Value engineering pays off on roadbuilding contract

By Andy Bateman, Engineering Editor

    A value engineering proposal on an Ontario roadbuilding contract has saved more than 20 per cent in direct project costs, as well as slicing nearly a year off the contract schedule for the general contractor Aecon Construction and Materials Ltd.
     Ministry of Transportation of Ontario (MTO) contract 2002-4001 extends Highway 417 west of Ottawa, near the village of Antrim by 7.2 km from Regional Road 20 easterly to 1.6 km west of Panmure Rd. The job involves the construction of new four-lane highway and one intersection in an area of Leda clay, a natural deposit well known in the Ottawa area for its instability. For road engineers, Leda clay presents several challenges, not least of which are structural weakness, large settlements under load and extreme sensitivity to disturbance. Here, for instance, the estimated total settlement is projected to be as much as 1.2 m. Recognising these properties, the original design incorporated polystyrene and blast furnace slag as lightweight fill materials, together with vertical wick drains to facilitate drainage of the underlying clay soils. (See sidebar on Leda clay).
     After reviewing the original design, Aecon Construction and Materials Ltd. developed and submitted a change proposal in partnership with Ottawa based consulting engineers Urkkada Technology. Under the proposal, most of the expensive lightweight materials would be replaced by locally available rock borrow and the drainage process would be accelerated by additional wick drains together with a thicker surface drainage layer. Such proposals are encouraged by the MTO and allow identified cost savings to be shared equally between the ministry (as owner) and the contractor. The proposal was accepted, with the result that the quantity of polystyrene fill was reduced from 26 000 to 6 000 m3 while the quantity of lightweight blast furnace slag fill was reduced from 65 000 to just 2 000 tonnes. Quantities for rock borrow and Granular B surface drainage layer were increased accordingly, while wick drain quantities jumped from 37 800 to over 200 000 linear metres. Andrew Weltz, Aecon's project coordinator, reports that these changes are expected to result in both significant cost savings and earlier job completion. The job started in October 2002 and is now scheduled to wrap up in summer 2004, nearly twelve months ahead of its original summer 2005 completion date.
     On site, wick drain installation is concentrated near the new intersection of Highway 417 and Regional Road 20, with some of the wick drains here up to 35 m long. In section, individual wick drains consist of fibre wrapped plastic sections 102 mm x 6 m and were installed by mandrels mounted on Caterpillar 365 and Hitachi 550LC excavator units. Once the drains have penetrated through the surface crust, insertion into the underlying soft Leda clay is straightforward. The surface settles as the clay then dewaters, with the rate of settlement accelerated by the weight of fill materials, supplemented by the weight of some 60 000 tonnes of rock borrow, placed as a 2 m thick surcharge lift on bridge approaches and ramps. Once monitoring has confirmed the settlement process is complete, construction of the bridge structures will begin, with the bridge abutments, wing walls and piers founded on piles driven down to bedrock.
     Granular base materials and rock borrow for the contracts are being supplied from the Kinburn quarry of Ottawa-based Thomas Cavanagh Construction Ltd.
     Aecon Construction and Materials Ltd. is based in Brampton, Ont.

