Superpave mixes, with 1 million tonnes placed during
the year. Overall, 28 contracts with 1.5 million tonnes of Superpave
mixes have been awarded, of which 14 contracts have been completed with
others at various stages. All the province's major contractors now have
experience of dealing with Superpave mixes. Looking forward, Superpave
mixes will comprise 50 per cent of the total hot mix asphalt tonnage
in 2004 MTO contracts, while 2005 is targeted for full Superpave implementation.
Tam also described the MTO's Superpave certification
and training initiatives, its experience with two successful Superpave
projects, and a correlation program to compare test results between
laboratories. Participation in the correlation program is mandatory
for MTO contracts with about 30 labs participating. So far, the deviation
between test results has been much less than reported by some U. S.
agencies, possibly due to the use of newer gyratory compactors and less
diversity in compactor manufacturers. Ongoing challenges with respect
to Superpave mix testing include the frequency of referee testing (still
at a similar level to Marshall mixes) and mix checks that often show
different results for voids, VMA, and stripping. Tam reports that the
Best Practices Document (jointly produced by industry and the MTO),
is a refinement of AASHTO protocols and should help address these issues.
The now familiar issue of gyratory compactor internal angle is still
a challenge, and can vary due to several factors. In response, the MTO
has purchased a device to measure the internal angle of gyration and
measurements are just getting underway. Additional work over winter
2003 /2004 has included the analysis of 2003 construction data for compaction
and smoothness. Remaining issues and concerns include the realignment
of existing HL 4 mixes with Superpave 19.0 and 12.5 mm mixes, the absence
of minimum asphalt cement or stone contents for Superpave mixes, the
absence of a performance test and the relevance of non-End Result Specification
(ERS) Superpave attributes. In summary, the province's transition from
Marshall to Superpave has been successful, facilitated by partnering
through the Ontario Superpave Implementation Committee (OSIC), already
advanced aggregate and mix requirements as well as established testing
and design capabilities. For some mix designs, Superpave has brought
about the use of better mixes through the use of higher quality aggregates
to meet the requirements.
The MTO's cold temperature trial section was
completed in 2003 on a section of Highway 655 near Timmins. (For further
information see article in this issue on the Ontario Paver of the Year
Awards - Northeastern Region.) The trial utilised six types of binder
and should provide data for the development of an improved binder grading
method. Overall, the MTO is positive about Superpave implementation
and will continue with its implementation as planned. Superpave specifications
will continue to evolve, recognising the need for a performance test
and improved binder specifications based on the cold temperature study.
Moore's presentation described pavement management
for the City of Hamilton, which consists of 6 municipalities and 15
ward boundaries having a combined total of 6065 lane km. In terms of
road condition, most of the city's roads have a satisfactory rating.
To maintain the overall condition index (OCI) at its current level of
just under 70 would require $50 -$60 million annually, while the OCI
would decline steadily over the next ten years at an annual $30 million
allocation. Hamilton's experience with Superpave mixes indicates that
these mixes deliver added pavement life, increased service levels and
reduced maintenance costs.
Herb Villneff Sr., manager of quality control
for Miller Paving North Bay rounded out the Superpave presentation with
"What contractors have learned". With respect to aggregates, Villneff
noted that more attention will have to be paid to aggregate sources,
as some local aggregates may not meet the requirements needed for Superpave
mixes. For instance, some of the new tests that must be done on aggregates
for Superpave mixes, such as Fine Aggregate Angularity and the Sand
Equivalent test may prohibit the use of some of the local aggregates.
With respect to mix designs, Villneff noted
that because aggregates for Superpave mixes must meet Densification
and Volumetric specifications, it can take longer to obtain an acceptable
mix design. Contractors must now anticipate longer turnaround times
for mix designs and try and plan their operations accordingly, which
in some instances is very difficult to do given "open grade" and or
pulverizing restrictions. These restrictions can become extremely costly
to contractors if it becomes difficult to get an acceptable Superpave
mix design.
In terms of the production of Superpave mixes,
Villneff noted that no modifications are required to asphalt plants
to produce Superpave mixes and Villneff is not aware of anyone having
problem in producing Superpave mixes.
When it comes to site operations, Villneff
is also not aware of any problems with the placement of Superpave mixes
and, in fact, some paving crews prefer them; "These mixes stay where
you put them" In other words, Superpave mixes are not tender mixes.
That said, other paving crews have complained that it is difficult to
make an acceptable transverse joint with Superpave mixes. On compaction,
the final step in the paving process, Villneff notes that in most cases
the compaction of Superpave mixes has not been an issue, as long as
proper attention is given to Superpave's somewhat thicker lifts. In
those areas where compaction has been a problem, it has usually been
due to improper rolling procedures and/or improper roller operation,
coarse mixes or late fall paving.
Contractor's costs for quality control have
increased, due to the cost of new laboratory equipment such as the gyratory
compactor, additional training costs for laboratory and technician certification,
waiting times for large gyratory compactor samples to cool, as well
as the higher shipping costs incurred in sending large test samples
to QA laboratories. Alternative methods of sampling have had to be developed,
due to the larger sample sizes required for the testing of Superpave
mixes, Two of these methods are the sampling bin, used only if an MTV
is part of the paving train and auger sampling. Most contractors have
had very little difficulty in meeting the MTO's ERS requirements with
Superpave mixes and in practice some very good bonuses were achieved.
However, a large percentage of the same contractors who had received
bonuses under the MTO's ERS system for their Superpave mixes have also
been penalized significantly for non-ERS attributes such as Nini, VMA
and VFA. According to Villneff, there is a great deal of inconsistency
and confusion in the way Non-ERS attributes are administered between
the province's MTO Regions and even contract to contract. Villneff noted
that most, if not all, of the Municipalities that have used Superpave
mixes on their roadways are satisfied with the product they have received.
All that said, Villneff concluded that Superpave
mixes are the future of the hot mix industry, and as all parties concerned
gain knowledge and experience, these mixes can only improve.
Back
to top
March/April
2004 issue
Aggregates
and Roadbuilding Magazine
4999 St Catherine Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca
|