Leda Clay - the roadbuilder's challenge

    The Ottawa area is known for its weak, sensitive and compressible marine clay soils. These clay deposits were originally laid down after the last glaciation, when the Champlain Sea flooded the area and then eventually receded as the land rebounded. Sediments from the Champlain Sea created clay plains including areas of 'Leda' clay. In some locations the resulting clay beds are up to 70 metres thick, with innumerable small tracts of shallower clay elsewhere. These are marine clays from which the salt has been leached, and their very high values for sensitivity (comparing undisturbed to remoulded strength) indicates a potentially severe loss of strength if disturbed. Design challenges associated with the sensitivity of Leda clay include, among others, limitations on embankment heights to address settlement and stability, difficult handling, grading, excavation and disposal operations, limitation on cut depths, extreme frost susceptibility and induced long term settlements resulting from dewatering. A number of major failures in the past are attributable to Leda clay.
     As recently as 1993, an area some 50 km east of Ottawa, failed and slid into the South Nation River. Settlement of older buildings and highway embankments is also evident in the area. On previous road construction projects, such as Highway 416, large settlements due to compression of clay subsoils was a major design consideration in areas of high bridge approach fills, resulting in innovative construction techniques such as lightweight fill materials to reduce the magnitude of settlements and vertical wick drains to accelerate the rate of settlement. Wick drains provide a route by which water can escape upwards from the loaded clay. On reaching the surface, this water can be contained within a drainage layer and directed to the site's surface drainage system. "Freeway Construction Techniques in Areas of Sensitive Clay Soils - Highway 416 Case Study," by Darwyn G. Sproule; P. Eng and Brent Loken; P. Eng, both of the MTO. Paper prepared for presentation at the 1998 Annual Conference of the Transportation Association of Canada.

Back to top


Loader demonstrates value of strict maintenance in tough quarry application

By Andy Bateman, Engineering Editor

An aggregate producer's approach to maintenance delivers long equipment service life in tough applications.

    Primary load and carry in a quarry is one of the most arduous duties for a wheeled loader and its operator. The machine is repeatedly digging into unsorted shot rock and then travelling loaded for some distance, often over uneven surfaces and in dusty or wet conditions. Some owners do not expect long machine life in this application, while others believe that a well-maintained machine, in the hands of a good operator, can deliver extended service life even in these punishing conditions. Aggregates and Roadbuilding recently visited the Burlington quarry of Nelson Aggregates where two loaders owned by crushing contractor Trent Valley Sand and Stone Ltd. were loading and hauling shot rock to a portable crushing spread.
     At first glance the loaders, both Komatsu WA600's, appeared to be of similar vintage, but in fact nearly fifteen years separated their respective delivery dates. Trent Valley purchased the older machine, a WA600-1, in March 1988 while the company's WA600-3LK was purchased just last year. The WA600-1 was fitted with a Komatsu 5.73 m3 bucket and the WA600 3LK was fitted with a Hensley 6.87 m3 bucket.
     Trent Valley's Peter Lloyd reports that the WA600-1 has been on primary load and carry duty for most of its service life, now 15,000 hours and counting, and has delivered 100 per cent operating availability to date. All routine maintenance on this loader has been completed in-house, including engine oil changes every 200-250 hours and transmission oil changes every 500 hours. Under the hood, the engine looked dry with no visible leaks and appeared clean burning when running, with minimal visible emissions even under heavy load. Still on routine maintenance, Lloyd reports that the oil in the loader's front and rear differentials is changed every 1000 hours rather than the specified interval of 2000 hours in recognition of the constant travelling inherent in load and carry duty.
     Lloyd also underlines the importance keeping the loader's radiator clean for efficient cooling and gives the radiator on this unit a full pressure wash every two weeks to remove any dust build up. Preventive maintenance measures, completed after 9000 hours, included an engine bearing roll-in and head overhaul, as well as flushing of the transmission cooler and resealing of the hydraulic pumps. The bearings on the original alternator, still going strong, were replaced last winter. The loader was repainted five years ago and is now on its second set of tires.
     As Lloyd says, "Not everyone will agree with the way we look after our machines, but we believe our approach pays off in the long run. With proper maintenance, the older loader should continue in service for some time. Not only that, when the time does come to replace it, we should realise its maximum resale value."
    Trent Valley Sand and Stone Ltd. is based in Scarborough, Ont.

Back to top

2004 Buyers' Guide issue

Aggregates and Roadbuilding Magazine
4999 St Catherine Street West. Suite 315
Westmount, Quebec H3Z 1T3
Tel: (514) 487-9868 Fax: (514) 487-9276
EMail: rocktoroad@sympatico.ca